POM Exam 2 Questions with Complete Solutions Production Requirement Formula - ANSWERS -Demand Forecast + (demand forecast x Required safety stock in decimals ex. 20% = 0.20) - beginning inventory The objective of the Aggregate Operations Plan is to insure that the marketing and sales plan are realistic - ANSWERS -False The main purpose of the aggregate operations planning is to specify the optimal combination of which of the following? - ANSWERS -Workforce levels and inventory on hand Which of the following methods discussed in the text requires generating several alternative aggregate plans? - ANSWERS -Cut and Try Aggregate Planning Techniques is developed from the master schedule and the strategic capacity plan. - ANSWERS -False The critical path of activities in a project is the sequence of activities that form the shortest chain in a project network of activities. - ANSWERS -False You know when you have arrived at the optional solution in using the Time_Cost CPM Scheduling model analysis when what happens? - ANSWERS -You have reached minimum total cost Project management software available today combines CPM and other scheduling aids, like Gantt charting, to aid in tracking progress of project completion. - ANSWERS -True

Show more Read less
Institution
POM
Module
POM









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
POM
Module
POM

Document information

Uploaded on
October 2, 2025
Number of pages
12
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

POM Exam 2 Questions with Complete
Solutions13

Production Requirement Formula - ANSWERS -Demand Forecast + (demand forecast x Required
safety stock in decimals ex. 20% = 0.20) - beginning inventory



The objective of the Aggregate Operations Plan is to insure that the marketing and sales plan
are realistic - ANSWERS -False



The main purpose of the aggregate operations planning is to specify the optimal combination of
which of the following? - ANSWERS -Workforce levels and inventory on hand



Which of the following methods discussed in the text requires generating several alternative
aggregate plans? - ANSWERS -Cut and Try



Aggregate Planning Techniques is developed from the master schedule and the strategic
capacity plan. - ANSWERS -False



The critical path of activities in a project is the sequence of activities that form the shortest
chain in a project network of activities. - ANSWERS -False



You know when you have arrived at the optional solution in using the Time_Cost CPM
Scheduling model analysis when what happens? - ANSWERS -You have reached minimum total
cost



Project management software available today combines CPM and other scheduling aids, like
Gantt charting, to aid in tracking progress of project completion. - ANSWERS -True

, A project may be designed as a series of related jobs directed toward some major output and
requiring a significant period of time to perform - ANSWERS -True



A simple project listing of five activities and their respective time estimates are presented below

Activity - Immediate Predecessor - Time in Days

A - none - 1

B-A-2

C --------A--------------------------1

D --------B&C-----------------------3

E -----------------D-----------------2 - ANSWERS -A,B,D,E



You have been placed in charge of a large project. Shortened communication lines are required
to ensure quick resolution of problems as they arise. You recognize that the project is going to
take a lot of time and require a lot of team pride, motivation, and commitment by all members.
Which project management structure should you use in this situation? - ANSWERS -Pure Project



PERT is an abbreviation for which of the following methodologies? - ANSWERS -Program
Evaluation and Review Technique



Check out Time Cost CPM Scheduling Model Analysis in Book - ANSWERS -I'll add the page
number later but should be chapter 5



The major goal of critical path analysis is to - ANSWERS -To determine when each activity in the
project should be scheduled



Earned Value Managament (EVM) has the capability to continue measurements of scope,
schedule, and cost in a project. - ANSWERS -True
£9.21
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached


Also available in package deal

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Bensuda Oxford University
Follow You need to be logged in order to follow users or courses
Sold
846
Member since
3 year
Number of followers
445
Documents
21389
Last sold
16 hours ago
ECONOMICS,NURSING,BIOLOGY AND ALL REVISION MATERIALS

DEDICATED TO PROVIDE YOU WITH THE BEST LEARNING MATERIALS THAT WILL IMPROVE YOUR GRADES ,WELCOME TO ALIZGRADES AND LETS DO IT TOGETHER!!! GOODLUCK!!!!!!!

3.7

158 reviews

5
74
4
24
3
25
2
11
1
24

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Frequently asked questions