If PJM experienced an event that caused the loss of a 1,000 MW generator, which of
the following would most likely provide the quickest impact to improve the
undegenerating Area Control Area (ACE)?
1. Remedial Action Reserve
2. Synch Reserve
3. Non-Synch Reserve
4. Secondary Reserve
Give this one a try later!
Synch Reserve
Generators are required to obtain PJM approval prior to removing a generating unit
from service.
The only exception is for:
,Give this one a try later!
injury to personnel will be prevented
Why is it important for PJM to know when a generator has limited fuel for operation?
Give this one a try later!
To plan for the most optimal time to utilize the resource
PJM's ACE configuration is such, that when the ACE is positive (+), it indicates
Give this one a try later!
too much generation
All of the following are limits that must be submitted to PJM for generating units
EXCEPT:
1. Eco Min
2. Eco Max
3. Emergency Max
4. Dynamic Instability
Give this one a try later!
Dynamic Instability
,Which of the following emergency procedures are issued in advance of a scheduled
load period to allow sufficient time for the generation dispatcher to prepare for the
anticipated capacity shortages?
Give this one a try later!
alerts
What is the benefit of the PJM system operators requesting members to submit
information for completing and IRC?
Give this one a try later!
I.D. any reserve shortages that may exist
PJM responds to capacity shortages by issuing alerts
Give this one a try later!
in advance of a scheduled load period to allow sufficient time for members
to prepare for anticipated initial capacity shortages
A CT has 26 burn hours at Max Capacity. How should this be offered into the Energy
Market?
Give this one a try later!
, normally
PJM performs a Reliability Assessment Commitment starting with the results of the DA
market.
What philosophy does PJM use when performing this RAC?
Give this one a try later!
Minimize start ups and no loads
A unit that fails to start when scheduled, would be classified as which of the following
types of outages?
1. planned
2. maintenance
3. forced
4. self-scheduled
Give this one a try later!
forced
All of the following elements must be reported to PJM when an IRC is requested
EXCEPT:
the following would most likely provide the quickest impact to improve the
undegenerating Area Control Area (ACE)?
1. Remedial Action Reserve
2. Synch Reserve
3. Non-Synch Reserve
4. Secondary Reserve
Give this one a try later!
Synch Reserve
Generators are required to obtain PJM approval prior to removing a generating unit
from service.
The only exception is for:
,Give this one a try later!
injury to personnel will be prevented
Why is it important for PJM to know when a generator has limited fuel for operation?
Give this one a try later!
To plan for the most optimal time to utilize the resource
PJM's ACE configuration is such, that when the ACE is positive (+), it indicates
Give this one a try later!
too much generation
All of the following are limits that must be submitted to PJM for generating units
EXCEPT:
1. Eco Min
2. Eco Max
3. Emergency Max
4. Dynamic Instability
Give this one a try later!
Dynamic Instability
,Which of the following emergency procedures are issued in advance of a scheduled
load period to allow sufficient time for the generation dispatcher to prepare for the
anticipated capacity shortages?
Give this one a try later!
alerts
What is the benefit of the PJM system operators requesting members to submit
information for completing and IRC?
Give this one a try later!
I.D. any reserve shortages that may exist
PJM responds to capacity shortages by issuing alerts
Give this one a try later!
in advance of a scheduled load period to allow sufficient time for members
to prepare for anticipated initial capacity shortages
A CT has 26 burn hours at Max Capacity. How should this be offered into the Energy
Market?
Give this one a try later!
, normally
PJM performs a Reliability Assessment Commitment starting with the results of the DA
market.
What philosophy does PJM use when performing this RAC?
Give this one a try later!
Minimize start ups and no loads
A unit that fails to start when scheduled, would be classified as which of the following
types of outages?
1. planned
2. maintenance
3. forced
4. self-scheduled
Give this one a try later!
forced
All of the following elements must be reported to PJM when an IRC is requested
EXCEPT: