Escrito por estudiantes que aprobaron Inmediatamente disponible después del pago Leer en línea o como PDF ¿Documento equivocado? Cámbialo gratis 4,6 TrustPilot
logo-home
Document preview thumbnail
Vista previa 4 fuera de 39 páginas
Examen

Florida Certified General Contractor Examination Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf

Document preview thumbnail
Vista previa 4 fuera de 39 páginas

Florida Certified General Contractor Examination Questions And Correct Answers (Verified Answers) Plus Rationales 2026 Q&A | Instant Download Pdf

Vista previa del contenido

Florida Certified General Contractor
Examination Questions And Correct
Answers (Verified Answers) Plus
Rationales 2026 Q&A | Instant
Download Pdf
1. A general contractor is preparing to procure a large quantity of structural
steel for a high-rise project. The project timeline is tight, and the primary
concern is ensuring the material meets strict engineering tolerances. Which
procurement planning step should be prioritized first?
A. Issuing a request for proposal to all qualified steel fabricators.
B. Developing a comprehensive scope of work and technical specifications.
C. Conducting market research to identify potential suppliers and lead
times.
D. Preparing a detailed cost estimate for the steel package.
Correct Answer: Conducting market research to identify potential
suppliers and lead times. Rationale: Market research is the foundational
step in procurement planning. It informs the project team about supplier
capabilities, current market conditions, and realistic lead times, which are
critical for a time-sensitive project with strict tolerances. Without this,
specifications and costs may be unrealistic.
2. An ethics violation most likely occurs when a contractor’s procurement
officer:
A. Accepts a modest meal from a supplier during a pre-bid meeting.
B. Shares a competitor's sealed bid information with a favored supplier
before the bid opening.
C. Attends a supplier-hosted educational seminar on new building materials.
D. Requests a formal quote from a supplier who has done previous work for

, the contractor.
Correct Answer: Shares a competitor's sealed bid information with a
favored supplier before the bid opening. Rationale: This constitutes a
serious breach of ethics, involving bid rigging and anti-competitive behavior.
It gives an unfair advantage to one supplier and is a violation of public trust
and fair procurement laws.
3. In the context of construction sourcing, "vertical integration" refers to a
contractor's decision to:
A. Use multiple suppliers for the same material to ensure redundancy.
B. Own or control the supply chain elements, such as a concrete batch plant
or a lumber mill.
C. Partner with a single supplier for all materials on a project.
D. Subcontract all work to specialty trade contractors.
Correct Answer: Own or control the supply chain elements, such as a
concrete batch plant or a lumber mill. Rationale: Vertical integration is a
strategic decision where a company takes ownership of its suppliers or
distributors. For a contractor, this means owning the sources of raw
materials or manufacturing capabilities to gain greater control over cost
and availability.
4. Specifications that require the use of a specific proprietary product, such as
a unique roofing membrane, without providing an "or equal" clause are
considered:
A. Performance-based specifications.
B. Proprietary or sole-source specifications.
C. Design-build specifications.
D. Descriptive specifications.
Correct Answer: Proprietary or sole-source specifications. Rationale: These
specifications are restrictive and name a specific manufacturer or product.
While sometimes necessary, they are generally discouraged in public
procurement due to their anti-competitive nature, unless a sole-source
justification is documented.

,5. For a large public school project, the procurement method that provides
the greatest opportunity for input on design and construction solutions
from the contractor is:
A. Design-Bid-Build.
B. Construction Manager at Risk (CMAR).
C. Low-bid procurement.
D. Unit price contracting.
Correct Answer: Construction Manager at Risk (CMAR). Rationale: CMAR is
a collaborative project delivery method where the construction manager is
brought on early in the design phase to provide input on constructability,
cost, and scheduling. This is a form of procurement that emphasizes
qualifications and collaboration over just the lowest initial price.
6. The primary purpose of a bid bond is to:
A. Guarantee the contractor will complete the project on time.
B. Cover any cost overruns during the construction phase.
C. Provide a warranty for materials and workmanship.
D. Ensure the contractor will enter into a contract if awarded and provide
the required performance bonds.
Correct Answer: Ensure the contractor will enter into a contract if
awarded and provide the required performance bonds. Rationale: A bid
bond is a form of surety that protects the project owner. If the winning
bidder refuses to sign the contract or provide the necessary performance
and payment bonds, the owner can claim the bid bond amount to cover the
cost of awarding the contract to the next bidder.
7. When evaluating proposals for a complex, federally funded water treatment
plant, the selection committee should weigh technical approach and
experience more heavily than price because:
A. Federal law prohibits price from being a consideration.
B. The lowest price always guarantees the best value.
C. The project's high complexity makes contractor qualifications and
proposed methodology critical to success, and a poorly planned low bid
could lead to project failure.

, D. The contract will be awarded solely on a random lottery system.
Correct Answer: The project's high complexity makes contractor
qualifications and proposed methodology critical to success, and a poorly
planned low bid could lead to project failure. Rationale: For highly complex
projects, a "best value" evaluation is appropriate. This means the
contracting authority considers technical merit, past performance, and
management approach alongside cost to ensure they select a contractor
capable of successfully executing a difficult project.
8. A contractor's project manager receives a change order request from the
owner to add a new wing to the building. The first step in formal contract
administration for this change is to:
A. Begin construction on the new wing to maintain the schedule.
B. Issue a formal change order to the owner for signature.
C. Prepare a detailed cost and schedule impact analysis and submit a
proposal.
D. Notify the subcontractors that a change is coming.
Correct Answer: Prepare a detailed cost and time impact analysis and
submit a proposal. Rationale: A change order is a formal amendment to the
contract. The process is initiated by the contractor preparing a proposal that
details the cost, overhead, profit, and time impacts of the change. This
proposal is then reviewed and negotiated before a formal change order is
executed.
9. An effective negotiation strategy for a general contractor when discussing a
large material supply contract is to:
A. Focus solely on achieving the absolute lowest unit price.
B. Build a collaborative relationship and focus on a "win-win" solution,
considering delivery schedules, payment terms, and quality.
C. Use threats of legal action to force the supplier into compliance.
D. Refuse to compromise on any initial demand.
Correct Answer: Build a collaborative relationship and focus on a "win-
win" solution, considering delivery schedules, payment terms, and
quality. Rationale: Effective negotiations are not zero-sum. By

Información del documento

Subido en
15 de julio de 2026
Número de páginas
39
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$22.89

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
masterystudyhub
5.0
(1)
Vendido
29
Seguidores
1
Artículos
9408
Última venta
2 días hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes