CAPM Practice Exam 150 Questions & answers 2026

Document preview thumbnail
Vista previa 2 fuera de 11 páginas

1. The process of establishing clear and achievable objectives, measuring their achievement, and adjusting performance in accordance with the results of the measurement is called: - correct answersManagement by Objectives 2. During the full life cycle of the project, a plot of the project's expected expenditures will usually follow a characteristic S curve. This indicates that: - correct answersThe bulk of the project budget will be spent in the execution phase 3. In which project lifecycle phase would you expect to have the greatest influence on overall project cost? - correct answersConcept 4. Requirement is - - correct answersQuantified and documented needs of stakeholders, customer, and sponsor 5. TQM is - - correct answersTotal Quality Management: A common approach to implementing a quality improvement program 6. Which describes Management Information Systems? - correct answersSoftware that an enterprise uses to support business and administrative operations 7. The type of planning that is equated with more specific data or is detailed in nature is called: - correct answersTactical 8. What are the different types of costs in Microsoft Project? - correct answersFixed Cost, Cost Per Use, Standard Cost, Overtime Cost 9. What is the name of PMI's Organization maturity model for project management? - correct answersOPM3 11. A group of related projects that are managed in a coordinated way that usually includes an element of ongoing activity is called a: - correct answersProgram 12. Project constraint could be on - - correct answersCost, resources, schedule 13. What is true about Project Management Office (PMO)? - correct answersSupport Project Managers by coaching and mentoring PMO is a project stakeholder PMO can terminate projects if required to keep business objectives consistent 14. Projects require project management while operations require business process management or operations management. Projects can intersect with operations at various points during the product lifecycle. Which of the following is not a stage to represent this? - correct answersAt each Executing phase

Vista previa del contenido

CAPM Practice Exam 150 Questions &
answers 2026
1. The process of establishing clear and achievable objectives, measuring their achievement, and
adjusting performance in accordance with the results of the measurement is called: - correct
answersManagement by Objectives

2. During the full life cycle of the project, a plot of the project's expected expenditures will usually follow
a characteristic S curve. This indicates that: - correct answersThe bulk of the project budget will be spent
in the execution phase

3. In which project lifecycle phase would you expect to have the greatest influence on overall project
cost? - correct answersConcept

4. Requirement is - - correct answersQuantified and documented needs of stakeholders, customer, and
sponsor

5. TQM is - - correct answersTotal Quality Management: A common approach to implementing a quality
improvement program

6. Which describes Management Information Systems? - correct answersSoftware that an enterprise
uses to support business and administrative operations

7. The type of planning that is equated with more specific data or is detailed in nature is called: - correct
answersTactical

8. What are the different types of costs in Microsoft Project? - correct answersFixed Cost, Cost Per Use,
Standard Cost, Overtime Cost

9. What is the name of PMI's Organization maturity model for project management? - correct
answersOPM3

11. A group of related projects that are managed in a coordinated way that usually includes an element
of ongoing activity is called a: - correct answersProgram

12. Project constraint could be on - - correct answersCost, resources, schedule

13. What is true about Project Management Office (PMO)? - correct answersSupport Project Managers
by coaching and mentoring
PMO is a project stakeholder
PMO can terminate projects if required to keep business objectives consistent

14. Projects require project management while operations require business process management or
operations management. Projects can intersect with operations at various points during the product
lifecycle. Which of the following is not a stage to represent this? - correct answersAt each Executing
phase

, 15. Enterprise environmental factors refer to both internal and external environmental factor that
surround or influence a project's success. Of the following, which is NOT an enterprise environmental
factor : - correct answersHistorical data

16. A person who is involved in or may be affected by the activities or anyone who has something to
gain or lose by the activity of the project is called a: - correct answersStakeholder

17. Large projects may be divided into smaller, more manageable components known as, - correct
answerssubprojects

18. A manager who manages a group of related projects is called a - - correct answersProgram manager

19. Which activity is conducted last as part of closing process group - correct answersCustomer
satisfaction survey

20. In the PMBOK, each process is broken into - - correct answersInputs and Outputs
Tools and techniques

21. A stakeholder has the greatest ability to influence a project during - - correct answersInitiation and
Planning

22. A Project Manager should support making changes during Execution - - correct answersWhen they
are warranted and inline with the strategic goals of the organization

23. Conducting Lessons Learned is a critical part of - - correct answersClosing

24. Which is not a process from the Planning Process Group? - correct answersPerform Quality
Assurance

25. The Change Management Plan should be included in which of the following? - correct
answersProject Management Plan

26. Who is a Project Initiator? - correct answersA person or organization that has the ability and
authority to start the project

27. Who does the Project Integration? - correct answersProject Manager

28. Which of the following is true about Project Plan ? - correct answersProject Plan needs to have the
buy in of the entire project team

29. Which of the following statements is MOST True? - correct answersThe project charter names and
authorizes the project manager

32. The project is characterized by frequent changes to the project charter. Authorizing project charter
changes should typically be the responsibility of __________ - correct answersSenior management

Información del documento

Subido en
21 de octubre de 2026
Número de páginas
11
Escrito en
2026/2027
Tipo
Examen
Contiene
Preguntas y respuestas
$7.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Vendido
0
Seguidores
0
Artículos
176
Última venta
-



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes