CDT Exam 2

What is Dual Nature of design? - Answer-Aesthetic and Technical Design



Hard Costs - Answer-Tangible components of completed projects

EX: Site related costs, construction, furniture/furnishings, equipment

*Included in the PROJECT BUDGET



Soft Costs - Answer-Non-Tangible components of completed projects.

EX: Due Diligence, Project Design Fees, Commissioning, Jurisdictional Fees, Relocation, Terminating
Leases and Rental Agreements

*Included in the project budget



Value Analysis - Answer-The process of evaluating a design to identify potential alternative methods,
systems, or materials that will benefit the project by enhancing the life cycle.

*Value: The decision making process is improved by analysis



Value Analysis Methodology - Answer-Value Analysis is conducted in a workshop format and can be held
anytime during Design and Construction Process

*The Workshop Steps: Information Phase, Speculation (creative) Phase, Evaluation (analysis) Phase,
Development Phase, Presentation Phase



Schematic Design - Answer-A/E Reviews and Evaluates the wonders program and budget requirements
and offers alternative approaches to the design of the project. *A/E prepares schematic design
documents for owners approval, Including: Preliminary Sketches, Small scale schematic plans,

,evaluations, sections, diagrams, renderings, and other GRAPHIC AND WRITTEN Documents that illustrate
the general extent, scale, and relationship among project components



Types of drawings prepared during the schematic design phase - Answer-* site plan

* floor plans

* perspective and renderings

* elevations

* building sections

* digital modeling



Preliminary Project Description (PPD) - Answer-Describes the scope and relationships of major elements
organized in terms of building systems and components

Includes information suitable for preliminary cost estimates, time schedules, and initial value

May include both performance criteria and some major product identification DEPENDING ON progress
of the design and decision making process



PPD Serves To: - Answer-State the A/E's understanding of the method of construction delivery (Bid,
negotiated, CMaR, D-B, O-B, etc. intended by owner, and conditions of the contract proposed to support
the delivery method

Inform owner of proposed design elements, components, and systems to be used.

Describe systems meeting the design and budget constraints

Document the basis for time schedules and estimates of probable construction costs.



Which CSI Classification Standard is used to Organize a PPD? - Answer-Uniformat



Cost Estimating Technique MOST APPROPRIATE during Schematic Design Phase? - Answer-Unit of
Measure (a "somewhat" more accurate method of predicting constructed costs than the order of
Magnitude Cost Estimate Method)

,Unit of Measure - Answer-"Somewhat" more accurate than order of magnitude

Construction MUST BE DEFINED AND APPROXIMATE total Facility size MUST BE KNOWN

Unit costs per SQ. FT/FT3 are established for Gross Area/Volume and Net Area/Volume

- Gross Area/Volume determined for ENTIRE facility

- Net Area/Volume is the Area/Volume decided for the Facility's INTENDED PRIMARY USE

SQ.FT. Or Volume method gets a more accurate project cost, usually 15 to 20%



Order of Magnitude - Answer-The quickest estimate to complete and the LEAST ACCURATE

provides a "Ballpark" estimate for project cost

-Accuracy is 20-25%

uses PER UNIT occupancy costs

EX: A cost per bed price for a nursing home, Hospital, or a hotel

OR

Cost per seat prices for a Theater or a Restaurant



Assemblies/Systems - Answer-Requires more detailed information about the project construction

Cost per unit of assembled construction is used to form the cost estimate

Uniformat can be used as a cost guide format

Cost per unit for windows, doors, Bath Fixtures etc.

Cost for each assembly, item, or group are totaled to get total cost estimate



Unit Price - Answer-Uses a complete, detailed list of project materials, components, and other cost
items for the entire project

MOST ACCURATE TYPE OF COST ESTIMATE

-Accurate to 3-5%

, Requires significant amount of time and effort

UTILIZES THE COMPLETED Construction Documents



Design Development - Answer-Comes AFTER owners approval of schematic design and any program or
budget adjustments



EMPHASIS shifts from overall relationships and functions to MORE TECHNICAL ISSUES OF
CONSTRUCTIBILITY AND INTEGRATION OF SYSTEMS AND COMPONENTS

Aesthetic concerns move from massing arrangements to MATERIALS, SURFACES, and DETAILS



Types of Drawings Prepared for The Design Development Phase - Answer-Site Plan

Floor Plans

Elevations

Building Sections

Perspective and Renderings

Digital Modeling

Structural Plans

Fire Protection Plans

Landscape Plans

Mechanical Plans

Grading and Drainage Plans



Outline Specifications - Answer-Help Owner become familiar with and understand building ELEMENTS,
PRODUCTS, and STANDARDS

Serve a variety of purposes for LENDERS, ESTIMATORS, CONSTRUCTION MANAGERS, and CODE
OFFICIALS

Información del documento

Subido en
12 de abril de 2026
Número de páginas
41
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$24.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
Zanaya
4.5
(12)
Vendido
78
Seguidores
29
Artículos
10176
Última venta
1 semana hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes