A generator is capable of producing 250 MW and is currently producing 175 MW with
a 5% governor droop. Frequency has suddenly risen by 1.2HZ, what will be the new
generator output?
A) Decrease 20MW
B) Decrease 10MW
C) Increase 10MW
D) Increase 20MW
Give this one a try later!
B) Decrease 10MW
During a restoration process you have 6,000MW of customer demand restored and
frequency drop by 1 Hz how much load needs to be shed to restore frequency back
to where it was prior to the disturbance?
,A) 180MW to 360MW
B) 300MW to 480MW
C) 360MW to 600MW
D) 480MW to 720MW
Give this one a try later!
C) 360MW to 600MW
For a capacity shortage, a Voltage Reduction Action is always performed at what level
of the system?
A) Bulk Electric System
B) Transmission System
C) Sub-Transmission System
D) Distribution System
Give this one a try later!
D) Distribution System
For temporary changes to a unite's reactive capability curve, the Generation Owner
must immediately submit an dDART ticket and....
A) Notify PJM and the TO
B) Notify PJM and NERC
C) Notify the TO and RFC/SERC
D) Notify PJM and RFC/SERC
Give this one a try later!
, A) Notify PJM and the TO
Select the statement that best describes why Minimum Source Requirements have
been established:
A) To ensure system stability prior to interconnecting with another entity
B) To reduce major frequency fluctuations when energizing load
C) To prevent or reduce the effects of line changing when energizing EHV
transmission
D) To ensure that adequate Dynamic Reserves exist prior to interconnection with
another entity
Give this one a try later!
C) To prevent or reduce the effects of line changing when energizing EHV
transmission
Which of the following emergency procedures are issued in advance of a scheduled
load period to allow sufficient time for the generation dispatcher to prepare for the
anticipated capacity shortages?
A) warnings
B) actions
C) alerts
D) notifications
Give this one a try later!
C) alerts
, What is the difference between Dynamic Reserve and Synchronized Reserve?
Give this one a try later!
Dynamic Reserve - (automatic) reserve on generators that is available via
governor action and load w/ under frequency relaying
Synchronized Reserve - (manual) spinning online gen
Emergency reducible generation is defined as the difference between
A) normal minimum and normal maximum generation
B) maximum emergency generation and minimum emergency generation
C) normal minimum generation and emergency minimum generation
D) emergency minimum generation and normal maximum generation
Give this one a try later!
C) normal minimum generation and emergency minimum generation
What is the reserve requirement percentage for a contingency?
A) 70
B) 100
C) 120
D) 150
Give this one a try later!
a 5% governor droop. Frequency has suddenly risen by 1.2HZ, what will be the new
generator output?
A) Decrease 20MW
B) Decrease 10MW
C) Increase 10MW
D) Increase 20MW
Give this one a try later!
B) Decrease 10MW
During a restoration process you have 6,000MW of customer demand restored and
frequency drop by 1 Hz how much load needs to be shed to restore frequency back
to where it was prior to the disturbance?
,A) 180MW to 360MW
B) 300MW to 480MW
C) 360MW to 600MW
D) 480MW to 720MW
Give this one a try later!
C) 360MW to 600MW
For a capacity shortage, a Voltage Reduction Action is always performed at what level
of the system?
A) Bulk Electric System
B) Transmission System
C) Sub-Transmission System
D) Distribution System
Give this one a try later!
D) Distribution System
For temporary changes to a unite's reactive capability curve, the Generation Owner
must immediately submit an dDART ticket and....
A) Notify PJM and the TO
B) Notify PJM and NERC
C) Notify the TO and RFC/SERC
D) Notify PJM and RFC/SERC
Give this one a try later!
, A) Notify PJM and the TO
Select the statement that best describes why Minimum Source Requirements have
been established:
A) To ensure system stability prior to interconnecting with another entity
B) To reduce major frequency fluctuations when energizing load
C) To prevent or reduce the effects of line changing when energizing EHV
transmission
D) To ensure that adequate Dynamic Reserves exist prior to interconnection with
another entity
Give this one a try later!
C) To prevent or reduce the effects of line changing when energizing EHV
transmission
Which of the following emergency procedures are issued in advance of a scheduled
load period to allow sufficient time for the generation dispatcher to prepare for the
anticipated capacity shortages?
A) warnings
B) actions
C) alerts
D) notifications
Give this one a try later!
C) alerts
, What is the difference between Dynamic Reserve and Synchronized Reserve?
Give this one a try later!
Dynamic Reserve - (automatic) reserve on generators that is available via
governor action and load w/ under frequency relaying
Synchronized Reserve - (manual) spinning online gen
Emergency reducible generation is defined as the difference between
A) normal minimum and normal maximum generation
B) maximum emergency generation and minimum emergency generation
C) normal minimum generation and emergency minimum generation
D) emergency minimum generation and normal maximum generation
Give this one a try later!
C) normal minimum generation and emergency minimum generation
What is the reserve requirement percentage for a contingency?
A) 70
B) 100
C) 120
D) 150
Give this one a try later!