Examen

Pmt 3600V Advanced Program Management Exam Prep Questions And Answers With Verified Solutions 2026/2027 Update. Just Released

Document preview thumbnail
Vista previa 3 fuera de 24 páginas

PMT 3600V ADVANCED PROGRAM MANAGEMENT EXAM PREP QUESTIONS AND ANSWERS WITH VERIFIED SOLUTIONS 2026/2027 UPDATE. JUST RELEASED

Vista previa del contenido

PMT 3600V ADVANCED PROGRAM
MANAGEMENT EXAM PREP
QUESTIONS AND ANSWERS WITH
VERIFIED SOLUTIONS 2026/2027
UPDATE. JUST RELEASED


1. A project manager is calculating the Estimate at Completion (EAC) for a project where the

current variances are expected to continue. Given BAC = $200,000; AC = $120,000; EV =

$100,000; and PV = $110,000. What is the EAC?

A. $200,000


B. $220,000


C. $240,000


D. $180,000


Answer: C


Conceptual Explanation: EAC = BAC / CPI. CPI = EV / AC = 100,,000 = 0.833.

EAC = 200,.833 = $240,000.


2. In a Fixed Price Incentive Fee (FPIF) contract, the Point of Total Assumption (PTA) is the

point where:

A. The seller assumes all cost risk for every dollar spent beyond this point.

,B. The buyer assumes all cost risk.


C. The project becomes unprofitable for the buyer.


D. The ceiling price is reached but profit is still paid.


Answer: A


Conceptual Explanation: PTA is the point where the seller assumes all cost risk for every

dollar spent beyond this point because the ceiling price limits the buyer’s liability.


3. A project has three critical paths. How does this affect the project’s risk profile?

A. It decreases the project risk because there are redundancies.


B. It has no effect on the project risk.


C. It makes the project easier to manage using crashing techniques.


D. It increases the project risk because a delay in any one path delays the project.


Answer: D


Conceptual Explanation: Multiple critical paths increase project risk because any delay on

any of the paths will result in a delay to the project finish date.


4. You are evaluating four projects. Project A has an NPV of $50,000, Project B has an NPV of

$75,000, Project C has an NPV of $15,000, and Project D has an NPV of -$10,000. Which

project should you select?

A. Project A


B. Project D

, C. Project C


D. Project B


Answer: D


Conceptual Explanation: In project selection, the project with the highest positive Net

Present Value (NPV) is typically selected as it adds the most value.


5. A project manager identifies a risk that a critical vendor might go bankrupt. The PM

decides to purchase an insurance policy to cover potential losses. What risk response strategy

is being used?

A. Mitigation


B. Avoidance


C. Transference


D. Acceptance


Answer: C


Conceptual Explanation: Transference involves shifting the impact of a threat and

ownership of the response to a third party, such as an insurance company.


6. A PERT estimate for a task shows Optimistic = 10 days, Pessimistic = 22 days, and Most

Likely = 13 days. What is the standard deviation for this task?

A. 3 days


B. 2 days

Información del documento

Subido en
23 de septiembre de 2026
Número de páginas
24
Escrito en
2026/2027
Tipo
Examen
Contiene
Preguntas y respuestas
$15.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
TheStar
3.7
(140)
Vendido
736
Seguidores
178
Artículos
28662
Última venta
1 día hace




Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes