• ¿Documento equivocado? Cámbialo gratis
  • Escrito por estudiantes que aprobaron
  • Inmediatamente disponible después del pago
  • Leer en línea o como PDF
Vender
¿Dónde estudias?
Tu idioma
Document preview thumbnail
Vista previa 4 fuera de 43 páginas
Examen

OPS Actual Final Exam | Most Recent Exam 2026 Actual Comprehensive Real Exam Questions And Verified Answers (100% Correct Answers) Already Graded A+ | Guaranteed Success | Newest Exam | Just Released!!

Document preview thumbnail
Vista previa 4 fuera de 43 páginas

OPS Actual Final Exam | Most Recent Exam 2026 Actual Comprehensive Real Exam Questions And Verified Answers (100% Correct Answers) Already Graded A+ | Guaranteed Success | Newest Exam | Just Released!! OPS Actual Final Exam | Most Recent Exam 2026 Actual Comprehensive Real Exam Questions And Verified Answers (100% Correct Answers) Already Graded A+ | Guaranteed Success | Newest Exam | Just Released!!

Vista previa del contenido

4/13/26, 12:29 PM OPS Final Exam


OPS Actual Final Exam | Most Recent Exam 2026 Actual
Comprehensive Real Exam Questions And Verified Answers
(100% Correct Answers) Already Graded A+ | Guaranteed
Success | Newest Exam | Just Released!!



1. Which of the following is an advantage of PERT and CPM?


a. Precedence relationships must be specified and networked together.
b. Project activities have to be clearly defined, independent, and stable
in their relationships.
c. Useful in monitoring only schedules.
d. Straightforward concept and not mathematically complex.


d. Straightforward concept and not mathematically complex.


2. A simple CPM network has three activities, A, B, and C. A is an immediate
predecessor of B and of C. B is an immediate predecessor of C. The activity
durations are A=4, B=3, C=8.


a. The critical path is A-C, duration 12.
b. The critical path cannot be determined without knowing PERT
expected activity times.
c. The network has no critical path.
d. The critical path is A-B-C, duration 15.
e. The critical path is A-B-C, duration 13.5


d. The critical path is A-B-C, duration 15.




/ 1/43

,4/13/26, 12:29 PM OPS Final Exam



3. The time an activity will take assuming very unfavorable conditions is:
a. the minimum time.
b. the activity variance.
c. the optimistic time.
d. the pessimistic time.


d. the pessimistic time.


4. Which of the following activities are NOT part of project scheduling?
a. Chart separate schedules for personnel needs by type of skill and materials
needs.
b. Make sure all necessary activities are finished in proper sequence and on
time.
c. Decide how long each activity will take.
d. Compute resources needed at each stage of production


b. Make sure all necessary activities are finished in proper sequence and on
time.

5. The _____ distribution is used by PERT analysis to calculate expected activity
times
and variances.
a. Normal
b. Alpha
c. Binomial
d. Beta
e. Gaussian


d. Beta




/ 2/43

,4/13/26, 12:29 PM OPS Final Exam



6. Which of the following statements regarding CPM networks is true?
a. The late start of an activity is its late finish plus its duration.
b. There can be multiple critical paths on the same project, all with
different durations.
c. If a specific project has multiple critical paths, all of them will have
the same duration.
d. The early finish of an activity is the latest early start of all preceding
activities.
e. None of the above are true.


c. If a specific project has multiple critical paths, all of them will have the same
duration.

7. Which of the following statements regarding CPM is true?
a. The critical path is the shortest of all paths through the network.
b. All activities on the critical path have their LS equal to the maximum
EF of all immediate predecessors.
c. The critical path is that set of activities that has positive slack.
d. Some networks have no critical path.
e. All activities on the critical path have their ES equal to their LF.


b. All activities on the critical path have their LS equal to the maximum EF of all
immediate predecessors.


8. Which of the following is used for computations in CPM?
a. pessimistic time
b. normal time
c. most likely time
d. optimistic time


b. normal time




/ 3/43

, 4/13/26, 12:29 PM OPS Final Exam



9. The three phases involved in the management of large projects are
a. planning, scheduling, and evaluating.
b. scheduling, operating, and evaluating.
c. planning, scheduling, and controlling.
d. scheduling, designing, and operating.


c. planning, scheduling, and controlling.


10. Which of the following does NOT belong to the planning phase of
project management?
a. team organization
b. goal setting
c. monitoring resources
d. defining the project



c. monitoring resources

11. Which of the following is NOT a technique that allows managers to plan,
schedule, and control projects?
a. Factor-rating method
b. CPM
c. Gantt charts
d. PERT


a. Factor-rating method




/ 4/43

Información del documento

Subido en
13 de abril de 2026
Número de páginas
43
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$21.00

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
NURSEGENLPN
3.8
(26)
Vendido
171
Seguidores
5
Artículos
10971
Última venta
1 semana hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes