1. Which activity is NOT permitted under an Arizona CR-65 glazing license?
A) Installing tempered glass in a storefront
B) Applying window film to existing glass
C) Installing structural steel beams for a curtain wall
D) Installing glass-holding members such as glazing beads
Answer: C
Rationale: The CR-65 license authorizes installation of glass, window film,
weatherproofing, caulking, sealants, adhesives, and glass-holding members . Installing
structural steel components requires a different contractor classification (e.g., structural
steel or general contracting license) .
2. A CR65 contractor in Arizona is primarily licensed to perform:
A) Any type of glass installation, including structural storefronts and curtain walls
B) Only residential window glass replacement
C) Glass installation but not metal framing
D) Only automotive glass
Answer: A
,Rationale: CR65 is the Glazing classification, allowing installation of glass, metal
framing, storefronts, curtain walls, mirrors, glass doors, and related hardware .
3. According to Arizona ROC statutes, how many years of relevant work experience
are required to qualify for a CR-65 license?
A) One year
B) Two years
C) Four years
D) Five years
Answer: C
Rationale: A.R.S. § 32-1121 and ROC rules generally require four years of relevant,
verified journeyman-level experience within the past ten years .
4. What is the primary role of the Arizona Registrar of Contractors (ROC)?
A) To enforce federal building codes
B) To regulate and license contractors operating within Arizona
C) To oversee city planning departments
D) To set international standards for glazing materials
Answer: B
Rationale: The ROC's primary purpose is to protect the public by licensing and
regulating contractors and ensuring compliance with state laws .
5. Under Arizona's Registrar of Contractors (ROC), the financial limit for a standard
CR65 license without a bond increase is:
A) $10,000 per project
B) $25,000 per project
C) $50,000 per project
D) No limit
Answer: B
,Rationale: A standard contractor license in Arizona has a $25,000 project limit unless a
higher bond is posted .
6. The Arizona CR65 Glazing Contractor license primarily authorizes the holder to:
A) Install and replace storefronts, curtain walls, and window walls
B) Manufacture glass and glazing materials
C) Install and replace residential windows and doors only
D) Fabricate and install structural steel for glass systems
Answer: A
Rationale: The CR65 license specifically covers the installation and replacement of
storefronts, curtain walls, and window walls, which are commercial/architectural glazing
systems .
7. According to Arizona law, a CR65 contractor may subcontract electrical work for
automatic glass doors:
A) Yes, if the CR65 holds an electrical license
B) Yes, any CR65 can subcontract it without restriction
C) No, only a licensed electrical contractor can perform electrical work for doors
D) Only if the door is under 6 feet tall
Answer: C
Rationale: CR65 covers glazing, not electrical. Any electrical work on automatic doors
must be performed by a licensed electrical contractor, even if subcontracted .
8. What is the minimum financial responsibility requirement (surety bond or
assigned account) for a CR65 contractor in Arizona?
A) $5,000
B) $7,500
C) $10,000
D) $15,000
, Answer: B
Rationale: The Arizona ROC requires a $7,500 surety bond for most residential and
commercial contractor licenses .
9. How often must a CR65 contractor in Arizona renew their license?
A) Annually
B) Biennially (every 2 years)
C) Every 4 years
D) Every 5 years
Answer: B
Rationale: Arizona contractor licenses require biennial renewal with fees .
10. Under Arizona Revised Statutes, a CR65 glazing contractor may legally perform
work on:
A) Glass only, without frames
B) Glass and framing systems for storefronts, windows, and doors
C) Structural steel erection
D) Plumbing for glass washers
Answer: B
Rationale: The CR65 license covers glazing and the installation of glass, windows, doors,
storefronts, curtain walls, and their framing systems, but not unrelated trades like
structural steel or plumbing .
SECTION 2: GLASS TYPES & SAFETY GLAZING
– Questions with Answers & Rationales |
150 Instant Pdf Download Construction
Technology / Glazing (Glass Installation)
/ Building Trades
SECTION 1: LICENSING, SCOPE & REGULATIONS
1. Which activity is NOT permitted under an Arizona CR-65 glazing license?
A) Installing tempered glass in a storefront
B) Applying window film to existing glass
C) Installing structural steel beams for a curtain wall
D) Installing glass-holding members such as glazing beads
Answer: C
Rationale: The CR-65 license authorizes installation of glass, window film,
weatherproofing, caulking, sealants, adhesives, and glass-holding members . Installing
structural steel components requires a different contractor classification (e.g., structural
steel or general contracting license) .
2. A CR65 contractor in Arizona is primarily licensed to perform:
A) Any type of glass installation, including structural storefronts and curtain walls
B) Only residential window glass replacement
C) Glass installation but not metal framing
D) Only automotive glass
Answer: A
,Rationale: CR65 is the Glazing classification, allowing installation of glass, metal
framing, storefronts, curtain walls, mirrors, glass doors, and related hardware .
3. According to Arizona ROC statutes, how many years of relevant work experience
are required to qualify for a CR-65 license?
A) One year
B) Two years
C) Four years
D) Five years
Answer: C
Rationale: A.R.S. § 32-1121 and ROC rules generally require four years of relevant,
verified journeyman-level experience within the past ten years .
4. What is the primary role of the Arizona Registrar of Contractors (ROC)?
A) To enforce federal building codes
B) To regulate and license contractors operating within Arizona
C) To oversee city planning departments
D) To set international standards for glazing materials
Answer: B
Rationale: The ROC's primary purpose is to protect the public by licensing and
regulating contractors and ensuring compliance with state laws .
5. Under Arizona's Registrar of Contractors (ROC), the financial limit for a standard
CR65 license without a bond increase is:
A) $10,000 per project
B) $25,000 per project
C) $50,000 per project
D) No limit
Answer: B
,Rationale: A standard contractor license in Arizona has a $25,000 project limit unless a
higher bond is posted .
6. The Arizona CR65 Glazing Contractor license primarily authorizes the holder to:
A) Install and replace storefronts, curtain walls, and window walls
B) Manufacture glass and glazing materials
C) Install and replace residential windows and doors only
D) Fabricate and install structural steel for glass systems
Answer: A
Rationale: The CR65 license specifically covers the installation and replacement of
storefronts, curtain walls, and window walls, which are commercial/architectural glazing
systems .
7. According to Arizona law, a CR65 contractor may subcontract electrical work for
automatic glass doors:
A) Yes, if the CR65 holds an electrical license
B) Yes, any CR65 can subcontract it without restriction
C) No, only a licensed electrical contractor can perform electrical work for doors
D) Only if the door is under 6 feet tall
Answer: C
Rationale: CR65 covers glazing, not electrical. Any electrical work on automatic doors
must be performed by a licensed electrical contractor, even if subcontracted .
8. What is the minimum financial responsibility requirement (surety bond or
assigned account) for a CR65 contractor in Arizona?
A) $5,000
B) $7,500
C) $10,000
D) $15,000
, Answer: B
Rationale: The Arizona ROC requires a $7,500 surety bond for most residential and
commercial contractor licenses .
9. How often must a CR65 contractor in Arizona renew their license?
A) Annually
B) Biennially (every 2 years)
C) Every 4 years
D) Every 5 years
Answer: B
Rationale: Arizona contractor licenses require biennial renewal with fees .
10. Under Arizona Revised Statutes, a CR65 glazing contractor may legally perform
work on:
A) Glass only, without frames
B) Glass and framing systems for storefronts, windows, and doors
C) Structural steel erection
D) Plumbing for glass washers
Answer: B
Rationale: The CR65 license covers glazing and the installation of glass, windows, doors,
storefronts, curtain walls, and their framing systems, but not unrelated trades like
structural steel or plumbing .