Escrito por estudiantes que aprobaron Inmediatamente disponible después del pago Leer en línea o como PDF ¿Documento equivocado? Cámbialo gratis 4,6 TrustPilot
logo-home
Document preview thumbnail
Vista previa 4 fuera de 64 páginas
Examen

WGU C722 |PROJECT MANAGEMENT| PA |PRE-ASSESSMENT |EXAM QUESTIONS AND ANSWERS| FULLY SOLVED

Document preview thumbnail
Vista previa 4 fuera de 64 páginas

WGU C722 |PROJECT MANAGEMENT| PA |PRE-ASSESSMENT |EXAM QUESTIONS AND ANSWERS| FULLY SOLVED

Vista previa del contenido

WGU C722 PROJECT MANAGEMENT |PA| |PRE-ASSESSMENT | EXAM
QUESTIONS AND ANSWERS



Correct

Incorrect




1 of 70

Term



which activity is accomplished as part of the planning process of a
project?



Give this one a try later!



a) initiating
b) executing*
c) operating
d) closing
e) planning*




a) recognizing and rewarding performance
b) drafting the project charter*
c) assessing project quality
d) completing the project documentation




2) Developing the work breakdown structure
5) Capturing lessons learned

, 3) Working to produce project deliverables
1) Collecting customer requirements
4) Customers evaluating the project outcomes



a) reconciling the vendor accounts
b) finalizing the project budget*
c) documenting any requested changes to scope
d) reviewing the lessons learned in the project


Don't know?




2 of 70

Term



Which PMBOK process group is described as the delivery part of
project management where the main activity happens?



Give this one a try later!



Deliverable Executing




Planning deliverable


Don't know?




3 of 70

Term


A general contractor is managing a highway construction project
that will repair a flood-damaged road. The project was documented

,in a cost-plus-incentive fee contract that specified a completion
date of June 30. The Dept of Transportation has offered an incentive
for early completion of repairs.
Which triple-constraint baseline remained unchanged by the effects
of the incentive?


Give this one a try later!



a) managing the change a) price
b) reinforcing the change* b) cost
c) preparing for the change c) scope*
d) upgrading the change d) time




a) 15 a) time*
b) 23* b) penalties
c) 30 c) cost
d) 35 d) incentives


Don't know?




4 of 70

Term


A project manager is working on a large two-year IT project. At the
end of the first year, the project is two months behind schedule
because the interface programming is taking longer than planned.
The sponsor will not extend the deadline or the budget but is willing
to eliminate the interface.
Which schedule compression technique can the project manager
use?

, Give this one a try later!


a) reinforce the change a) sacred cow
b) upgrading the change b) operating necessity
c) managing the change c) competitive necessity*
d) preparing for the change* d) checklists




a) scope reduction* a) reduced quality of deliverables*
b) determining the critical path b) reduction in rework
c) resource leveling c) less overtime
d) fast-tracking d) use of fewer resources


Don't know?




5 of 70

Term



What is the purpose of the cost performance index (CPI)?



Give this one a try later!



a) the concept that a dollar today Is worth a dollar, but a dollar in a year will be
worth less than a dollar*
b) the measure in time in which total cash received is equal to, or exceeds, total
costs
c) the value of what you are giving up when you select one of two projects
d) the discount amount when present value of cash intake equals the original
investment




a) assigning project team members to new projects
b) coaching team members
c) verifying that the deliverables meet the required scope
d) reconciling the vendor accounts*

Información del documento

Subido en
25 de agosto de 2026
Número de páginas
64
Escrito en
2026/2027
Tipo
Examen
Contiene
Preguntas y respuestas
$16.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
millyphilip
3.6
(555)
Vendido
2967
Seguidores
1963
Artículos
46086
Última venta
14 horas hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes