NCIDQ Practice Exam Questions – IDPX
Graded A+
Which event triggers the issuance of a certificate of occupancy?
A. Construction work is complete except for fire alarm testing.
B. The contractor sends you a pay request for 100% complete work.
C. The owner wants to move into part of the space before the rest is finished.
D. The city inspector has inspected and finalized the job. - Correct answer-Answer:
D
What factors are MOST important in determining the locations of individual
workstations within departments?
A. Planning and design concepts
B. Company image and employee status
C. Work relationships and job adjacencies
D. Client's business and communication patterns - Correct answer-Answer: C
In which situation should you use a construction change directive?
©COPYRIGHT 2025, ALL RIGHTS RESERVED 1
, A. To request an electrical contractor not listed by the contractor in the bid [tender]
documents
B. To request pricing for an additional receptacle per the client's request
C. To provide additional dimensions to the contractor regarding a receptacle
location
D. To relocate an electrical receptacle because of revised furniture plans - Correct
answer-Answer: D
Why are addenda issued?
A. To provide additional information not included in the bid package
B. To inform potential bidders about acceptable alternates
C. To obtain additional information
D. To request a change during construction - Correct answer-Answer: A
Which light and color characteristic would be MOST effective to enhance way-
finding in a senior living facility?
A. Brightness
B. Hue
C. Contrast
©COPYRIGHT 2025, ALL RIGHTS RESERVED 2
Graded A+
Which event triggers the issuance of a certificate of occupancy?
A. Construction work is complete except for fire alarm testing.
B. The contractor sends you a pay request for 100% complete work.
C. The owner wants to move into part of the space before the rest is finished.
D. The city inspector has inspected and finalized the job. - Correct answer-Answer:
D
What factors are MOST important in determining the locations of individual
workstations within departments?
A. Planning and design concepts
B. Company image and employee status
C. Work relationships and job adjacencies
D. Client's business and communication patterns - Correct answer-Answer: C
In which situation should you use a construction change directive?
©COPYRIGHT 2025, ALL RIGHTS RESERVED 1
, A. To request an electrical contractor not listed by the contractor in the bid [tender]
documents
B. To request pricing for an additional receptacle per the client's request
C. To provide additional dimensions to the contractor regarding a receptacle
location
D. To relocate an electrical receptacle because of revised furniture plans - Correct
answer-Answer: D
Why are addenda issued?
A. To provide additional information not included in the bid package
B. To inform potential bidders about acceptable alternates
C. To obtain additional information
D. To request a change during construction - Correct answer-Answer: A
Which light and color characteristic would be MOST effective to enhance way-
finding in a senior living facility?
A. Brightness
B. Hue
C. Contrast