CORRECT ANSWERS
What does the CDM Regulations 2015 stand for? - CORRECT ANSWER The Construction
(Design and Management) Regulations 2015
When did the CDM Regulations 2015 come into force? - CORRECT ANSWER · 06 April
2015.
Who are the duty holders under the CDM Regulations 2015? - CORRECT ANSWER ·
Commercial client.
· Domestic client.
· Principal designer.
· Designer.
· Principal contractor.
· Contractor.
· Worker.
What are main duties of the client? - CORRECT ANSWER · Make suitable arrangements to
manage a project to ensure construction works are carried out safely and adequate welfare facilities
are provided.
· Provide the pre-construction information.
· Ensure the appointment of the principal designer and principal contractor in writing before the
construction phase begins.
· Ensure both the principal designer and principal contractor comply with their own duties.
· Ensure the construction phase plan is produced by the principal contractor.
· Ensure the health and safety file is prepared by the principal designer.