WGU D670 TASK 1
COMPLETE QUESTION SET WITH VERIFIED
SOLUTIONS GRADED A+
Question 1.
Plan Resource Management, Outputs
ANSWER
Resource Management Plan, Team charter, Project document updates
Question 2.
Control Quality, Tools & Techniques
ANSWER
Data gathering, Data analysis, Inspection,
Testing/product evaluations, Data representation, Meetings
Question 3.
Perform Qualitative Risk Analysis, Outputs
ANSWER
Project documents updates
Question 4.
Monitor Stakeholder engagement, Inputs (stk)
ANSWER
Project Management Plan, Project documents, Work performance data, EEFs, OPAs (stk)
Question 5.
Create WBS, Tools & Techniques
ANSWER
Expert judgement, Decomposition
,Question 6.
Control Quality, Inputs
ANSWER
Project Management Plan, Project documents, Approved change requests, Deliverables, Work
performance data, EEFs, OPAs
Question 7.
Estimate Activity Resources, Outputs
ANSWER
Resource requirements, Basis of estimates, Resource breakdown structure, Project document
updates
Question 8.
Plan Cost Management, Inputs
ANSWER
Project Charter, Project Management Plan, EEFs, OPAs
Question 9.
Manage Project Knowledge, Outputs
ANSWER
Lessons learned register, PM plan updates, and org. process assets updates
Question 10.
Determine Budget, Tools & Techniques
ANSWER
Expert judgement, Cost aggregation, Data analysis, Historical information review, Funding limit
reconciliation, Financing
, Question 11.
Control Costs, Outputs
ANSWER
Work performance information, Cost forecasts, Change requests, Project Management Plan
updates, Project document updates
Question 12.
Develop Schedule, Outputs
ANSWER
Schedule baseline, project schedule, schedule data, project calendars, change requests, PM
plan updates, project document updates
Question 13.
Perform Qualitative Risk Analysis, Inputs (ql)
ANSWER
Project Management Plan, Project documents, EEFs, OPAs (ql)
Question 14.
Develop Schedule, Tools & Techniques
ANSWER
Schedule network analysis
Critical path method
Resource optimization techniques
Data Analysis
Leads and lags
Schedule compression
PMIS
Agile release planning
COMPLETE QUESTION SET WITH VERIFIED
SOLUTIONS GRADED A+
Question 1.
Plan Resource Management, Outputs
ANSWER
Resource Management Plan, Team charter, Project document updates
Question 2.
Control Quality, Tools & Techniques
ANSWER
Data gathering, Data analysis, Inspection,
Testing/product evaluations, Data representation, Meetings
Question 3.
Perform Qualitative Risk Analysis, Outputs
ANSWER
Project documents updates
Question 4.
Monitor Stakeholder engagement, Inputs (stk)
ANSWER
Project Management Plan, Project documents, Work performance data, EEFs, OPAs (stk)
Question 5.
Create WBS, Tools & Techniques
ANSWER
Expert judgement, Decomposition
,Question 6.
Control Quality, Inputs
ANSWER
Project Management Plan, Project documents, Approved change requests, Deliverables, Work
performance data, EEFs, OPAs
Question 7.
Estimate Activity Resources, Outputs
ANSWER
Resource requirements, Basis of estimates, Resource breakdown structure, Project document
updates
Question 8.
Plan Cost Management, Inputs
ANSWER
Project Charter, Project Management Plan, EEFs, OPAs
Question 9.
Manage Project Knowledge, Outputs
ANSWER
Lessons learned register, PM plan updates, and org. process assets updates
Question 10.
Determine Budget, Tools & Techniques
ANSWER
Expert judgement, Cost aggregation, Data analysis, Historical information review, Funding limit
reconciliation, Financing
, Question 11.
Control Costs, Outputs
ANSWER
Work performance information, Cost forecasts, Change requests, Project Management Plan
updates, Project document updates
Question 12.
Develop Schedule, Outputs
ANSWER
Schedule baseline, project schedule, schedule data, project calendars, change requests, PM
plan updates, project document updates
Question 13.
Perform Qualitative Risk Analysis, Inputs (ql)
ANSWER
Project Management Plan, Project documents, EEFs, OPAs (ql)
Question 14.
Develop Schedule, Tools & Techniques
ANSWER
Schedule network analysis
Critical path method
Resource optimization techniques
Data Analysis
Leads and lags
Schedule compression
PMIS
Agile release planning