1. Project schedules should be updated at least ______________ once the
project has started,
- Correct Answer: Weekly
2. The size and route of sanitary sewer lines are indicated in the ________
drawings.
- Correct Answer: P Drawing
3. Which of the following documents is used to track daily activities at the
work site?
- Correct Answer: Project Log
4. Which of the following is submitted to request clarification, supplemental
information, or approval of material substitutions?
- Correct Answer: RFI Form
5. M drawings indicate the size and route of:
- Correct Answer: Air Handler Units, Chilled Water Piping,
Refrigerant Piping, HVAC System Ducts
6. Which of the following testers should be used for optical fiber
identification?
- Correct Answer: Visual Fault Locator (VFL)
,7. What is the first step that you should take to verify the existing
infrastructure before you begin a retrofit?
- Correct Answer: Review the existing documentation with the
customer.
8. A graphical representation of a building space, or object prepared with
adequate detail to convey design information in a manner to serve as a
guide for construction.
- Correct Answer: A Drawing
9. A graphical representation of the electrical components of a construction
project (e.g., power distribution, lighting).
- Correct Answer: E Drawing
10.Abbreviation for fire protection drawings
- Correct Answer: FP Drawing
11.Abbreviation for mechanical drawings.
- Correct Answer: M Drawing
12.Abbreviation for plumbing drawings
- Correct Answer: P Drawing
13.Abbreviation for structural drawings
- Correct Answer: S Drawing
14.This document covers the requirements for the ICT systems team and lists
all of the elements of the installation.
- Correct Answer: Scope of Work (SOW)
15.Abbreviation for telecommunications, security, and audiovisual drawings
, - Correct Answer: T Drawing
16.Layer of a telecommunication drawing that contains campus or site
information such as exterior pathways and interbuilding systems
- Correct Answer: T0 Layer
17.Layer of a telecommunication drawing that contains building information.
- Correct Answer: T1 Layer
18.Layer of a telecommunication drawing that contains serving zone
information
- Correct Answer: T2 Layer
19.Layer of a telecommunication drawing that contains information about
telecommunications rooms.
- Correct Answer: T3 Layer
20.Layer of a telecommunication drawing that contains the detail drawings.
- Correct Answer: T4 Layer
21.Layer of a telecommunication drawing that contains schedules and
spreadsheets.
- Correct Answer: T5 Layer
22.A list of the quantity and specific types of materials to be used on a project.
This list also should consider miscellaneous hardware.
- Correct Answer: BOM
23.Abbreviation for operations and maintenance
- Correct Answer: O&M