Examen

CMIT Exam (Multiple Choice) Comprehensive Q&A For Certification Success 2026

Document preview thumbnail
Vista previa 4 fuera de 67 páginas

CMIT Exam (Multiple Choice) Comprehensive Q&A For Certification Success 2026

Vista previa del contenido

1|Page



CMIT Exam (Multiple Choice)
Comprehensive Q&A For Certification
Success 2026



A CM's role and responsibilities are governed solely by the Owner/CM

Agreement.

True False - correct-answer - True




There are two basic forms of CM, agency and at-risk. Each form provides for the

basic services of construction management practice. However, there are some

key differences. Which of the following do not apply to both CM forms?

A) Both forms provide advice to the owner on constructibility, budget and the

schedule.

B) Both require that the liabilities and risks assumed by the parties be clearly

understood, coordinated, and stated in the respective contracts.

,2|Page


C) Both forms allow the CM to function in an advisory role for the entire

engagement of the CM.

D) Services can vary based on the contractual relationships of the parties and the

risks that are assumed. - correct-answer - C) Both forms allow the CM to function

in an advisory role for the entire engagement of the CM.




Actual usage of a particular contract form for the construction phase depends on:

A) The particular delivery system being used.

B) The type of project being implemented and the completion status of the plans

and specifications at the time of contracting.

C) The consideration of any performance requirements, the level of sophistication

of the owner, and the role of the architect/engineers involved.

D) All of the above - correct-answer - D) All of the above




There are two basic categories of construction phase contracts, cost

reimbursement and fixed price.

True False - correct-answer - True

,3|Page




Under a fixed price or lump sum contract, the contractors can be asked to bid on

work based on partially completed documents (scope bid), or a complete set of

drawings and specifications.

True False - correct-answer - True




The primary advantage of the fixed price or lump sum contract is that bids should

be taken on contract documents that are only 50% complete.

True False - correct-answer - False




A general contractor working under a fixed price contract will always put its

interests ahead of the owner.

True False - correct-answer - True

, 4|Page


Under a cost plus fixed fee arrangement, fixed fee is usually established at the

time of contract award; however, it may vary with the actual cost expended as

the scope of work changes.

True False - correct-answer - True




Under a Guaranteed Maximum Price arrangement, the contractor is usually

selected and a GMP is established with the understanding by the parties that the

actual cost of the work could be greater than the GMP.

True False - correct-answer - False




On some GMP projects, the owner may reserve the right to approve all trade and

purchase contracts. Normally the owner pays the difference between the

estimated trade contract costs and the trade contract award value when the

award value approved by the owner is greater than the estimated bid element

included in the contractor's GMP.

True False - correct-answer - True

Información del documento

Subido en
18 de septiembre de 2026
Número de páginas
67
Escrito en
2026/2027
Tipo
Examen
Contiene
Preguntas y respuestas
$17.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Isladoc
3.8
(13)
Vendido
115
Seguidores
0
Artículos
9225
Última venta
1 semana hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes