CONSTRUCTION PROJECT PLANNING & SCHEDULING
Full Practice Exam (2026 Edition)
Total Questions: 50 | Passing Score: 75% | Time: 90
minutes
SECTION 1: CPM & NETWORK LOGIC (Questions 1–10)
1. Which relationship type requires Activity B to finish
before Activity A can start?
A) FS
B) FF
C) SS
D) SF
VERIFIED ANSWER: D) SF (Start-to-Finish)
Rationale: SF is rare but reverses the dependency: B
finishes so A can start.
2. If Activity A (5 days) and B (7 days) overlap with SS+2
lag, what is the earliest B can finish?
A) 5 days
B) 7 days
C) 9 days
D) 12 days
,VERIFIED ANSWER: C) 9 days
Rationale: B starts at time 2 (after A starts), duration 7 →
EF = 9.
3. Which is NOT a required element for a logic-driven
CPM schedule?
A) Unique activity ID
B) Calendar assignment
C) Resource cost
D) Predecessor/successor links
VERIFIED ANSWER: C) Resource cost
Rationale: Cost is for EVM, not CPM logic.
4. What does a negative total float of -3 days indicate?
A) Project will finish 3 days early
B) Milestone is constrained earlier than logic allows
C) Free float is also negative
D) Schedule has no critical path
VERIFIED ANSWER: B) Milestone is constrained earlier
than logic allows
Rationale: Negative float = imposed date earlier than
calculated early finish.
5. In a PDM network, what is the maximum number of
logical relationships between two activities?
A) 1
,B) 2
C) 3
D) 4
VERIFIED ANSWER: D) 4
Rationale: FS, SS, FF, SF all possible between same pair.
6. Which float is consumed without affecting successors?
A) Total float
B) Free float
C) Project float
D) Independent float
VERIFIED ANSWER: B) Free float
Rationale: Free float = delay available before any
successor’s early start is impacted.
7. A hammock activity’s duration is calculated by:
A) Resource loading
B) Difference between two dates
C) Fixed duration entered by user
D) Monte Carlo simulation
VERIFIED ANSWER: B) Difference between two dates
Rationale: Hammock stretches from its start anchor to
end anchor dates.
, 8. What is the critical path’s total float?
A) Positive
B) Zero or negative
C) Equal to project float
D) Always zero
VERIFIED ANSWER: B) Zero or negative
Rationale: Critical path has minimum float (can be
negative under constrained dates).
9. If an activity has 2 days free float and 5 days total
float, delaying it by 3 days will:
A) Delay project by 1 day
B) Delay successors by 1 day
C) Delay project by 0 days, successors by 1 day
D) Delay project by 3 days
VERIFIED ANSWER: C) Delay project by 0 days,
successors by 1 day
Rationale: 3 days uses all free float (2 days) + 1 day of
total float → impacts successors but not project (since
total float not fully consumed).
10. Which best describes a mandatory dependency?
A) Preferred sequence
B) Legal requirement
Full Practice Exam (2026 Edition)
Total Questions: 50 | Passing Score: 75% | Time: 90
minutes
SECTION 1: CPM & NETWORK LOGIC (Questions 1–10)
1. Which relationship type requires Activity B to finish
before Activity A can start?
A) FS
B) FF
C) SS
D) SF
VERIFIED ANSWER: D) SF (Start-to-Finish)
Rationale: SF is rare but reverses the dependency: B
finishes so A can start.
2. If Activity A (5 days) and B (7 days) overlap with SS+2
lag, what is the earliest B can finish?
A) 5 days
B) 7 days
C) 9 days
D) 12 days
,VERIFIED ANSWER: C) 9 days
Rationale: B starts at time 2 (after A starts), duration 7 →
EF = 9.
3. Which is NOT a required element for a logic-driven
CPM schedule?
A) Unique activity ID
B) Calendar assignment
C) Resource cost
D) Predecessor/successor links
VERIFIED ANSWER: C) Resource cost
Rationale: Cost is for EVM, not CPM logic.
4. What does a negative total float of -3 days indicate?
A) Project will finish 3 days early
B) Milestone is constrained earlier than logic allows
C) Free float is also negative
D) Schedule has no critical path
VERIFIED ANSWER: B) Milestone is constrained earlier
than logic allows
Rationale: Negative float = imposed date earlier than
calculated early finish.
5. In a PDM network, what is the maximum number of
logical relationships between two activities?
A) 1
,B) 2
C) 3
D) 4
VERIFIED ANSWER: D) 4
Rationale: FS, SS, FF, SF all possible between same pair.
6. Which float is consumed without affecting successors?
A) Total float
B) Free float
C) Project float
D) Independent float
VERIFIED ANSWER: B) Free float
Rationale: Free float = delay available before any
successor’s early start is impacted.
7. A hammock activity’s duration is calculated by:
A) Resource loading
B) Difference between two dates
C) Fixed duration entered by user
D) Monte Carlo simulation
VERIFIED ANSWER: B) Difference between two dates
Rationale: Hammock stretches from its start anchor to
end anchor dates.
, 8. What is the critical path’s total float?
A) Positive
B) Zero or negative
C) Equal to project float
D) Always zero
VERIFIED ANSWER: B) Zero or negative
Rationale: Critical path has minimum float (can be
negative under constrained dates).
9. If an activity has 2 days free float and 5 days total
float, delaying it by 3 days will:
A) Delay project by 1 day
B) Delay successors by 1 day
C) Delay project by 0 days, successors by 1 day
D) Delay project by 3 days
VERIFIED ANSWER: C) Delay project by 0 days,
successors by 1 day
Rationale: 3 days uses all free float (2 days) + 1 day of
total float → impacts successors but not project (since
total float not fully consumed).
10. Which best describes a mandatory dependency?
A) Preferred sequence
B) Legal requirement