Although third level players do not have direct links to the primary players, they still exercise a great deal of influence on a construction project. - Answer True Historically, the construction industry has been looked on as incredibly efficient, safe and time saving. - Answer False What is the contractor responsible for providing? - Answer Labor, material, equipment, and expertise Subcontractors typically contract directly with the owner for special or trade specific work - Answer False In environmental Construction a contractor will probably be collaborating with ecologists, chemists, biologists, and other scientists - Answer True Who is the player in charge of the project from beginning to end? - Answer Project Manager Through their use of stone and stonemasons, the Greeks pioneered the development of Arches and Domes - Answer False Which of the following are considered third level Players? - Answer Trade Associations, Local, State and Federal Gov. The industrial revolution better defined the roles of various professions involved in construction wherein contractors took on greater responsibility for technical coordination - Answer False With what is the financial officer primarily concerned - Answer the creation of the budget The owner on a construction project is accountable for which of the following - Answer Developing the program to outline the needs of the end users Second level players in the construction industry exercise great influence on a project through direct contracts with the owner, designer and contractor - Answer False

Vista previa del contenido

Construction Management Final Review
Questions and Answers.
Although third level players do not have direct links to the primary players, they still exercise a
great deal of influence on a construction project. - Answer True



Historically, the construction industry has been looked on as incredibly efficient, safe and time
saving. - Answer False



What is the contractor responsible for providing? - Answer Labor, material, equipment, and
expertise



Subcontractors typically contract directly with the owner for special or trade specific work -
Answer False



In environmental Construction a contractor will probably be collaborating with ecologists,
chemists, biologists, and other scientists - Answer True



Who is the player in charge of the project from beginning to end? - Answer Project Manager



Through their use of stone and stonemasons, the Greeks pioneered the development of Arches
and Domes - Answer False



Which of the following are considered third level Players? - Answer Trade Associations, Local,
State and Federal Gov.



The industrial revolution better defined the roles of various professions involved in construction
wherein contractors took on greater responsibility for technical coordination - Answer False



With what is the financial officer primarily concerned - Answer the creation of the budget



The owner on a construction project is accountable for which of the following - Answer
Developing the program to outline the needs of the end users



Second level players in the construction industry exercise great influence on a project through
direct contracts with the owner, designer and contractor - Answer False

, The prime contractor on a construction project is the contractor that has a contract directly with
the owner - Answer True



Maintaining a relationship with upper management is one of the attributes of leadership
abilities - Answer Yes



Which of the following are Three Levels of skill developed in the middle ages - Answer
Apprentice, Journeyman, Master



There are primarily three types of architects designers, project architects, and specification
writers - Answer True



In construction a finite time frame associated with a completion date is one of the prime
characteristics of a project. - Answer True



In Construction a program is a set of instruction telling the contractor how to build the building -
Answer False



What is used to monitor the quality of a project - Answer Specifications and Drawings



What is used to monitor the scope of a project - Answer The Project program



What is not considered a construction management function - Answer Funding the Project



What is used to monitor the cost of the project - Answer The Estimate



What is used to monitor the safety of a project - Answer Potential Risk Indemnification



When an owner contracts with a architect to design a project and then places the contract out
for contractors to bid on. This is the Design-Build delivery system - Answer False



What is not a construction management job description - Answer Electrical Subcontractor



What is used to monitor the Time of the project - Answer The schedule



Construction management at risk requires the construction manager to make design inputs as
well as construct the project as a general contractor - Answer True

Información del documento

Subido en
16 de agosto de 2026
Número de páginas
12
Escrito en
2026/2027
Tipo
Examen
Contiene
Preguntas y respuestas
$13.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
COCOSOLUTIONS
4.2
(37)
Vendido
220
Seguidores
16
Artículos
9281
Última venta
3 días hace




Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes