Examen

Cmit Exam (200 Multiple Choice) Updated Actual Questions With Correct Answers

Document preview thumbnail
Vista previa 4 fuera de 47 páginas

Cmit Exam (200 Multiple Choice) Updated Actual Questions With Correct Answers

Vista previa del contenido

CMIT EXAM (200 MULTIPLE CHOICE)
UPDATED ACTUAL QUESTIONS WITH CORRECT
ANSWERS

Question 1.
Under a fixed price or lump sum contract, the contractors can be asked to bid on work based on
partially completed documents (scope bid), or a complete set of drawings and specifications.
True False

ANSWER
True



Question 2.
There are no accepted industry-wide standards or guidelines for determining what is considered to be
reasonable and fair compensation for construction management services.
True False

ANSWER
False



Question 3.
To the extent that a CM assumes the designer's responsibilities for cost estimates, the CM faces the
same liability as similarly situated designers.
True False

ANSWER
True



Question 4.
Sustainable materials are composed of nonrenewable resources.
True False

ANSWER
False






,Question 5.
The contractor is obligated to notify the CM of conflicts, errors and/or discrepancies in the contract
documents.
True False

ANSWER
True



Question 6.
One of the stipulations of the CMAA Code of Professional Ethics is that a CM should charge fees and
expenses that are reasonable.
True False

ANSWER
True



Question 7.
Prior to the workshop it is helpful to have job site interviews with field representatives of the parties.
True False

ANSWER
True



Question 8.
If a designer uses the CMAA A-4 contract document instead of the AIA B132-2009 document, the
designer's exposure to professional liability during the construction phase is reduced.
True False

ANSWER
True



Question 9.
What is the term sometimes used to describe the standard language of the full set of contract
documents? A) Special provisions
B) MasterFormat
C) Boiler plate
D) Contract agreement

ANSWER
C) Boiler plate






,Question 10.
A mini-trial, whether required by contract or agreed to voluntarily, results in a binding decision.
True False

ANSWER
False



Question 11.
There is more than one type of legal relationship that may exist between an owner and the CM.
True False

ANSWER
True



Question 12.
The parties to a contract need to have a ________________ in order to make an accurate economic
judgment as to cost.
A) budget
B) schedule
C) specific project design
D) specific scope statement

ANSWER
D) specific scope statement



Question 13.
The use of a BIM model on a project can lead to faster construction as a result of which of the following
factors?
A) Increased prefabrication
B) Increased changes
C) Reduced claims
D) Reduced design

ANSWER
A) Increased prefabrication






, Question 14.
Arrangements to select a form of alternative dispute resolution can be made by contractual agreement
or at the time a dispute arises.
True False

ANSWER
True



Question 15.
The parties, namely, the owner, the designer, CM, contractor and others, can be described as
stakeholders. True False

ANSWER
True



Question 16.
Most definitions of construction management are similar. However, a contractual definition is not
known until:
A) The legal form of the CM contract is chosen.
B) The specific scope of services to be provided is identified.
C) The relationship of the CM to others and the risks and authority assumed by the parties are clearly
defined.
D) All of the above

ANSWER
D) All of the above



Question 17.
The CM does not have the responsibility to generate and track the project budget.
True False

ANSWER
False

Información del documento

Subido en
13 de octubre de 2026
Número de páginas
47
Escrito en
2026/2027
Tipo
Examen
Contiene
Preguntas y respuestas
$16.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
GradeGalaxy
4.3
(18)
Vendido
210
Seguidores
6
Artículos
64143
Última venta
8 horas hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes