The purpose of Construction Quality Management is to: ANS >>
Achieve the quality established by properly developed
requirements through the combined responsibility, but separate
efforts of contractor sad government personnel.
Construction Quality Management is the performance of tasks,
which ensure that construction is performed. ANS >> According to
plans and specifications, on time, within a defined budget and a
safe work environment.
Partnering relationships are based upon: ANS >> Building trust
and dedication to common goals
, It is the responsibility of Quality Assurance Personnel to: ANS >>
Periodically verify that the contractor’s system of control is
working effectively.
An effective contractor quality control program will: ANS >> Be an
incentive for work to be done correctly the first time resulting in
earlier completion, reduced field overhead costs, and greater
profits.
The success or failure of all contractors is based upon: ANS >> The
ability to control costs, finance work, estimate jobs, schedule
the work, and maintain effective quality control.
Quality Assurance Personnel have the responsibility to: ANS >>
Require contractors to maintain the quality specified in the
plans and specifications.
Inspection is: ANS >> The process by which ongoing and
completed work is examined
During the punch-out inspection of a project: ANS >> Quality
Assurance Personnel must assure that the contractor prepares a
punch-list and makes corrections.