Question 1
You are on a team that is using XP. Your team seems to be confused during a discussion,
where people seem to be talking about different things, when you believe they are just
using different words, which is confusing. Which XP practice are you probably not
following?
A.Sustainable Pace
B.Simple Design
C.System Metaphor
D.Pair Programming
CORRECT ANSWER
C
Question 2
Which is the appropriate leadership style for when your team is in the Storming Phase?
A.Directing
B.Coaching
C.Supporting
D.Delegating
CORRECT ANSWER
B
1
@THE STUDY VAULT
,Question 3
Which of the following shows changes in scope?
A.Iteration Burndown chart
B.Release Burn-up chart
C.Release Burndown Chart
D.None of the above
CORRECT ANSWER
B
Question 4
When you are coaching an individual, which of the following is the least beneficial
technique?
A.Talk with the person one-on-one away from the rest of the team
B.Discuss the matter with the entire team
C.Have the person you are coaching come up with some plans for improvement
D.Keep a positive attitude
CORRECT ANSWER
B
Question 5
In Agile, which of the following is not a success strategy?
A.Matching the work assignments with the person
B.Get Feedback
C.Have management give a monetary award
D.Use appropriate reward that preserve joy for your team
2
@THE STUDY VAULT
,CORRECT ANSWER
C
Question 6
Which iteration of a release is most likely to have the lowest velocity?
A.The first iteration
B.The Last iteration
C.The second to last iteration
D.All iterations should have the same velocity
CORRECT ANSWER
A
Question 7
Which of the following is not true about incremental delivery?
A.Your customer only receives the value when the last piece is delivered
B.The product is built and delivered in chunks
C.You can more easily incorporate requested changes during the project
D.The order of work is determined by value-based prioritization
CORRECT ANSWER
A
Question 8
Which of the following is an example of a workshop?
A.Status Meetings
3
@THE STUDY VAULT
, B.Daily Standups
C.Product Reviews
D.Backlog Prioritization meeting
CORRECT ANSWER
D
Question 9
An estimating method that is similar to Wide Band Delphi is
A.Planning Poker
B.Parametric Estimation
C.Rolling Wave Planning
D.Task Estimating
CORRECT ANSWER
A
Question 10
Which of the following is not a main activity of release planning?
A.Selecting the stories for inclusion in the next release
B.Estimating Velocity
C.Defining Acceptance Criteria
D.Slicing the Stories
CORRECT ANSWER
C
4
@THE STUDY VAULT
You are on a team that is using XP. Your team seems to be confused during a discussion,
where people seem to be talking about different things, when you believe they are just
using different words, which is confusing. Which XP practice are you probably not
following?
A.Sustainable Pace
B.Simple Design
C.System Metaphor
D.Pair Programming
CORRECT ANSWER
C
Question 2
Which is the appropriate leadership style for when your team is in the Storming Phase?
A.Directing
B.Coaching
C.Supporting
D.Delegating
CORRECT ANSWER
B
1
@THE STUDY VAULT
,Question 3
Which of the following shows changes in scope?
A.Iteration Burndown chart
B.Release Burn-up chart
C.Release Burndown Chart
D.None of the above
CORRECT ANSWER
B
Question 4
When you are coaching an individual, which of the following is the least beneficial
technique?
A.Talk with the person one-on-one away from the rest of the team
B.Discuss the matter with the entire team
C.Have the person you are coaching come up with some plans for improvement
D.Keep a positive attitude
CORRECT ANSWER
B
Question 5
In Agile, which of the following is not a success strategy?
A.Matching the work assignments with the person
B.Get Feedback
C.Have management give a monetary award
D.Use appropriate reward that preserve joy for your team
2
@THE STUDY VAULT
,CORRECT ANSWER
C
Question 6
Which iteration of a release is most likely to have the lowest velocity?
A.The first iteration
B.The Last iteration
C.The second to last iteration
D.All iterations should have the same velocity
CORRECT ANSWER
A
Question 7
Which of the following is not true about incremental delivery?
A.Your customer only receives the value when the last piece is delivered
B.The product is built and delivered in chunks
C.You can more easily incorporate requested changes during the project
D.The order of work is determined by value-based prioritization
CORRECT ANSWER
A
Question 8
Which of the following is an example of a workshop?
A.Status Meetings
3
@THE STUDY VAULT
, B.Daily Standups
C.Product Reviews
D.Backlog Prioritization meeting
CORRECT ANSWER
D
Question 9
An estimating method that is similar to Wide Band Delphi is
A.Planning Poker
B.Parametric Estimation
C.Rolling Wave Planning
D.Task Estimating
CORRECT ANSWER
A
Question 10
Which of the following is not a main activity of release planning?
A.Selecting the stories for inclusion in the next release
B.Estimating Velocity
C.Defining Acceptance Criteria
D.Slicing the Stories
CORRECT ANSWER
C