1. The minimum crane team for a mobile crane on outriggers would consist of-
A) The Crane Operator, Rigger Supervisor, and Crane Rigger
B) The Crane Operator, Crane Supervisor, Rigger Supervisor, and
Crane Rigger
C) The Crane Operator, Crane Supervisor, and Crane Rigger
D) The Crane Operator and Rigger-in-Charge
E) The Crane Operator, Crane Walker, and Crane Rigger: C) The Crane Operator, Crane
Supervisor, and Crane Rigger
2. When operating floating cranes, you must start swinging or rotating quickly
and stop smoothly to prevent excessive barge list.
A) True
B) False: B) False
3. Extending a telescoping boom without lowering the hoist may result in
"two-blocking" the crane.
A) True
B) False: A) True
4. All of the following require a license to operate EXCEPT a(n)-
A) Cab-operated category 3 bridge crane
B) Mobile hydraulic truck crane
C) Non-cab operated category 3 bridge crane
D) Articulating boom category 4 crane
E) Floor-operated category 2 bridge crane: C) Non-cab operated category 3 bridge crane
5. Which of the following lift types would NOT be considered a complex lift?
A) Multiple-crane lifts
B) Oxygen/Acetylene bottles in racks designed for lifting
O C) Large geometric shapes
D) Loads with multi-level attachment points
E) Hazardous or explosive materials: B) Oxygen/Acetylene bottles in racks designed for lifting
6. What is the minimum amount of rope that shall be on a grooved drum and a
smooth drum?
A) There is no minimum
, General crane safety EXAM, SOLUTIONS (MULTIPLE CHOICES) (A+ GRADE
100% VERIFIED) LATEST VERSION 2025!!
Study online at https://quizlet.com/_ic3cii
B) 4 full wraps, 2 full wraps
C) 2 full wraps, 3 full wraps
D) 6 full wraps, 4 full wraps
E) 1 full wrap, 2 full wraps: B) 4 full wraps, 2 full wraps
7. The horizontal distance from the center of rotation of the crane to the center
of the hoist line(s) with load applied is called
A) Boom Length
B) Radius
C) Lift Zone
D) Quadrant
E) Circumference: B) Radius
8. What is two-blocking, and why is two-blocking dangerous?
A) Two-blocking occurs when the hook contacts another block or hook on the
crane. It is dangerous because the hook could damage the crane, causing loss
of load control.
B) Two-blocking occurs when the block or hook contacts the ground.
It is dangerous because the wire rope may come off of the drum and drop the
block.
C) Two-blocking occurs when the hook block comes in contact with the upper
sheave block during hoisting of the hook. It is dangerous because it could result
in damage to the crane, parting of the hoist lines, and dropping the load.: C)
Two-blocking occurs when the hook block comes in contact with the upper sheave block during hoisting of the hook.
It is dangerous because it could result in damage to the crane, parting of the hoist lines, and dropping the load.
9. When should a tagline be used during lifting operations?
A) when lifting a load over or near electrical transmission lines
B) to prevent the load from swinging or rotating
C) when the supervisor approves their use
D) only when lifting the load to extreme heights: B) to prevent the load from swinging or
rotating
10. What is the weight of a 24 square foot, 2 inch thick aluminum plate with a
unit weight of 15 lbs. per square foot of material per inch of thickness?
, General crane safety EXAM, SOLUTIONS (MULTIPLE CHOICES) (A+ GRADE
100% VERIFIED) LATEST VERSION 2025!!
Study online at https://quizlet.com/_ic3cii
A) 348 pounds
B) 720 pounds
C) 6,720 pounds
D) 60 pounds
E) 120 pounds: B) 720 pounds
11. The two expiration dates that are of particular importance to crane operators
are-
A) Vehicle registration expiration date
B) Hydraulic oil expiration date
C) CAC card expiration date
D) The certification expiration date of the crane
E) The crane operator's license expiration date: D) The certification expiration date of the crane
E) The crane operator's license expiration date
12. Which of the following is NOT an acceptable method of communication
between the signal person and the crane operator?
A) Signal Flags
B) Direct Voice
C) Hand Signals
D) Sound-powered Phones
E) Approved Radios: A) Signal Flags
13. What is a jib boom?
A) A boom that is attached to the main boom to allow rotation of the load
B) An extension attached to the main boom used when lifting light loads to a
higher elevation than that permitted by the main boom
C) A boom that is used to lift extremely heavy loads: B) An extension attached to the main
boom used when lifting light loads to a higher elevation than that permitted by the main boom
14. If you find cracking or flaking paint on a welded joint of a structural compo-
nent on the boom, you should
A) Look closer to see if it is a crack.
B) Report it immediately to your supervisor.
C) Do nothing as it is not significant.