⩥ Using drawing, what is the elevation of "P?"
Answer: 15 feet and 7 inches.
⩥ When is the best time to design a job-specific material handling plan?
Answer: The best time is before the job starts.
⩥ Assume you are working with a 40 foot run of pipe with 1/8ths inches
of pitch per foot. What is the overall amount of pitch over the course of
the run?
Answer: 5 inches
⩥ Which of the following purchasing procedures is MOST likely to
reduce material handling time?
Answer: Bag and tag all materials as appropriate.
⩥ When rigging for lifting, it is important to know the weight of what is
being hoisted to ensure the safety of workers, equipment and the client's
property. The formula below allows the calculation of load weights.
Formula: Weight Per Foot = (Outside Diameter) x (Wall Thickness) x
,(10)You are rigging to hoist a load of pipe. Given the following
information, what would be the total weight of the pipe? Outside
Diameter = 6 inches; Wall Thickness = 5/8 inches; Length = 4 feet
Answer: 150 pounds
⩥ Which one of the following skills is MOST beneficial when
interacting with other employees?
Answer: Effective listening.
⩥ Which of the following is NOT a characteristic of a good leader?
Answer: Dictatorial.
⩥ Assume that each of the steps below must be taken at some point
when ordering materials:
a. call supply house with lists.
b. make a drawing.
c. list materials.
d. call for availability and prices. What is the proper order or sequence
of these steps?
Answer: b, c, d, a
⩥ You have an apprentice on your project that is struggling to do their
job. What is theBEST approach to helping them?
Answer: Have them work with an experienced journeyman.
, ⩥ If a confined space is shown to be oxygen deficient, which of the
following should you do?
Answer: Purge with fresh air.
⩥ What is the difference between a CBA and a Job Specific labor
agreement?
Answer: All of the above
⩥ A pipe has a 9 foot above finished floor (AFF) center line elevation
and a benchmark that is 2 feet above finished floor (AFF). What is
center line of the pipe above benchmark?
Answer: 7 feet
⩥ Which of the following is NOT considered a direct job cost?
Answer: Home office overhead.
⩥ During the course of a project you have noticed that there is a greater
than normal number of Change Orders being submitted. Which of the
following is the MOST important step that you need to take?
Answer: Maintain an accurate Job Log in case specific questions are
asked about why the project was completed in the way it was
CERTIFICATION REVIEW 2026 TESTED
ANSWERS GRADED A+
⩥ Using drawing, what is the elevation of "P?"
Answer: 15 feet and 7 inches.
⩥ When is the best time to design a job-specific material handling plan?
Answer: The best time is before the job starts.
⩥ Assume you are working with a 40 foot run of pipe with 1/8ths inches
of pitch per foot. What is the overall amount of pitch over the course of
the run?
Answer: 5 inches
⩥ Which of the following purchasing procedures is MOST likely to
reduce material handling time?
Answer: Bag and tag all materials as appropriate.
⩥ When rigging for lifting, it is important to know the weight of what is
being hoisted to ensure the safety of workers, equipment and the client's
property. The formula below allows the calculation of load weights.
Formula: Weight Per Foot = (Outside Diameter) x (Wall Thickness) x
,(10)You are rigging to hoist a load of pipe. Given the following
information, what would be the total weight of the pipe? Outside
Diameter = 6 inches; Wall Thickness = 5/8 inches; Length = 4 feet
Answer: 150 pounds
⩥ Which one of the following skills is MOST beneficial when
interacting with other employees?
Answer: Effective listening.
⩥ Which of the following is NOT a characteristic of a good leader?
Answer: Dictatorial.
⩥ Assume that each of the steps below must be taken at some point
when ordering materials:
a. call supply house with lists.
b. make a drawing.
c. list materials.
d. call for availability and prices. What is the proper order or sequence
of these steps?
Answer: b, c, d, a
⩥ You have an apprentice on your project that is struggling to do their
job. What is theBEST approach to helping them?
Answer: Have them work with an experienced journeyman.
, ⩥ If a confined space is shown to be oxygen deficient, which of the
following should you do?
Answer: Purge with fresh air.
⩥ What is the difference between a CBA and a Job Specific labor
agreement?
Answer: All of the above
⩥ A pipe has a 9 foot above finished floor (AFF) center line elevation
and a benchmark that is 2 feet above finished floor (AFF). What is
center line of the pipe above benchmark?
Answer: 7 feet
⩥ Which of the following is NOT considered a direct job cost?
Answer: Home office overhead.
⩥ During the course of a project you have noticed that there is a greater
than normal number of Change Orders being submitted. Which of the
following is the MOST important step that you need to take?
Answer: Maintain an accurate Job Log in case specific questions are
asked about why the project was completed in the way it was