AND ANSWERS 2026 | Construction Quality
Management for Contractors | Practice Test |
Pass Guaranteed - A+ Graded
Section 1: CQM Fundamentals and Terminology
Questions 1-10
Question 1 What is the primary purpose of Construction Quality Management (CQM) on federal
construction projects?
A. To reduce construction costs
B. To ensure that work is performed in accordance with contract requirements [CORRECT]
C. To speed up project completion
D. To eliminate the need for Government oversight
Correct Answer: B
Rationale: The primary purpose of CQM, as defined in ER 1180-1-6 and USACE regulations, is
to ensure all work conforms to contract requirements, specifications, and drawings. While
effective quality management may indirectly reduce costs (A) by preventing rework, or affect
schedule (C), these are secondary outcomes, not primary purposes. Option D is incorrect because
Government oversight (QA) remains essential; CQM does not eliminate the Government's
quality assurance role but rather ensures the contractor's quality control is effective.
Question 2 In USACE construction terminology, Quality Control (QC) is performed by:
A. The Government
B. The Contractor [CORRECT]
C. A third-party testing agency
D. The architect/engineer
Correct Answer: B
Rationale: Quality Control (QC) is exclusively the contractor's responsibility to ensure their
own work meets contract requirements before offering it for Government acceptance. Quality
,Assurance (QA) is performed by the Government (typically the Resident Engineer or their
representatives) to verify the effectiveness of the contractor's QC program. Third-party testing
agencies (C) may perform testing under contract to the contractor, but the QC responsibility
remains with the contractor. The A/E (D) typically performs design-phase QA, not construction
QC.
Question 3 A QC Plan must be submitted by the contractor and approved by the Government
before:
A. Any work begins [CORRECT]
B. The contract is awarded
C. Final payment
D. The preparatory phase
Correct Answer: A
Rationale: The QC Plan must be submitted within a specified time after contract award
(typically 14-30 days) and approved by the Government before any physical work begins on site.
The plan outlines the contractor's QC organization, personnel qualifications, procedures, and
documentation requirements. Submitting after award (B) is too early (contractor hasn't been
selected). Final payment (C) is far too late. The preparatory phase (D) occurs after work planning
but before physical work; the QC Plan must be approved before any preparatory phase activities.
Question 4 Which of the following best describes the relationship between QC and QA on a
USACE construction project?
A. QC and QA are the same function performed by different people
B. QC is the contractor's inspection of their own work; QA is the Government's verification of
the contractor's QC [CORRECT]
C. QC is performed before construction; QA is performed after completion
D. QC is optional; QA is mandatory
Correct Answer: B
Rationale: QC (Quality Control) is the contractor's process of inspecting, testing, and verifying
their own work to ensure it meets requirements before offering it to the Government. QA
(Quality Assurance) is the Government's process of monitoring, witnessing, and verifying that
the contractor's QC is effective and that work meets contract requirements. They are distinct
functions (A is wrong). Both occur during construction (C is wrong). QC is mandatory on
USACE projects (D is wrong).
, Question 5 The QC Manager must have which of the following qualifications?
A. A professional engineering license only
B. Experience and authority to implement the QC Plan, as approved by the Contracting Officer
[CORRECT]
C. A high school diploma only
D. Government employment status
Correct Answer: B
Rationale: The QC Manager must have sufficient experience, technical knowledge, and
organizational authority to implement the QC Plan effectively. While professional licensure may
be beneficial, it is not always mandatory (A). Minimum education (C) is insufficient without
experience and authority. The QC Manager works for the contractor, not the Government (D).
The Contracting Officer must approve the QC Manager's qualifications.
Question 6 Which document provides the primary basis for determining whether work conforms
to contract requirements?
A. The contractor's standard practices
B. The contract specifications, drawings, and approved submittals [CORRECT]
C. The QC Plan only
D. Industry standards, regardless of contract requirements
Correct Answer: B
Rationale: Conformance is determined by comparing work to the contract documents:
specifications (written requirements), drawings (graphical requirements), and approved
submittals (shop drawings, material approvals, etc.). The contractor's standard practices (A) may
exceed but cannot fall below contract requirements. The QC Plan (C) describes how the
contractor will achieve quality but is not the acceptance criteria. Industry standards (D) apply
only when specifically referenced in the contract.
Question 7 The difference between inspection and testing is:
A. There is no difference; the terms are interchangeable
B. Inspection is visual examination; testing is physical measurement or performance verification
[CORRECT]
C. Inspection is performed by the Government; testing is performed by the contractor
D. Inspection occurs before construction; testing occurs after
Correct Answer: B