QUESTIONS AND CORRECT ANSWERS (VERIFIED
ASWERS) Q&A 2027|INSTANT DOWNLOAD PDF
1. What is the primary responsibility of a program manager?
A. Managing only individual project tasks
B. Coordinating related projects to achieve strategic benefits
C. Performing all technical work personally
D. Managing only the organization's finances
Correct Answer: B. Coordinating related projects to achieve
strategic benefits
Rationale: A program manager oversees related projects and
activities collectively to achieve outcomes and benefits that
support organizational strategy.
2. What best distinguishes a program from a project?
A. A program is always shorter than a project
B. A program consists of unrelated activities
C. A program coordinates related projects to obtain strategic
benefits
D. A project always has a larger budget
Correct Answer: C. A program coordinates related projects to
obtain strategic benefits
,Rationale: Projects produce specific outputs, while programs
coordinate related projects and activities to realize broader
benefits.
3. Which document typically establishes the program at a high
level?
A. Program charter
B. Project invoice
C. Employee handbook
D. Procurement receipt
Correct Answer: A. Program charter
Rationale: The program charter formally authorizes the
program and provides its purpose, objectives, governance, and
high-level expectations.
4. What is program governance primarily concerned with?
A. Coding software
B. Establishing decision-making, accountability, and oversight
C. Preparing employee payroll
D. Designing individual project deliverables
Correct Answer: B. Establishing decision-making, accountability,
and oversight
Rationale: Governance defines who makes decisions, how
decisions are made, and how the program is controlled.
,5. Which of the following is a key program management
activity?
A. Coordinating interdependencies
B. Eliminating all project managers
C. Avoiding stakeholders
D. Ignoring organizational strategy
Correct Answer: A. Coordinating interdependencies
Rationale: Programs often contain projects whose schedules,
resources, risks, and deliverables depend on one another.
6. What is a program benefit?
A. A project task
B. A measurable improvement resulting from program
outcomes
C. A meeting agenda
D. A procurement document
Correct Answer: B. A measurable improvement resulting from
program outcomes
Rationale: Benefits represent measurable improvements or
advantages realized through program outputs and outcomes.
7. Which activity should occur early in program initiation?
, A. Closing all projects
B. Identifying strategic objectives and expected benefits
C. Conducting final audits
D. Releasing all resources
Correct Answer: B. Identifying strategic objectives and expected
benefits
Rationale: The program must be aligned with organizational
strategy and have clearly understood intended benefits.
8. Who typically provides executive support for a program?
A. Program sponsor
B. Project scheduler
C. Technical assistant
D. Procurement clerk
Correct Answer: A. Program sponsor
Rationale: The sponsor provides authority, strategic support,
resources, and organizational advocacy.
9. What is stakeholder management designed to accomplish?
A. Eliminate stakeholder participation
B. Understand and appropriately engage people affected by the
program
C. Replace program governance
D. Reduce all communications