BA 320 EXAM 2 || A+ GRADED.
What are the different types of networks? correct answers Project Network with arrows and
nodes, PDM (Precedence Diagramming Method)

Slack / Float (SL) correct answers how long can an activity be delayed

SL correct answers LS - ES or LF - EF

Critical Path: correct answers The longest path through the activity network that allows for
the completion of all project-related activities.

Represents the shortest expected time in which the entire project can be completed.

Non-Critical Path correct answers Series of activities that can be slipped to a certain degree
without threatening the completion date of the overall project

Sensitivity correct answers How likely a CP is likely to change (Gnatt chart can be used for this)

When do you move to Critical to Non-Critical? correct answers When you need to use slack?

Free slack (FS) correct answers is the amount of time an activity can be delayed without delaying
any immediately following (successor) activity

Total slack tells us correct answers the amount of time an activity can be delayed and not delay
the project

Total slack is correct answers the amount of time an activity can exceed its early finish date
without affecting the project end date or an imposed completion date

What are the different ways to report a status? correct answers Gnatt chart, milestone chart,
control chart

Why is time burn rate insufficient to do analysis? correct answers Because you also need to look
at the budget burn rate to determine how much is being spent.

What is Earned Value Management (EVM)? correct answers is a project management technique
for measuring project performance and progress in an objective manner ---- it is the percent
complete of baseline budget earned by actual work performed.

Earned Value correct answers Authorized budget for work actually

EV = correct answers PV to date x RP

Cost Variance (CV) = correct answers EV - AC (Earned Value - Actual Cost)

, Schedule Variance (SV) = correct answers EV - PV

CPI Cost Performance Index correct answers EV/AC

SPI Schedule Performance Index correct answers EV/PV

Burn Rate = correct answers 1/CPI

Simple Budget Estimate at Completion = correct answers Original Budget Estimate/ CPI

Planned Value (PV) = correct answers Planned % complete * Budget at Completion

Earned Value (EV) = correct answers % Complete * Budget at Completion

Resource smoothing: correct answers CNHF

Consists of moving non-critical to non-critical PRIOR to baselining
Never impacts the end date
Has a minimal impact on financials
Focuses on scarce resources

Finish-to-Finish correct answers Predecessor must finish before Successor can finish.
-Laying Asphalt must be complete before line painting can be completed

Finish-to-Start correct answers Predecessor must finish before Successor can start.
-Land must be purchased before road building can start

What are the 8 options to react to a change request? correct answers AUCASOCJ




Add Lead Time to overlap activities

Use available Lag Time

Change (Reduce) Durations

Adjust Resources

Schedule overtime

Outsource project work if previously authorized

Change the Scope

Información del documento

Subido en
28 de febrero de 2026
Número de páginas
6
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$11.19

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
SirAnton
3.7
(118)
Vendido
791
Seguidores
438
Artículos
40035
Última venta
1 semana hace




Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes