Escrito por estudiantes que aprobaron Inmediatamente disponible después del pago Leer en línea o como PDF ¿Documento equivocado? Cámbialo gratis 4,6 TrustPilot
logo-home
Document preview thumbnail
Vista previa 1 fuera de 4 páginas
Examen

Unit 5-Project Management -Questions and Answers.

Document preview thumbnail
Vista previa 1 fuera de 4 páginas

Mary sets a target for the project budget during the planning phase. While executing the project, she checks to make sure she is within budget. Mary determines that she needs to refine the scope of the project and change her timeline and costs for the project activities. Mary is using which tool to manage the cost of this project? - Answer funding limit reconciliation Liz looks at the activity costs that must be incurred to complete all project deliverables. Liz is determining the: - Answer project funding requirements Management Contingency Reserve is identified in which process: - Answer Determine Budget Felicia averages three quoted costs and determines that she will need to put an extra $20,000 into the project budget. What cost estimating technique did Felicia use? - Answer vendor bid analysis Jenna's team is creating a new product. A deliverable for the project consists of building a website for the product. Jenna announces that she will be outsourcing this deliverable. Company A estimated a cost of $60,000 with completion in 3 months, Company B estimated a cost of $100,000 with completion in 2 months, and Company C estimated a cost of $50,000 with completion in 4 months. Jenna averages the three proposed costs and determines that she will need to put $70,000 into the project budget for the website deliverable. What cost estimating technique did Jenna use? - Answer vendor bid analysis As the project manager, it's your responsibility to develop the project budget. Inputs to the project budget do not include the - Answer stakeholder register The project manager is estimating the cost of procuring a specialist on a part-time basis. Because she doesn't know for sure whether the desired resource will be available when the project begins, she has some uncertainty in developing the cost estimate. To account for the uncertainty, she calculates an optimistic cost estimate, a pessimistic cost estimate, and a most likely cost estimate. Next, she selects the average of these estimates. The technique she used to develop the estimate is referred to as a - Answer none of these Glenn is determining the project cost baseline by calculating the costs approved for each of the project's work packages. Glenn is determining the: - Answer planned value Tucker is the construction project manager for a new school building. He measures the project's performance and progress by looking at the planned value, earned value, and actual cost.

Vista previa del contenido

Unit 5-Project Management -Questions
and Answers.
Mary sets a target for the project budget during the planning phase. While executing the
project, she checks to make sure she is within budget. Mary determines that she needs to refine
the scope of the project and change her timeline and costs for the project activities. Mary is
using which tool to manage the cost of this project? - Answer funding limit reconciliation



Liz looks at the activity costs that must be incurred to complete all project deliverables. Liz is
determining the: - Answer project funding requirements



Management Contingency Reserve is identified in which process: - Answer Determine Budget



Felicia averages three quoted costs and determines that she will need to put an extra $20,000
into the project budget. What cost estimating technique did Felicia use? - Answer vendor bid
analysis



Jenna's team is creating a new product. A deliverable for the project consists of building a
website for the product. Jenna announces that she will be outsourcing this deliverable.
Company A estimated a cost of $60,000 with completion in 3 months, Company B estimated a
cost of $100,000 with completion in 2 months, and Company C estimated a cost of $50,000 with
completion in 4 months. Jenna averages the three proposed costs and determines that she will
need to put $70,000 into the project budget for the website deliverable. What cost estimating
technique did Jenna use? - Answer vendor bid analysis



As the project manager, it's your responsibility to develop the project budget. Inputs to the
project budget do not include the - Answer stakeholder register



The project manager is estimating the cost of procuring a specialist on a part-time basis.
Because she doesn't know for sure whether the desired resource will be available when the
project begins, she has some uncertainty in developing the cost estimate. To account for the
uncertainty, she calculates an optimistic cost estimate, a pessimistic cost estimate, and a most
likely cost estimate. Next, she selects the average of these estimates. The technique she used to
develop the estimate is referred to as a - Answer none of these



Glenn is determining the project cost baseline by calculating the costs approved for each of the
project's work packages. Glenn is determining the: - Answer planned value



Tucker is the construction project manager for a new school building. He measures the project's
performance and progress by looking at the planned value, earned value, and actual cost.
Which method is Tucker using to determine the project performance? - Answer earned value
management

Información del documento

Subido en
16 de agosto de 2026
Número de páginas
4
Escrito en
2026/2027
Tipo
Examen
Contiene
Preguntas y respuestas
$12.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
COCOSOLUTIONS
4.2
(37)
Vendido
220
Seguidores
16
Artículos
9281
Última venta
3 días hace




Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes