PMI CAPM Questions with Answers (100% Correct Answers) PMI CAPM Questions with Answers (100% Correct Answers)

Institution
PMI CAPM
Module
PMI CAPM











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
PMI CAPM
Module
PMI CAPM

Document information

Uploaded on
November 20, 2025
Number of pages
106
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

1




PMI CAPM Questions with Answers (100%
Correct Answers)
Once the make-or-buy analysis is completed, which document defines the
project delivery method?



A. Procurement statement of work (SOW)



B. Procurement strategy



C. Terms of reference



D. Change request Answer: B. Procurement strategy

A project is just beginning, and management creates a long list of potential
stakeholders. Which statement about identifying and engaging stakeholder, is
correct?



A. The project manager should identify and deal with stakeholders only during
the execution phase.



B. Stakeholder satisfaction should be identified immediately and managed as a
project objective.

,2


C. The project manager should focus on project objectives and deal with
stakeholders as a secondary priority.



D. Stakeholder satisfaction is the most important goal, and project objectives
should be considered a secondary priority. Answer: B. Stakeholder satisfaction
should be identified immediately and managed as a project objective.

Which is an example of leveraging evolving trends and emerging practices in
Project Integration Management?



A. Hybrid methodologies



B. Risk register updates



C. Outsourced project resources



D. Reliance on lessons learned documents Answer: A. Hybrid methodologies

What should a project manager use to determine how much money is needed
to complete a project?



A. Earned value management (EVM)



B. Estimate at completion (EAC)

,3


C. Earned value analysis (EVA)



D. Budget at completion (BAC) Answer: C. Earned value analysis (EVA)

The project manager is creating the communications management plan. Which
group of inputs is required to begin?



A. Work performance reports, change requests, and risk register



B. Work performance data, project documents, and stakeholder engagement
plan



C. Project charter, project management plan, and project documents



D. Work performance data, stakeholder register, and team management plan
Answer: C. Project charter, project management plan, and project documents

A project is in progress and about to move to a different phase, according to the
plan. This will be a good opportunity for the project manager to:



A. create the project management plan.



B. identify the project objectives.

, 4


C. review and update stakeholder engagement.



D. create the schedule baseline. Answer: C. review and update stakeholder
engagement.

A new project has been set. Four main stakeholders besides the project
manager and four other team members have been identified. How many
communication channels are available?



A. 8



B. 18



C. 36



D. 40 Answer: C. 36

A project manager is preparing to meet with three crucial project stakeholders
on a new project. Which tools and techniques can the project manager use to
capture stakeholder interest?



A. Review stakeholder register and meeting



B. Data analysis and communication skills

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Metric Yale School Of Medicine
Follow You need to be logged in order to follow users or courses
Sold
95
Member since
1 year
Number of followers
5
Documents
13109
Last sold
1 week ago

Welcome to Metric – Your Go-To Study Resource on Stuvia! At Metric, we believe studying should be smart, efficient, and effective. That’s why we offer high-quality, exam-ready study notes, summaries, and resources designed to help you understand key concepts faster and achieve better results. Whether you're cramming for finals, revising for a quiz, or looking to deepen your understanding, Metric provides content that’s clear, structured, and aligned with real course requirements. ✨ What you’ll find at Metric: ✔️ Accurate, in-depth summaries ✔️ Easy-to-follow formats for fast revision ✔️ Notes based on real syllabus & past exams ✔️ Regularly updated content you can trust Join hundreds of students who rely on Metric to study smarter—not harder. Browse the shop, grab what you need, and level up your academic game today!ades with Expert Academic Help

Read more Read less
2.8

13 reviews

5
3
4
1
3
2
2
5
1
2

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Frequently asked questions