A ladder should extend a minimum of ___ above the top of a trench or excavation.
A. 1 feet
B. 2 feet
C. 3 feet
D. 4 feet - (ANSWER)C. 3 feet
Accordring to OSHA, shoring lumber shall be ___.
A. #1 treated
B. #2 treated
C. select structural
D. #3 common - (ANSWER)C. select structural
Cal/OSHA inspectors cannot, under most circumstances:
A. enter a business outside of normal business hours
B. inspect a workplace without prior notice
C. obtain an inspection warrant
D. require an employer to post a citation - (ANSWER)A. enter a business outside of normal business
hours
Every employer is required to post Material Safety Data Sheets:
A. at the office
B. on each job site
,SAFETY CALIFORNIA CONTRACTORS LAW AND BUSINESS EXAM
WITH COMPLETE SOLUTIONS!!! ALREADY GRADED A+ LATEST
UPDATE!!!
C. on every vehicle
D. it is not required to be posted - (ANSWER)B. on each job site
Handrails must be installed on all open sides of a scaffold if workers are subject to falls of ___ or more.
A. 5 feet
B. 6 feet
C. 7.5 feet
D. 10 feet - (ANSWER)C. 7 1/2 feet
When boom-type equipment is in operation, how close can it be to high voltage power lines?
A. 6 feet
B. 10 feet
C. 20 feet
D. 25 feet - (ANSWER)B. 10 feet
How should you store oily mops or rags on the job site?
A. In a closed metal container
B. In a plastic container
C. Out in the sun to dry off
D. In a plastic bag - (ANSWER)A. In a closed metal container
If a Cal/OSHA inspector is coming to inspect a job site, it is best for the contractor to:
,SAFETY CALIFORNIA CONTRACTORS LAW AND BUSINESS EXAM
WITH COMPLETE SOLUTIONS!!! ALREADY GRADED A+ LATEST
UPDATE!!!
A. inform the owner that the inspector is coming
B. personally walk through the job site and check the work
C. have a foreman or supervisor check the job site
D. have all the employees leave the job site - (ANSWER)B. personally walk through the job site and check
the work
In most cases, a crane cannot lift more than ___ % fo its capacity. Always consult the manufacturer's
operations manual and all applicable codes before using a crane and never attempt to use on without
being thoroughly trained and certified to operate the crane.
A. 50
B. 75
C. 100
D. 125 - (ANSWER)B. 75
In stable soil, a trench that is ___ or deeper requires shoring.
A. 3 feet
B. 5 feet
C. 6 feet
D. 8 feet - (ANSWER)B. 5 feet
On a construction site, flammable liquids can be found in what color containers?
A. red
, SAFETY CALIFORNIA CONTRACTORS LAW AND BUSINESS EXAM
WITH COMPLETE SOLUTIONS!!! ALREADY GRADED A+ LATEST
UPDATE!!!
B. orange
C. green
D. blue - (ANSWER)A. red
Prior to erecting scaffolding, it is best to consult the:
A. Uniform Building Code
B. State Housing Code
C. Construction Safety Orders
D. Contractors State License Board - (ANSWER)C. Construction Safety Orders
The rule of thumb that is used when digging a trench near another excavation is that the horizontal
distance from the trench to the excavation is no less than:
A. the width of the trench
B. the depth of the trench
C. half the depth of the trench
D. 25 feet - (ANSWER)B. the depth of the trench
What agency requires Material Safety Data Sheets?
A. U.B.C
B. Cal/OSHA
C. California Energy Efficiency Standards Board
D. Contractors State License Board - (ANSWER)B. Cal/OSHA
WITH COMPLETE SOLUTIONS!!! ALREADY GRADED A+ LATEST
UPDATE!!!
A ladder should extend a minimum of ___ above the top of a trench or excavation.
A. 1 feet
B. 2 feet
C. 3 feet
D. 4 feet - (ANSWER)C. 3 feet
Accordring to OSHA, shoring lumber shall be ___.
A. #1 treated
B. #2 treated
C. select structural
D. #3 common - (ANSWER)C. select structural
Cal/OSHA inspectors cannot, under most circumstances:
A. enter a business outside of normal business hours
B. inspect a workplace without prior notice
C. obtain an inspection warrant
D. require an employer to post a citation - (ANSWER)A. enter a business outside of normal business
hours
Every employer is required to post Material Safety Data Sheets:
A. at the office
B. on each job site
,SAFETY CALIFORNIA CONTRACTORS LAW AND BUSINESS EXAM
WITH COMPLETE SOLUTIONS!!! ALREADY GRADED A+ LATEST
UPDATE!!!
C. on every vehicle
D. it is not required to be posted - (ANSWER)B. on each job site
Handrails must be installed on all open sides of a scaffold if workers are subject to falls of ___ or more.
A. 5 feet
B. 6 feet
C. 7.5 feet
D. 10 feet - (ANSWER)C. 7 1/2 feet
When boom-type equipment is in operation, how close can it be to high voltage power lines?
A. 6 feet
B. 10 feet
C. 20 feet
D. 25 feet - (ANSWER)B. 10 feet
How should you store oily mops or rags on the job site?
A. In a closed metal container
B. In a plastic container
C. Out in the sun to dry off
D. In a plastic bag - (ANSWER)A. In a closed metal container
If a Cal/OSHA inspector is coming to inspect a job site, it is best for the contractor to:
,SAFETY CALIFORNIA CONTRACTORS LAW AND BUSINESS EXAM
WITH COMPLETE SOLUTIONS!!! ALREADY GRADED A+ LATEST
UPDATE!!!
A. inform the owner that the inspector is coming
B. personally walk through the job site and check the work
C. have a foreman or supervisor check the job site
D. have all the employees leave the job site - (ANSWER)B. personally walk through the job site and check
the work
In most cases, a crane cannot lift more than ___ % fo its capacity. Always consult the manufacturer's
operations manual and all applicable codes before using a crane and never attempt to use on without
being thoroughly trained and certified to operate the crane.
A. 50
B. 75
C. 100
D. 125 - (ANSWER)B. 75
In stable soil, a trench that is ___ or deeper requires shoring.
A. 3 feet
B. 5 feet
C. 6 feet
D. 8 feet - (ANSWER)B. 5 feet
On a construction site, flammable liquids can be found in what color containers?
A. red
, SAFETY CALIFORNIA CONTRACTORS LAW AND BUSINESS EXAM
WITH COMPLETE SOLUTIONS!!! ALREADY GRADED A+ LATEST
UPDATE!!!
B. orange
C. green
D. blue - (ANSWER)A. red
Prior to erecting scaffolding, it is best to consult the:
A. Uniform Building Code
B. State Housing Code
C. Construction Safety Orders
D. Contractors State License Board - (ANSWER)C. Construction Safety Orders
The rule of thumb that is used when digging a trench near another excavation is that the horizontal
distance from the trench to the excavation is no less than:
A. the width of the trench
B. the depth of the trench
C. half the depth of the trench
D. 25 feet - (ANSWER)B. the depth of the trench
What agency requires Material Safety Data Sheets?
A. U.B.C
B. Cal/OSHA
C. California Energy Efficiency Standards Board
D. Contractors State License Board - (ANSWER)B. Cal/OSHA