CON 496: Construction Contract Administration With A+ Graded Solutions Version 2026/2027

Document preview thumbnail
Vista previa 3 fuera de 18 páginas

1. What is a "Letter of Intent" (LOI)? • A) A final contract signed by all parties. • B) An interim document expressing a serious intent to contract, often used to allow long-lead ordering. • C) A letter from the contractor quitting the job. • D) A letter from the bank approving a loan. • Correct Answer: B. LOIs allow work or procurement to start while the formal legal contract is being finalized. 2. What is "Unbalanced Bidding"? • A) Bidding on a project while standing on one foot. • B) Inflating unit prices for early work items and deflating later ones to get more cash early. • C) Bidding the same price as a competitor. • D) Forgetting to include the cost of labor. • Correct Answer: B. While common, it can be grounds for rejecting a bid in public works because it increases the owner's risk. 3. What is "Job Cost Accounting"? • A) Tracking the contractor’s personal bank account. • B) The process of tracking all expenses and revenues associated with a specific construction project. • C) Counting the number of workers on site. • D) Paying for the architect's lunch. • Correct Answer: B. It is essential for determining if a project is profitable in real-time. 4. What is the "Critical Path Method" (CPM)? • A) The fastest way to drive to the job site. • B) A scheduling technique that identifies the sequence of tasks that determines the project duration. • C) A method for choosing a contractor. • D) A safety protocol for high-rise buildings. • Correct Answer: B. Any delay in a critical path task results in a delay of the entire project.

Vista previa del contenido

CON 496: Construction Contract Administration With
A+ Graded Solutions Version 2026/2027
1. What is a "Letter of Intent" (LOI)?

 A) A final contract signed by all parties.

 B) An interim document expressing a serious intent to contract, often used to allow
long-lead ordering.

 C) A letter from the contractor quitting the job.

 D) A letter from the bank approving a loan.

 Correct Answer: B. LOIs allow work or procurement to start while the formal legal
contract is being finalized.

2. What is "Unbalanced Bidding"?

 A) Bidding on a project while standing on one foot.

 B) Inflating unit prices for early work items and deflating later ones to get more cash
early.

 C) Bidding the same price as a competitor.

 D) Forgetting to include the cost of labor.

 Correct Answer: B. While common, it can be grounds for rejecting a bid in public
works because it increases the owner's risk.

3. What is "Job Cost Accounting"?

 A) Tracking the contractor’s personal bank account.

 B) The process of tracking all expenses and revenues associated with a specific
construction project.

 C) Counting the number of workers on site.

 D) Paying for the architect's lunch.

 Correct Answer: B. It is essential for determining if a project is profitable in real-time.

4. What is the "Critical Path Method" (CPM)?

 A) The fastest way to drive to the job site.

 B) A scheduling technique that identifies the sequence of tasks that determines the
project duration.

 C) A method for choosing a contractor.

 D) A safety protocol for high-rise buildings.

 Correct Answer: B. Any delay in a critical path task results in a delay of the entire
project.

,5. What is "Total Float"?

 A) The amount of time a project can be late.

 B) The amount of time an activity can be delayed without delaying the project
completion date.

 C) A tool for smoothing concrete.

 D) The number of extra workers available.

 Correct Answer: B. Tasks with zero total float are on the critical path.

6. What is "Free Float"?

 A) Extra materials that were given for free.

 B) The amount of time an activity can be delayed without delaying the very next
activity.

 C) Working on a barge.

 D) A bonus payment.

 Correct Answer: B. It is a subset of total float.

7. What is a "No-Damage-for-Delay" clause?

 A) A clause saying no one can be late.

 B) A provision stating that a contractor's only remedy for owner-caused delay is a
time extension, not money.

 C) A clause that pays the contractor for every day they are early.

 D) A safety rule.

 Correct Answer: B. These are controversial and are banned in several states for
public projects.

8. What is "Constructive Acceleration"?

 A) Building a wall very quickly.

 B) When an owner refuses a valid time extension, forcing the contractor to spend
more to finish on time.

 C) Using a faster crane.

 D) Hiring more subcontractors voluntarily.

 Correct Answer: B. The contractor can often claim the extra costs associated with
this "forced" speed-up.

9. What is a "Suspension of Work" clause?

 A) A clause about building a suspension bridge.

,  B) A provision allowing the owner to stop work for a period without terminating the
contract.

 C) A rule about hanging lights.

 D) A type of insurance policy.

 Correct Answer: B. The contractor is usually entitled to an adjustment in price and
time once work resumes.

10. What is "Direct Labor"?

 A) Labor performed by the owner.

 B) Labor specifically engaged in the physical construction of the project.

 C) Labor performed by the office secretary.

 D) Labor performed for free.

 Correct Answer: B. This is a primary cost driver in construction estimates.

11. What is "Burdened Labor Rate"?

 A) The weight a worker can carry.

 B) The hourly wage plus all employer-paid benefits, taxes, and insurance (UI, FICA,
etc.).

 C) A worker who is unhappy.

 D) The cost of tools.

 Correct Answer: B. This is the "true" cost of an employee to the company.

12. What is "Prevailing Wage" (Davis-Bacon Act)?

 A) The wage the contractor wants to pay.

 B) A minimum wage set by the government for workers on public construction
projects.

 C) The highest wage in the country.

 D) A bonus for working in the rain.

 Correct Answer: B. It ensures contractors don't win bids by undercutting local labor
standards.

13. What is "Broad-Form Indemnity"?

 A) A very wide insurance policy.

 B) A clause requiring the contractor to indemnify the owner even for the owner’s
own negligence.

 C) A type of foundation.

 D) A project summary.

Información del documento

Subido en
27 de marzo de 2026
Número de páginas
18
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$16.49

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Vendido
3
Seguidores
0
Artículos
201
Última venta
7 meses hace



Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes