Design and Construction Contracting (MCPPO
)Newest Exam Preparation With Complete Questions
And Correct Answers With Rationales Already
Graded A+Brand New Version!!
Question 1
Which Massachusetts statute is the primary bid law for public building
construction contracts exceeding $150,000?
A) M.G.L. c. 30, § 39M
B) M.G.L. c. 149A
C) M.G.L. c. 149
D) M.G.L. c. 7C, §§ 44-58
Answer: C
Explanation: M.G.L. c. 149 governs the competitive bidding process for
public building projects above the $150,000 threshold.
Question 2
Under M.G.L. c. 30, § 39M, which type of projects are regulated?
,2|Page
A) Public building construction
B) Public works and horizontal projects
C) Design-Build contracts only
D) Emergency procurements
Answer: B
Explanation: Section 39M applies to public works that are not building
construction, such as roads, bridges, and other horizontal infrastructure.
Question 3
What is the purpose of M.G.L. c. 7C, §§ 44-58?
A) To set wage rates for construction labor
B) To establish the Designer Selection Law (DSL)
C) To define the Uniform Procurement Act
D) To regulate demolition contracts
Answer: B
Explanation: These sections create the Designer Selection Law, which
governs how architects and engineers are chosen for public projects.
Question 4
Which delivery method allows the owner to contract with a single
entity that provides both design and construction services?
,3|Page
A) Design-Bid-Build
B) Construction Management at Risk
C) Design-Build
D) Traditional procurement
Answer: C
Explanation: Design-Build consolidates design and construction under
one contract, streamlining communication and responsibility.
Question 5
In Construction Management at Risk (CM at Risk), when does the
construction manager assume the risk of cost overruns?
A) After the design is complete and a GMP is issued
B) During the pre-design phase
C) Only if the owner changes the scope
D) Never; the risk remains with the owner
Answer: A
Explanation: The CM at Risk issues a Guaranteed Maximum Price (GMP)
after the design, assuming cost overrun risk beyond that amount.
Question 6
, 4|Page
At what project cost threshold is the hiring of an Owner's Project
Manager (OPM) mandatory?
A) $500,000
B) $1,000,000
C) $1,500,000
D) $2,000,000
Answer: C
Explanation: Massachusetts law requires an OPM for public
construction projects whose total cost equals or exceeds $1.5 million.
Question 7
What is the maximum retainage percentage permitted under
Massachusetts law for each progress payment?
A) 3%
B) 5%
C) 10%
D) 15%
Answer: B
Explanation: Massachusetts law caps retainage at a maximum of 5% of
each progress payment.