Examen

CIV E 270 Final Exam | Mechanics of Deformable Bodies I Practice Questions & Verified Answers | University of Alberta 2026–2027

Document preview thumbnail
Vista previa 3 fuera de 30 páginas

Comprehensive CIV E 270 Final Exam review for University of Alberta Civil Engineering students studying Mechanics of Deformable Bodies I. Covers stress and strain, stress-strain relationships, axial and transverse loading, torsion, bending, combined stress, statically indeterminate members, column buckling, and related mechanics of materials concepts. Includes practice questions and verified answers to help students reinforce core CIV E 270 concepts and prepare for the final examination in 2026–2027.

Vista previa del contenido

CIVE 270 Final Exam – Practice Questions
& Verified Answers | Comprehensive Civil
Engineering Final Exam Review |
2026–2027




Stuvia 2026-2027

,What payment method is the most risky for a contractor? Lump Sum
- Cost+ Incentive
- Lump Sum
- Guaranteed Max Price
- Unit Price
- Cost+ Fee


A study conducted by the Construction Industry Institute Design - Build
found which form of project delivery to have the lowest
design and construction cost growth? (on average, which
form had the lowest amount of cost overages)


What is a disadvantage of competitive bidding? Creates incentive for bidders to underbid work to get job, then try to make up costs
- Creates incentive for bidders to underbid work to get job, later through claims, etc.
then try to make up costs later through claims, etc.
- Competitive pressure forces bidders to offer their lowest
price
- Results in work starting later, therefore is more costly
- General contractors share information on the project and
their bids


What is not an advantage of Cost Plus Fee payment? The owner knows the actual cost of the project before it begins.
- Can be initiated with minimal design information.
- Opportunity for value engineering and scope extensions.
- Lower risk for contractor can result in lower price.
- The owner knows the actual cost of the project before it
begins.


What is an advantage of design bid build ? Only two prime contracts administered by owner.
- Relatively low opportunity for construction input during
design.
- Least flexible for fast-track.
- Sequential process can be slower.
- Only two prime contracts administered by owner.


The term fast track... Means that construction is begun before the design is complete
- Is synonymous with design/manage
- Means that construction is begun before the design is
complete
- Is synonymous with turnkey
- Indicates that two or more companies have combined
forces for the duration of the project.
- None of the above


Which of the following best describes our discussions in Taking a lifecycle approach to long term maintenance costs
class of how Public Private Partnerships delivery approach
generates value for money:
- Public sector retaining maximum amount of risk
- Taking a lifecycle approach to long term maintenance
costs
- Sole-sourcing contracts with the private sector partners
- Separating the integration of design and construction
phase


Which is NOT the advantage of professional construction Participants must all be cooperative and communicate well.
management?
- Participants must all be cooperative and communicate
well.
- Early construction involvement, good value engineering
potential.
- CM acts on owner's behalf, independent of design and
construction.
- Suitable for phased, fast-track projects, while still
benefiting from competitive bid, lump-sum construction
contracts.

, Why might a contractor take on risk for a given project? Because they may be able to increase their profit if the risk doesn't occur
- Because they enjoy extra stress
- Because they may be able to increase their profit if the
risk doesn't occur
- Because they can eliminate the risk


In which of the following cases should you treat the risk as When probability that the risk event will occur is higher than 50%.
part of your primary plan?
- When the likelihood and consequence risk matrix
represent a high result.
- When probability that the risk event will occur is higher
than 50%.
- When expected impact calculated by formula Probability
x (O+4M+P)/6 is greater than 1M.


Calculate a combined risk value for cost and schedule: the Expected Risk value cost: 0.9M; Expected Risk value schedule: .8mo.
following risks were identified in building a bridge. Risk 1:
Unaccounted utility ( there is a major gas line on the bridge
that needs to be removed) Cost Probability : 20% | Cost
Impact: 2M; Schedule Probability :10% | Schedule Impact :
3mo. Risk 2: The owner of the property for which one of
the bridge piers is supposed to be located decides not to
sell. Cost Probability :10% | Cost Impact: 5M; Schedule
Probability : 50% | Schedule Impact: 1 mo.
- Expected Risk value cost: 0.8 M; Expected Risk value
schedule: .9mo.
- Expected Risk value cost: 0.9M; Expected Risk value
schedule: .8mo.
- Expected Risk value cost: 1.9M; Expected Risk value
schedule: 1.8yr.
- Expected Risk Value : 7.2M/ mo.


A culture of safety should be led by who? Senior Executives/Managers
- Senior Executives/Managers
- Project Manager
- Workforce
- Project Coordinator


What are the 3 levels of safety? A culture of safety, a safety system, safety mechanics
- Project success, regulatory obligations, financial
implications
- Safety pyramid, safety hazards, safety mechanics
- A culture of safety, a safety system, safety mechanics
- A culture of safety, safety hazards, safety statics
- Safety training, safety hazards, safety mechanics


Which of the following is NOT a method to reduce risk? Include more items in the risk management plan
- Change plans to avoid or reduce specific risks
- Transfer risks to other parties
- Sell a portion of your risk
- Include more items in the risk management plan


Which of the following is NOT a driver for safety? Reduce total project times
- Professional/Regulatory Obligations
- Reduce total project times
- Financial Implications
- Project Success
- Personal/Ethical


According to the PMBOK, which of the following would be Project safety plan
considered to be an OUTPUT to the safety planning
process (select ALL that apply)?:
- Laws and regulations
- Subcontractor selection
- Management commitment
- Project safety plan
- Hazard analysis

Información del documento

Subido en
25 de septiembre de 2026
Número de páginas
30
Escrito en
2026/2027
Tipo
Examen
Contiene
Preguntas y respuestas
$12.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
gurutech
4.9
(13)
Vendido
48
Seguidores
0
Artículos
2046
Última venta
3 días hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes