Escrito por estudiantes que aprobaron Inmediatamente disponible después del pago Leer en línea o como PDF ¿Documento equivocado? Cámbialo gratis 4,6 TrustPilot
logo-home
Document preview thumbnail
Vista previa 4 fuera de 48 páginas
Examen

COMPTIA PROJECT+ EXAM ACTUAL PREP QUESTIONS AND WELL REVISED ANSWERS - LATEST AND COMPLETE UPDATE WITH VERIFIED SOLUTIONS – ASSURES PASS

Document preview thumbnail
Vista previa 4 fuera de 48 páginas

COMPTIA PROJECT+ EXAM ACTUAL PREP QUESTIONS AND WELL REVISED ANSWERS - LATEST AND COMPLETE UPDATE WITH VERIFIED SOLUTIONS – ASSURES PASS

Vista previa del contenido

COMPTIA PROJECT+ EXAM ACTUAL PREP
QUESTIONS AND WELL REVISED ANSWERS -
LATEST AND COMPLETE UPDATE WITH
VERIFIED SOLUTIONS – ASSURES PASS


1. Which of the following is the primary purpose of a project charter?
A. To define the project scope and objectives
B. To assign daily tasks to team members
C. To create a project schedule
D. To track project risks
Answer: A
Rationale: A project charter formally authorizes a project, defining its
scope, objectives, and stakeholders.
2. What is the critical path in project management?
A. The path with the most resources assigned
B. The sequence of tasks that determines the project duration
C. The path with the lowest costs
D. The sequence of tasks with the least dependencies
Answer: B
Rationale: The critical path is the longest sequence of dependent tasks that
determines the minimum project duration.
3. During which phase of a project does the team perform a feasibility study?
A. Planning
B. Initiation
C. Execution

, D. Closure
Answer: B
Rationale: Feasibility studies are conducted during the initiation phase to
assess whether the project should proceed.
4. Which project management tool is used to visualize the project schedule and
task dependencies?
A. Gantt chart
B. SWOT analysis
C. RACI matrix
D. Fishbone diagram
Answer: A
Rationale: A Gantt chart displays the project schedule and dependencies
between tasks, allowing for visual tracking.
5. What is the purpose of a risk register?
A. To record all project risks and responses
B. To track project budgets
C. To define project objectives
D. To document team roles
Answer: A
Rationale: A risk register documents identified risks, their probability,
impact, and mitigation plans.
6. Which of the following best defines scope creep?
A. Adding extra tasks without changing project objectives
B. Uncontrolled changes to project scope without approval
C. A delay in the project schedule
D. Overestimating project costs
Answer: B

, Rationale: Scope creep occurs when project scope changes occur without
formal approval, affecting schedule and resources.
7. What is a stakeholder in project management?
A. A team member responsible for tasks
B. Anyone affected by or having an interest in the project
C. A project sponsor
D. Only the project manager
Answer: B
Rationale: Stakeholders include anyone who is impacted by the project or
has influence over it.
8. Which method is best for prioritizing project tasks based on urgency and
importance?
A. Pareto analysis
B. MoSCoW method
C. Critical path method
D. Fishbone diagram
Answer: B
Rationale: The MoSCoW method prioritizes tasks into Must, Should, Could,
and Won’t categories.
9. What is the main purpose of a project baseline?
A. To track approved scope, schedule, and cost
B. To define stakeholder roles
C. To list project risks
D. To assign daily tasks
Answer: A
Rationale: A baseline represents the approved version of the project scope,
schedule, and budget against which progress is measured.

, 10.During the execution phase, a team member identifies a significant risk.
What should the project manager do first?
A. Update the project schedule
B. Notify stakeholders and update the risk register
C. Add tasks to the critical path
D. Reduce project scope
Answer: B
Rationale: Risks identified during execution must be documented and
communicated to stakeholders with mitigation plans.
11.What is the main goal of project closing?
A. Completing all project deliverables and obtaining formal acceptance
B. Assigning tasks for the next project
C. Creating a risk register
D. Conducting daily team meetings
Answer: A
Rationale: Project closing ensures all deliverables are completed, accepted,
and documented, and lessons learned are recorded.
12.Which document outlines roles, responsibilities, and reporting relationships
in a project?
A. Project charter
B. Work Breakdown Structure (WBS)
C. RACI matrix
D. Gantt chart
Answer: C
Rationale: The RACI matrix clarifies who is Responsible, Accountable,
Consulted, and Informed for each task.

Información del documento

Subido en
30 de diciembre de 2025
Número de páginas
48
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas
$24.99

¿Documento equivocado? Cámbialo gratis Dentro de los 14 días posteriores a la compra y antes de descargarlo, puedes elegir otro documento. Puedes gastar el importe de nuevo.
Escrito por estudiantes que aprobaron
Inmediatamente disponible después del pago
Leer en línea o como PDF

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
tutorlincon
4.4
(409)
Vendido
816
Seguidores
26
Artículos
6150
Última venta
1 día hace


Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes