◉ The person conducting the fire watch ______ have other duties.
Answer: CANNOT
◉ A portable fire extinguisher with a rating of _________ is required
and should be within ____ feet travel distance hot work area.
Answer: 2-A:20-B:C///30
◉ For ROOFING OPERATIONS, a portable fire extinguisher with a
minimum rating of ______ is required.
Answer: 3-A:40-B:C
◉ Fire watch on floors below is ______.
Answer: required
◉ The fire watch must continue for a minimum of ____ minutes after
the hot work is done.
Answer: 30
, ◉ For any CNG or LPG torch operations, the first inspection shall be
conducted ___ minutes after completion. The second inspection shall
be conducted _______ after completion of torch operations..
Answer: 30 min///1 hour
◉ The fire guard or fire watch personnel must complete a signed
inspection report and it must be submitted to and retained by the
person in charge of the torch operations..
Answer: The report must be made available and maintained on the
premises for a minimum of 48 hours after the work is complete.
◉ Most common fuel gasses used in blowtorches are ______.
Answer: LPG (butane, propane) natural gas (methane) (either CNG
or piped natural gasses)
◉ Soldering and brazing temperatures are typically______.
Answer: 840 degrees F
◉ Oxy-acetylene generates the highest temperature which can reach
up to _____.
Answer: 6000 degrees F
◉ Gas torches can exceed _________ and are used for burning weeds,
melting ice, or applying tar to a roof.
PAPER WITH CORRECT ANSWERS
◉ The person conducting the fire watch ______ have other duties.
Answer: CANNOT
◉ A portable fire extinguisher with a rating of _________ is required
and should be within ____ feet travel distance hot work area.
Answer: 2-A:20-B:C///30
◉ For ROOFING OPERATIONS, a portable fire extinguisher with a
minimum rating of ______ is required.
Answer: 3-A:40-B:C
◉ Fire watch on floors below is ______.
Answer: required
◉ The fire watch must continue for a minimum of ____ minutes after
the hot work is done.
Answer: 30
, ◉ For any CNG or LPG torch operations, the first inspection shall be
conducted ___ minutes after completion. The second inspection shall
be conducted _______ after completion of torch operations..
Answer: 30 min///1 hour
◉ The fire guard or fire watch personnel must complete a signed
inspection report and it must be submitted to and retained by the
person in charge of the torch operations..
Answer: The report must be made available and maintained on the
premises for a minimum of 48 hours after the work is complete.
◉ Most common fuel gasses used in blowtorches are ______.
Answer: LPG (butane, propane) natural gas (methane) (either CNG
or piped natural gasses)
◉ Soldering and brazing temperatures are typically______.
Answer: 840 degrees F
◉ Oxy-acetylene generates the highest temperature which can reach
up to _____.
Answer: 6000 degrees F
◉ Gas torches can exceed _________ and are used for burning weeds,
melting ice, or applying tar to a roof.