You are installing a 250 fpm freight elevator. what type of buffers
should you use? ---------CORRECT ANSWER-----------------oil buffers
You are working in a pit deeper than normal. what can you do to bring
the buffers up to the proper height? ---------CORRECT ANSWER------------
-----buffer stands
What document will tell you if you need buffer channels? ---------
CORRECT ANSWER-----------------final layout
When installing a reduced stroke buffer, what additional component is
required? ---------CORRECT ANSWER-----------------speed limiting device
You just attached a governor tension sheave to a rail. what must be
done to finalize its position? ---------CORRECT ANSWER-----------------
check for plumb and tighten all bolts.
,You are installing pit equip for a high rise elevator. which of the
following is required for an 800 fpm car? ---------CORRECT ANSWER------
-----------compensating sheave tie down
You have installed the comp rope sheave. what must you do to prepare
for comp rope install? ---------CORRECT ANSWER-----------------block the
comp sheave above normal position
You are about to perform maintenance on pit equip. what is required
for oil buffers? ---------CORRECT ANSWER-----------------check the oil level
You are working in a pit 72" deep. what does asme require regarding
stop switches? ---------CORRECT ANSWER-----------------a second stop
switch must be installed 47" above the pit floor
What would you use to connect round rails? ---------CORRECT ANSWER--
---------------bushings
, You are moving rails to storage. what should be taken into
consideration? ---------CORRECT ANSWER-----------------floor load
capacity
You must stack rails on the floor of a storage room. how do they go? ----
-----CORRECT ANSWER-----------------on their backs
You are installing rails with little distance between the beam and rail.
what type of bracket must you use? ---------CORRECT ANSWER-------------
----angle bracket
You must fasten a bracket to a brick wall. how do you do it? ---------
CORRECT ANSWER-----------------(quick bolt that bitch) use a threaded
rod and thru plate it
When installing formed guide rails, what must be done to ensure that
the guide rail is secured to the rail bracket? ---------CORRECT ANSWER---
--------------rail clip heel must contact the edge of the rail
QUESTIONS AND CORRECT ANSWERS | VERIFIED
ANSWERS | BRAND NEW VERSION!
You are installing a 250 fpm freight elevator. what type of buffers
should you use? ---------CORRECT ANSWER-----------------oil buffers
You are working in a pit deeper than normal. what can you do to bring
the buffers up to the proper height? ---------CORRECT ANSWER------------
-----buffer stands
What document will tell you if you need buffer channels? ---------
CORRECT ANSWER-----------------final layout
When installing a reduced stroke buffer, what additional component is
required? ---------CORRECT ANSWER-----------------speed limiting device
You just attached a governor tension sheave to a rail. what must be
done to finalize its position? ---------CORRECT ANSWER-----------------
check for plumb and tighten all bolts.
,You are installing pit equip for a high rise elevator. which of the
following is required for an 800 fpm car? ---------CORRECT ANSWER------
-----------compensating sheave tie down
You have installed the comp rope sheave. what must you do to prepare
for comp rope install? ---------CORRECT ANSWER-----------------block the
comp sheave above normal position
You are about to perform maintenance on pit equip. what is required
for oil buffers? ---------CORRECT ANSWER-----------------check the oil level
You are working in a pit 72" deep. what does asme require regarding
stop switches? ---------CORRECT ANSWER-----------------a second stop
switch must be installed 47" above the pit floor
What would you use to connect round rails? ---------CORRECT ANSWER--
---------------bushings
, You are moving rails to storage. what should be taken into
consideration? ---------CORRECT ANSWER-----------------floor load
capacity
You must stack rails on the floor of a storage room. how do they go? ----
-----CORRECT ANSWER-----------------on their backs
You are installing rails with little distance between the beam and rail.
what type of bracket must you use? ---------CORRECT ANSWER-------------
----angle bracket
You must fasten a bracket to a brick wall. how do you do it? ---------
CORRECT ANSWER-----------------(quick bolt that bitch) use a threaded
rod and thru plate it
When installing formed guide rails, what must be done to ensure that
the guide rail is secured to the rail bracket? ---------CORRECT ANSWER---
--------------rail clip heel must contact the edge of the rail