SCM 300 Exam 3 (COMBINED) EXAM Questions with Correct Answers (Grade A+)

Document preview thumbnail
Vista previa 3 fuera de 19 páginas

SCM 300 Exam 3 (COMBINED) EXAM Questions with Correct Answers (Grade A+)

Vista previa del contenido

SCM 300 Exam 3 (COMBINED) EXAM Questions with Correct
Answers (Grade A+)

Question 1: project

Answer: a unique undertaking in which resources (human, material, and/or financial) are organized to
achieve an end goal or outcome


Question 2: Project manage- ment:

Answer: Long term


Question 3: Process manage- ment:

Answer: short term


Question 4: Budget:

Answer: Reduce the cost of logistics by 10%


Question 5: Time:

Answer: Complete construction by July 1st


Question 6: steps in project management

Answer: define the project establish project priorities (cost/time/performance) work breakdown structure
(aon diagram/milestones) track project progress


Question 7: project priorities

Answer: result in outstanding performance completed quickly, and with minimal resources


Question 8: work breakdown structure

Answer: project broken down into smallest units estimate of needs: people, time, cost


Question 9: objectives:

Answer: desired outcomes for the project (goals)




Page 1

,Question 10: deliverables:

Answer: a description of the products and/or services that should be delivered by the end of the project
(what client expect to be delivered)


Question 11: deliverables ex- amples

Answer: - Presentation and/or Documents: design, process, report, contract - Research (data or document) -
Physical item or intangible outputs (software)


Question 12: milestones

Answer: A specifc/major event indicating progress toward project completion


Question 13: milestones ex- amples

Answer: Project initiation Design Approval Deliverable completion Project Completion


Question 14: Project initiation: he

Answer: start of the project, including securing funding and forming the project team


Question 15: Design Approval: final

Answer: approval of the project design or plan


Question 16: Deliverable com- pletion:

Answer: completion of a major deliverable or phase of the project


Question 17: Project Comple- tion:

Answer: the final delivery of the project or product


Question 18: scope creep (scope inflation)

Answer: - additional scope that you don't have in your project - Managers put more of my requirements into
your project but you don't get more time or resources so the project likely pushes out/fail


Question 19: project manage- ment software

Answer: can assist in organizing the project and tracking the progress (can help run ditterent scenarios)



Page 2

, Question 20: AON Network Di- agrams

Answer: illustration where each circle represents a single activity in the project (projects must be completed
in sequential order)


Question 21: Inside the circles: activity

Answer: is given a name or symbol, a number will indicate how much time is required to complete the
activity


Question 22: Arrows leading into circle/activi- ty:

Answer: allows a project manager to see which activities must be completed before this activity begins


Question 23: Arrow leading out of circle/ac- tivity:

Answer: allows a project manager to see which activities can begin once that activity is completed


Question 24: project paths

Answer: ABEG is 16 days, ABDG is 20 days




Question 25: critical path

Answer: project path with the longest total duration, defines expected length of the project (can have
multiple) - must be completed on time


Question 26: slack

Answer: amount of time a path or single activity can be delayed without impacting the project duration


Question 27: crashing the pro- ject

Answer: act of finding a cost-ettective way to decrease the present length of the project (decreasing times)




Page 3

Información del documento

Subido en
22 de septiembre de 2026
Número de páginas
19
Escrito en
2026/2027
Tipo
Examen
Contiene
Preguntas y respuestas
$10.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
DrJon
3.8
(160)
Vendido
593
Seguidores
188
Artículos
23563
Última venta
13 horas hace




Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes