CWB LEVEL 1 FULLY SOLVED TEST PAPER
GRADED A+
◉ What is the first step in the preparation of a WPS?
A) Qualify the welding personnel for use on the procedure.
B) Calibrate the welding equipment used for establishing the WPS.
C) Select the variables to be used for welding.
D) Inform the jurisdictional authority of your intensions.
Answer: C) Select the variables to be used for welding.
◉ According to CSA B51, which code is designated for welding?
A) CSA Z662, Oil and Gas Pipeline Systems.
B) AWS B2.1, Specification for Welding Procedure and Performance
Qualification.
C) ASME BPVC-IX.
D) American Petroleum Institute (API) 650.
Answer: C) ASME BPVC-IX.
◉ Which code of construction does CSA B52 work in conjunction
with?
,A) ASME B31.1
B) ASME B31.3
C) ASME B31.5
D) ASME B31.9
Answer: C) ASME B31.5
◉ Where does ASME B31.1 Boiler External Piping terminate in
relation to the boiler?
A) The first circumferential joint.
B) The face of the first flange.
C) The first threaded joint.
D) All of the above.
Answer: B) The face of the first flange.
◉ The standard that covers the general requirements for hollow
sections, sheet, cold formed channels and other structural quality
steel in Canada is:
A) ASTM A500
B) CCIIW
C) CSA W117.1
D) CSA G40.20/G40.21
, Answer: D) CSA G40.20/G40.21
◉ Which code stipulates the requirement of an operational control
procedure?
A) CSA W47.1
B) CSA W47.2
C) CSA W59
D) CSA W59.2
Answer: B) CSA W47.2
◉ Which company division requires a full-time engineer on staff?
A) Division 1.
B) Division 2.
C) Division 3.
D) All divisions.
Answer: A) Division 1.
◉ The AWS D1.1 Structural Welding Code - Steel:
A) is identical in coverage to the CSA W47.1 standard.
GRADED A+
◉ What is the first step in the preparation of a WPS?
A) Qualify the welding personnel for use on the procedure.
B) Calibrate the welding equipment used for establishing the WPS.
C) Select the variables to be used for welding.
D) Inform the jurisdictional authority of your intensions.
Answer: C) Select the variables to be used for welding.
◉ According to CSA B51, which code is designated for welding?
A) CSA Z662, Oil and Gas Pipeline Systems.
B) AWS B2.1, Specification for Welding Procedure and Performance
Qualification.
C) ASME BPVC-IX.
D) American Petroleum Institute (API) 650.
Answer: C) ASME BPVC-IX.
◉ Which code of construction does CSA B52 work in conjunction
with?
,A) ASME B31.1
B) ASME B31.3
C) ASME B31.5
D) ASME B31.9
Answer: C) ASME B31.5
◉ Where does ASME B31.1 Boiler External Piping terminate in
relation to the boiler?
A) The first circumferential joint.
B) The face of the first flange.
C) The first threaded joint.
D) All of the above.
Answer: B) The face of the first flange.
◉ The standard that covers the general requirements for hollow
sections, sheet, cold formed channels and other structural quality
steel in Canada is:
A) ASTM A500
B) CCIIW
C) CSA W117.1
D) CSA G40.20/G40.21
, Answer: D) CSA G40.20/G40.21
◉ Which code stipulates the requirement of an operational control
procedure?
A) CSA W47.1
B) CSA W47.2
C) CSA W59
D) CSA W59.2
Answer: B) CSA W47.2
◉ Which company division requires a full-time engineer on staff?
A) Division 1.
B) Division 2.
C) Division 3.
D) All divisions.
Answer: A) Division 1.
◉ The AWS D1.1 Structural Welding Code - Steel:
A) is identical in coverage to the CSA W47.1 standard.