Escrito por estudiantes que aprobaron Inmediatamente disponible después del pago Leer en línea o como PDF ¿Documento equivocado? Cámbialo gratis 4,6 TrustPilot
logo-home
Document preview thumbnail
Vista previa 4 fuera de 201 páginas
Examen

MCPPO Design & Construction Contracting: Complete Exam Prep with 400+ Q&A

Document preview thumbnail
Vista previa 4 fuera de 201 páginas

Prepare for the Massachusetts MCPPO Design and Construction Contracting certification with this comprehensive exam guide featuring over 400 practice questions covering all essential topics. Master public bidding laws (M.G.L. c. 149, c. 149A, c. 30 § 39M), Designer Selection Law, Owner's Project Manager requirements, alternative project delivery methods (Design-Build, CM at Risk), and the Uniform Procurement Act. Each question includes detailed rationales explaining legal requirements and practical applications. Perfect for public officials, procurement officers, project managers, and construction professionals working with Massachusetts public projects. Updated with the latest regulations and MSBA requirements, this graded A+ resource will help you achieve MCPPO certification with confidence.

Vista previa del contenido

1|Page




Design and Construction Contracting (MCPPO
)Newest Exam Preparation With Complete Questions
And Correct Answers With Rationales Already
Graded A+Brand New Version!!




Question 1
Which Massachusetts statute is the primary bid law for public building
construction contracts exceeding $150,000?
A) M.G.L. c. 30, § 39M
B) M.G.L. c. 149A
C) M.G.L. c. 149
D) M.G.L. c. 7C, §§ 44-58


Answer: C
Explanation: M.G.L. c. 149 governs the competitive bidding process for
public building projects above the $150,000 threshold.


Question 2
Under M.G.L. c. 30, § 39M, which type of projects are regulated?

,2|Page


A) Public building construction
B) Public works and horizontal projects
C) Design-Build contracts only
D) Emergency procurements


Answer: B
Explanation: Section 39M applies to public works that are not building
construction, such as roads, bridges, and other horizontal infrastructure.


Question 3
What is the purpose of M.G.L. c. 7C, §§ 44-58?
A) To set wage rates for construction labor
B) To establish the Designer Selection Law (DSL)
C) To define the Uniform Procurement Act
D) To regulate demolition contracts


Answer: B
Explanation: These sections create the Designer Selection Law, which
governs how architects and engineers are chosen for public projects.


Question 4
Which delivery method allows the owner to contract with a single
entity that provides both design and construction services?

,3|Page


A) Design-Bid-Build
B) Construction Management at Risk
C) Design-Build
D) Traditional procurement


Answer: C
Explanation: Design-Build consolidates design and construction under
one contract, streamlining communication and responsibility.


Question 5
In Construction Management at Risk (CM at Risk), when does the
construction manager assume the risk of cost overruns?
A) After the design is complete and a GMP is issued
B) During the pre-design phase
C) Only if the owner changes the scope
D) Never; the risk remains with the owner


Answer: A
Explanation: The CM at Risk issues a Guaranteed Maximum Price (GMP)
after the design, assuming cost overrun risk beyond that amount.


Question 6

, 4|Page


At what project cost threshold is the hiring of an Owner's Project
Manager (OPM) mandatory?
A) $500,000
B) $1,000,000
C) $1,500,000
D) $2,000,000


Answer: C
Explanation: Massachusetts law requires an OPM for public
construction projects whose total cost equals or exceeds $1.5 million.


Question 7
What is the maximum retainage percentage permitted under
Massachusetts law for each progress payment?
A) 3%
B) 5%
C) 10%
D) 15%


Answer: B
Explanation: Massachusetts law caps retainage at a maximum of 5% of
each progress payment.

Información del documento

Subido en
16 de agosto de 2026
Número de páginas
201
Escrito en
2026/2027
Tipo
Examen
Contiene
Preguntas y respuestas
$25.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Vendido
2
Seguidores
2
Artículos
1446
Última venta
1 mes hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes