Examen

WGU E055 Project Scoping and Scheduling Objective Assessment (OA) V1 & V2 | 106 Study Questions with Correct Answers, Detailed Rationales & Scheduling Calculations | 2026/2027.

Document preview thumbnail
Vista previa 4 fuera de 47 páginas

WGU E055 Project Scoping and Scheduling Objective Assessment (OA) V1 & V2 | 106 Study Questions with Correct Answers, Detailed Rationales & Scheduling Calculations | 2026/2027.

Vista previa del contenido

WGU E055 Project Scoping and Scheduling Objective Assessment (OA) V1 & V2 | 106 Study Questions
with Correct Answers, Detailed Rationales & Scheduling Calculations | 2026/2027.


2026 OA-Style Practice Assessment
53 Original Multiple-Choice Questions with Answers and Rationales

This original practice assessment is aligned with the E055 competencies you provided and builds
on the foundational project-management concepts introduced in WGU E054. It is not a
reproduction of WGU’s secure OA.




Domain 1: Project Scope Planning and Definition
Question 1

During project planning, the project manager must document how scope will be defined,
validated, and controlled. Which document should be developed?

A. Requirements traceability matrix
B. Scope management plan
C. Project charter
D. Activity list

Correct answer: B. Scope management plan

Rationale: The scope management plan establishes the procedures for defining, developing,
validating, and controlling project and product scope. The charter authorizes the project but does
not contain detailed scope-management procedures.



Question 2

A company is developing a new mobile banking application. Which item represents product
scope?

A. Training the development team
B. Creating the project schedule
C. Providing biometric authentication
D. Conducting weekly status meetings

Correct answer: C. Providing biometric authentication

,Rationale: Product scope describes the features and functions of the deliverable. Training,
scheduling, and meetings are project work and therefore belong to project scope.



Question 3

Which item is an example of project scope?

A. The application must support fingerprint authentication
B. The building must contain six conference rooms
C. The project team must test and deploy the application
D. The vehicle must achieve 40 miles per gallon

Correct answer: C. The project team must test and deploy the application

Rationale: Project scope describes the work required to produce the deliverable. The other
choices describe product characteristics or requirements.



Question 4

A project scope statement specifies that employee payroll processing is included, but contractor
payments are excluded. What is the primary purpose of this distinction?

A. Establish the project budget
B. Define the project boundaries
C. Identify the critical path
D. Assign project resources

Correct answer: B. Define the project boundaries

Rationale: Explicit inclusions and exclusions establish what the project will and will not deliver.
Clear boundaries reduce misunderstandings and uncontrolled scope expansion.



Question 5

During requirements gathering, two department managers provide conflicting requirements.
What should the project manager do first?

A. Select the less expensive requirement
B. Include both requirements in the scope baseline

,C. Facilitate clarification and resolution with the relevant stakeholders
D. Ask the project team to select the preferred requirement

Correct answer: C. Facilitate clarification and resolution with the relevant stakeholders

Rationale: Conflicting requirements should be analyzed and reconciled with the stakeholders
who own or influence them. The project manager should not make an unsupported decision or
baseline unresolved requirements.



Question 6

Which document links each requirement to its source, business objective, deliverable, and
verification method?

A. Requirements traceability matrix
B. Milestone list
C. Schedule baseline
D. Resource calendar

Correct answer: A. Requirements traceability matrix

Rationale: The requirements traceability matrix tracks requirements from their origin through
implementation and validation. It helps ensure that every approved requirement is addressed.



Question 7

A project manager records that regulatory approval will be received within 30 days. How should
this statement be classified?

A. Deliverable
B. Assumption
C. Product requirement
D. Work package

Correct answer: B. Assumption

Rationale: An assumption is a factor treated as true for planning even though it has not been
fully proven. If approval timing is uncertain, it should also be monitored as a potential risk.



Question 8

, A project must be completed before the organization’s current software license expires. How
should this condition be classified?

A. Constraint
B. Assumption
C. Acceptance criterion
D. Decomposition rule

Correct answer: A. Constraint

Rationale: A constraint limits project options. A mandatory completion date restricts the
schedule and must be considered during planning.




Domain 2: Work Breakdown Structure Creation
Question 9

What is the principal purpose of a work breakdown structure?

A. Display reporting relationships
B. Organize the total project scope into manageable components
C. Show only the activities on the critical path
D. Document approved project risks

Correct answer: B. Organize the total project scope into manageable components

Rationale: A WBS hierarchically decomposes the complete project scope into progressively
smaller, manageable components.



Question 10

What is the lowest level of a work breakdown structure?

A. Milestone
B. Control account
C. Work package
D. Schedule activity

Correct answer: C. Work package

Información del documento

Subido en
13 de agosto de 2026
Número de páginas
47
Escrito en
2026/2027
Tipo
Examen
Contiene
Preguntas y respuestas
$18.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Wiseman
3.9
(1649)
Vendido
8245
Seguidores
3899
Artículos
30698
Última venta
2 horas hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes