100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

Engineer BOLC (EBOLC) Comprehensive Study Guide & Practice Test 2025/2026 QUESTIONS BANK AND VERIFIED CORRECT SOLUTIONS WITH RATIONALES || 100% GUARANTEED PASS <LATEST VERSION>

Rating
-
Sold
-
Pages
77
Grade
A+
Uploaded on
14-09-2025
Written in
2025/2026

Engineer BOLC (EBOLC) Comprehensive Study Guide & Practice Test 2025/2026 QUESTIONS BANK AND VERIFIED CORRECT SOLUTIONS WITH RATIONALES || 100% GUARANTEED PASS &lt;LATEST VERSION&gt; 1. Activity Estimate Worksheet - ANSWER a planning tool for developing an estimate of material, manpower, equipment and time required to complete a specific activity within a logic network of construction tasks 2. Bill of Materials (BOM) - ANSWER comprehensive list of materials, stock numbers, and prices required to complete the full scope of an assigned construction mission 3. Construction Directive - ANSWER Formal notification to initiate planning and execution of a construction mission. Generated at the battalion level or higher, the directive defines the location and scope of work, establishes specific milestones, and sets the project's Estimated Start Date (ESD) and Estimated Completion Date (ECD) 4. Construction Mission File - ANSWER A complete historical record of a project from inception to completion. The file will include the original construction directive with all amendments and extensions, construction briefs and the OPORD, inspection reports, AARs, plans, specifications, the BOM, Construction Reports, the CPM, CWE, CWS, all related correspondence, photographic documentation, and the acceptance letter. 5. Construction Work Schedule (CWS) - ANSWER a chart that depicts the activities generated for the CPM in calendar form, showing early start and late start times, and float 6. Critical Path Method (CPM) - ANSWER Involves determining the longest path through the network diagram, the earliest and latest an activity can start, and the earliest and latest activities can be completed 7. Gantt Chart - ANSWER a project management tool that depicts project activities, their assigned resources, start and end dates, durations, and interdependencies. 8. Letter of Acceptance - ANSWER A letter that serves as official closure and completion of the project, stating that the constructing unit has met the requirements and expectations of the customer. The letter includes multiple signature blocks for all parties involved (the constructing unit, S3 Construction, and the customer) 9. Logic Network - ANSWER Commonly referred to as a network diagram, it is the representation of project activities in an array of parallelograms with lines drawn to show their interdependencies without a time scale. Is used to analyze the critical path(s) in a project (CPM) 10. Command Sergeants Major - ANSWER -Provides management mentorship and guidance to first sergeants -Provides input to the Battalion Commander on strategic goal alignment with construction-related activities 11. Operations Officer, S-3 - ANSWER -Overall responsible for the management and prioritization of construction projects for the battalion -Directs equipment and personnel support between companies as requested by the constructing unit -Provides guidance to the CMS as necessary 12. S-3 Construction Management Section (CMS) - ANSWER -The CMS cell is the liaison to other units and organizations on the installation concernig all construction efforts for the battalion. He/she determines the feasibility and scope for all potential projects and presents them to the BN CDR for battalion acceptance -Issues Troop Construction Directives to the companies. Construction Directives will contain the following documents: a. Construction Directive memorandum outlining the project b. Statement of work containing specific design requirements for constructing units. c. Plans and specifications for the construction project d. Any other pertinent information BN CMS finds necessary to include in the directive -Reviews directives, plans, specifications and bills of materials (BOM). Develops the same if not provided externally. Final approval of all plans and drawings. -Conducts pre-design conferences, and 30%, 60%, and 90% design reviews of all construction missions. At a minimum, this meeting should involve the customer and the BN Technical Headquarters Section. -Reviews the Project OIC's CWS, CPM, Level III Gantt chart, risk assessment (DRAW), project management plan, and construction OPORD prior to the Pre-Construction Brief (PCB) to the Battalion Commander. -Monitors and ensures the mission milestone target dates are met. -Acquires and provides DA 4283's (Facilities Engineering Work Request), where applicable, dig permits, and other necessary paper work needed to conduct construction missions. -Provides Quality Assurance (QA). Inspects active missions to ensure high quality construction, adherence to plans and specifications, timely mission completion, and safety compliance. Will forward copies of all QA reports to the constructing unit commander as well as filing a copy in the BN project folder -Receives daily and weekly construction reports from companies 13. What type of command is typically led by a four star general and is responsible for all military operations in a geographical area? Army Service Component Command Combatant Command (COCOM) FORSCOM 14. Brigade - ANSWER Combatant Command (COCOM) 15. T/F A Squad is the smallest unit in the U.S. Army - ANSWER False 16. OPCON is a ______ relationship, while Direct Support is a ______ relationship - ANSWER command, support 17. Military symbols and terms are found in which pieces of U.S. Army doctrine? Select the answer with both correct. ADP 1-02, FM 1-02.1 ATTP 2-01, FM 1-02.1 FM 3-90-1, FM 3-90-2 FM 100, FM 3-34.85 - ANSWER ADP 1-02, FM 1-02.1 18. Which of the following is a combined arms organization formed by attaching one or more nonorganic armor, mechanized infantry, Stryker infantry, or light infantry platoons to a tank, mechanized infantry, Stryker, or infantry company either in exchange for, or in addition to its organic platoons? Task Force Regimental Combat Team Company Team Battle Group - ANSWER Company Team 19. Engineer Tasks - ANSWER Provide freedom of action at the objective. Clearing, reducing, emplacing, building, repairing... Obstacle Reduction Route Clearance Technical Rescue Infrastructure Assessments 20. Mobility Operations - ANSWER combined arms activities that mitigate the effects of obstacles to enable freedom of movement and maneuver. 21. 6 Primary Tasks of Mobility Operations - ANSWER Breaching * Gap-Crossing ** Clearing (Area & Route) * Combat Roads/Trails * Forward Airfields/LZs * Traffic Operations 22. Assured Mobility - ANSWER A framework of processes, actions, and capabilities that assures the ability of a force to deploy, move, and maneuver where and when desired, to achieve the commander's intent. 23. Strategic, Operational, Tactical Levels - ANSWER Tactical: Company Operational: Battalion/Brigade Strategic: Division and higher

Show more Read less
Institution
EBOLC
Module
EBOLC











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
EBOLC
Module
EBOLC

Document information

Uploaded on
September 14, 2025
Number of pages
77
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

Engineer BOLC (EBOLC) Comprehensive Study Guide
& Practice Test 2025/2026 QUESTIONS BANK AND
VERIFIED CORRECT SOLUTIONS WITH RATIONALES ||
100% GUARANTEED PASS
<LATEST VERSION>


1. Activity Estimate Worksheet - ANSWER ✓ a planning tool for developing
an estimate of material, manpower, equipment and time required to complete
a specific activity within a logic network of construction tasks

2. Bill of Materials (BOM) - ANSWER ✓ comprehensive list of materials,
stock numbers, and prices required to complete the full scope of an assigned
construction mission

3. Construction Directive - ANSWER ✓ Formal notification to initiate
planning and execution of a construction mission. Generated at the battalion
level or higher, the directive defines the location and scope of work,
establishes specific milestones, and sets the project's Estimated Start Date
(ESD) and Estimated Completion Date (ECD)

4. Construction Mission File - ANSWER ✓ A complete historical record of a
project from inception to completion. The file will include the original
construction directive with all amendments and extensions, construction
briefs and the OPORD, inspection reports, AARs, plans, specifications, the
BOM, Construction Reports, the CPM, CWE, CWS, all related
correspondence, photographic documentation, and the acceptance letter.

5. Construction Work Schedule (CWS) - ANSWER ✓ a chart that depicts the
activities generated for the CPM in calendar form, showing early start and
late start times, and float

6. Critical Path Method (CPM) - ANSWER ✓ Involves determining the longest
path through the network diagram, the earliest and latest an activity can start,
and the earliest and latest activities can be completed

,7. Gantt Chart - ANSWER ✓ a project management tool that depicts project
activities, their assigned resources, start and end dates, durations, and
interdependencies.

8. Letter of Acceptance - ANSWER ✓ A letter that serves as official closure
and completion of the project, stating that the constructing unit has met the
requirements and expectations of the customer. The letter includes multiple
signature blocks for all parties involved (the constructing unit, S3
Construction, and the customer)

9. Logic Network - ANSWER ✓ Commonly referred to as a network diagram,
it is the representation of project activities in an array of parallelograms with
lines drawn to show their interdependencies without a time scale. Is used to
analyze the critical path(s) in a project (CPM)

10.Command Sergeants Major - ANSWER ✓ -Provides management
mentorship and guidance to first sergeants
-Provides input to the Battalion Commander on strategic goal alignment
with construction-related activities

11.Operations Officer, S-3 - ANSWER ✓ -Overall responsible for the
management and prioritization of construction projects for the battalion
-Directs equipment and personnel support between companies as requested
by the constructing unit
-Provides guidance to the CMS as necessary

12.S-3 Construction Management Section (CMS) - ANSWER ✓ -The CMS cell
is the liaison to other units and organizations on the installation concernig all
construction efforts for the battalion. He/she determines the feasibility and
scope for all potential projects and presents them to the BN CDR for
battalion acceptance
-Issues Troop Construction Directives to the companies. Construction
Directives will contain the following documents:
a. Construction Directive memorandum outlining the project
b. Statement of work containing specific design requirements for
constructing units.
c. Plans and specifications for the construction project

, d. Any other pertinent information BN CMS finds necessary to include
in the directive
-Reviews directives, plans, specifications and bills of materials (BOM).
Develops the same if not provided externally. Final approval of all plans and
drawings.
-Conducts pre-design conferences, and 30%, 60%, and 90% design reviews
of all construction missions. At a minimum, this meeting should involve the
customer and the BN Technical Headquarters Section.
-Reviews the Project OIC's CWS, CPM, Level III Gantt chart, risk
assessment (DRAW), project management plan, and construction OPORD
prior to the Pre-Construction Brief (PCB) to the Battalion Commander.
-Monitors and ensures the mission milestone target dates are met.
-Acquires and provides DA 4283's (Facilities Engineering Work Request),
where applicable, dig permits, and other necessary paper work needed to
conduct construction missions.
-Provides Quality Assurance (QA). Inspects active missions to ensure high
quality construction, adherence to plans and specifications, timely mission
completion, and safety compliance. Will forward copies of all QA reports to
the constructing unit commander as well as filing a copy in the BN project
folder
-Receives daily and weekly construction reports from companies

13.What type of command is typically led by a four star general and is
responsible for all military operations in a geographical area?

Army Service Component Command

Combatant Command (COCOM)

FORSCOM

14.Brigade - ANSWER ✓ Combatant Command (COCOM)

15.T/F A Squad is the smallest unit in the U.S. Army - ANSWER ✓ False

16.OPCON is a ______ relationship, while Direct Support is a ______
relationship - ANSWER ✓ command, support

, 17.Military symbols and terms are found in which pieces of U.S. Army
doctrine? Select the answer with both correct.
ADP 1-02, FM 1-02.1
ATTP 2-01, FM 1-02.1
FM 3-90-1, FM 3-90-2
FM 100, FM 3-34.85 - ANSWER ✓ ADP 1-02, FM 1-02.1

18.Which of the following is a combined arms organization formed by
attaching one or more nonorganic armor, mechanized infantry, Stryker
infantry, or light infantry platoons to a tank, mechanized infantry, Stryker, or
infantry company either in exchange for, or in addition to its organic
platoons?
Task Force
Regimental Combat Team
Company Team
Battle Group - ANSWER ✓ Company Team

19.Engineer Tasks - ANSWER ✓ Provide freedom of action at the objective.
Clearing, reducing, emplacing, building, repairing...
Obstacle Reduction
Route Clearance
Technical Rescue
Infrastructure Assessments

20.Mobility Operations - ANSWER ✓ combined arms activities that mitigate
the effects of obstacles to enable freedom of movement and maneuver.

21.6 Primary Tasks of Mobility Operations - ANSWER ✓ Breaching *
Gap-Crossing **
Clearing (Area & Route) *
Combat Roads/Trails *
Forward Airfields/LZs *
Traffic Operations

22.Assured Mobility - ANSWER ✓ A framework of processes, actions, and
capabilities that assures the ability of a force to deploy, move, and maneuver
where and when desired, to achieve the commander's intent.

23.Strategic, Operational, Tactical Levels - ANSWER ✓ Tactical: Company

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
ProfBenjamin Havard School
Follow You need to be logged in order to follow users or courses
Sold
404
Member since
1 year
Number of followers
14
Documents
2832
Last sold
9 hours ago
EXCELLENT ACHIEVERS LIBRARY

As a professional tutor, I provide exceptional assistance with homework, quizzes, and exams across various subjects, including Psychology, Nursing, Biological Sciences, Business, Engineering, Human Resource Management, and Mathematics. I am dedicated to offering high-quality support and ensuring that all work meets scholarly standards. To enhance the effectiveness of our services, I work with a team of experienced tutors to create comprehensive and effective revision materials. Together, we are committed to helping students achieve excellent grades through our collaborative efforts and expertise.

Read more Read less
3.9

75 reviews

5
35
4
11
3
21
2
4
1
4

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Frequently asked questions