OPSM 4820 Exam 3 Questions With New Update Solutions /. ____________________ concerns execution of material plans. a. ERP b. MRP c. MPC d. PAC e. "a" and "d" - Answer-d. PAC /.In purchasing, ____________ is seen as a professional activity where information networks, relationships, terms, and conditions are established with vendor companies outside of production activity control, while release of individual orders and follow-up activities are a part of production activity control. a. warehousing b. inventory c. procurement d. "a" and "b" e. none - Answer-c. procurement /._____________ includes where things are, notification of operational completions, count verifications, order closeout and disposition, and accounting data. c. feedback b. status information d. "a" and "b" a. warning signals e. none - Answer-b. status information /._____________ help flag inadequacies in material and capacity plans e. none d. "a" and "b" c. feedback a. warning signals b. status information - Answer-a. warning signals /.Formal systems for shop-floor control are largely unnecessary under ______. Release of orders is still part of PAC, but the typical "shop order" with associated paperwork isn't maintained. e. PAC d. MPC b. ERP c. JIT a. MRP - Answer-c. JIT /.Vendor scheduling under __________ can be a bit more complex than shop-floor control, but if the relationship with the vendors is good, differences are very small. e. PAC b. ERP c. JIT a. MRP d. MPC - Answer-c. JIT /.The primary __________ objective is managing the materials flow to meet _________ plans. a. PAC, MPC b. MPC, PAC c. PAC, MRP d. MRP, PAC e. none - Answer-a. PAC, MPC /.The choice of objectives for ___________ reflects the firm's position vis-à-vis its competitors, customers, and vendors. e. JIT d. MRP b. APC a. PAC c. MPC - Answer-a. PAC /._________ is an approach to shop-floor control. b. priority sequencing rules c. theory of constraints scheduling a. gantt charts d. all e. none - Answer-d. all - gantt charts - theory of constraints scheduling - priority sequencing rules /.Reducing ________ means shorter lead time and, therefore, reduced work-in-process inventory. a. demand d. "a" and "c" e. none c. inventory b. queue time - Answer-b. queue time /.__________ show a schedule in production activity control techniques. c. bar charts b. priority sequencing rules d. "a" and "c" e. none a. gantt charts - Answer-d. "a" and "c" - gantt charts - bar charts /.________________ determine which job to run next at a work center in production activity control techniques. d. "a" and "c" c. bar charts e. none a. gantt charts b. priority sequencing rules - Answer-b. priority sequencing rules /.In an ____________ system, each shop order would be a scheduled receipt for the part. As such, the scheduled receipt has a due date. c. JIT d. MPC e. TOC b. ERP a. MRP - Answer-a. MRP /.Theory of constraints (TOC) scheduling systems were viewed as a replacement of an integrated MPC system. b. ERP a. MRP e. TOC d. MPC c. JIT - Answer-d. MPC /.Any resource whose capacity is equal to or less than the required demand is referred to as a _____________ . d. "a" and "c" a. bottleneck c. constraint e. none b. limited - Answer-a. bottleneck /.The objective of __________ scheduling is to maximize throughput. e. TOC d. MPC c. JIT b. ERP a. MRP - Answer-e. TOC

Vista previa del contenido

OPSM 4820 Exam 3 Questions With
New Update Solutions
/. ____________________ concerns execution of material plans.
a. ERP
b. MRP
c. MPC
d. PAC
e. "a" and "d" - Answer-d. PAC

/.In purchasing, ____________ is seen as a professional activity where information
networks, relationships, terms, and conditions are established with vendor companies
outside of production activity control, while release of individual orders and follow-up
activities are a part of production activity control.
a. warehousing
b. inventory
c. procurement
d. "a" and "b"
e. none - Answer-c. procurement

/._____________ includes where things are, notification of operational completions,
count verifications, order closeout and disposition, and accounting data.
c. feedback
b. status information
d. "a" and "b"
a. warning signals
e. none - Answer-b. status information

/._____________ help flag inadequacies in material and capacity plans
e. none
d. "a" and "b"
c. feedback
a. warning signals
b. status information - Answer-a. warning signals

/.Formal systems for shop-floor control are largely unnecessary under ______. Release
of orders is still part of PAC, but the typical "shop order" with associated paperwork isn't
maintained.
e. PAC
d. MPC
b. ERP
c. JIT
a. MRP - Answer-c. JIT

,/.Vendor scheduling under __________ can be a bit more complex than shop-floor
control, but if the relationship with the vendors is good, differences are very small.
e. PAC
b. ERP
c. JIT
a. MRP
d. MPC - Answer-c. JIT

/.The primary __________ objective is managing the materials flow to meet _________
plans.
a. PAC, MPC
b. MPC, PAC
c. PAC, MRP
d. MRP, PAC
e. none - Answer-a. PAC, MPC

/.The choice of objectives for ___________ reflects the firm's position vis-à-vis its
competitors, customers, and vendors.
e. JIT
d. MRP
b. APC
a. PAC
c. MPC - Answer-a. PAC

/._________ is an approach to shop-floor control.
b. priority sequencing rules
c. theory of constraints scheduling
a. gantt charts
d. all
e. none - Answer-d. all
- gantt charts
- theory of constraints scheduling
- priority sequencing rules

/.Reducing ________ means shorter lead time and, therefore, reduced work-in-process
inventory.
a. demand
d. "a" and "c"
e. none
c. inventory
b. queue time - Answer-b. queue time

/.__________ show a schedule in production activity control techniques.
c. bar charts
b. priority sequencing rules

, d. "a" and "c"
e. none
a. gantt charts - Answer-d. "a" and "c"
- gantt charts
- bar charts

/.________________ determine which job to run next at a work center in production
activity control techniques.
d. "a" and "c"
c. bar charts
e. none
a. gantt charts
b. priority sequencing rules - Answer-b. priority sequencing rules

/.In an ____________ system, each shop order would be a scheduled receipt for the
part. As such, the scheduled receipt has a due date.
c. JIT
d. MPC
e. TOC
b. ERP
a. MRP - Answer-a. MRP

/.Theory of constraints (TOC) scheduling systems were viewed as a replacement of an
integrated MPC system.
b. ERP
a. MRP
e. TOC
d. MPC
c. JIT - Answer-d. MPC

/.Any resource whose capacity is equal to or less than the required demand is referred
to as a _____________ .
d. "a" and "c"
a. bottleneck
c. constraint
e. none
b. limited - Answer-a. bottleneck

/.The objective of __________ scheduling is to maximize throughput.
e. TOC
d. MPC
c. JIT
b. ERP
a. MRP - Answer-e. TOC

Información del documento

Subido en
22 de abril de 2026
Número de páginas
17
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$15.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Brainariam
3.4
(30)
Vendido
160
Seguidores
7
Artículos
8386
Última venta
2 semanas hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes