/A j On-demand scheduling
B Resource leveling
C Critical path method
D Iterative scheduling with a backlog
You need to develop a new website for a large customer that is in the business of selling many types of
household products. You know that your organization did a similar project for a similar organization
and that website took six months to develop. You therefore estimate that this project will take about six
months as well. Which estimating tool do you use?
A T-shirt sizing
B Parametric estimating
C j Analogous estimating
D Relative estimating
As team members work with the product owner to prioritize user stories, it has become obvious that
they need a better understanding of the requirements because this is a new technology that they are
not familiar with. What is the best approach to handle this situation?
Extend the schedule of the sprints to allow for additional time to analyze the requirements
and the new system.
B Create a spike experiment for further investigation.
Adjust the sprints so that the first sprint focuses on learning the new system and
requirements.
D Ensure the team has the tools and information to perform further analysis.
, a
| Your project is running behind schedule, but you have plenty of float on some activities. You decide to
Al - S - o .
move resources from noncritical path activities to critical path activities. What are you performing?
X A Crashing
B Resource leveling
C Fast-tracking
D Resource smoothing
Your customer has approached you and told you that you now need to finish the project two weeks
earlier than anticipated. What does this mean in terms of the critical path?
A You have a positive float of two weeks.
B Your project will be delayed by two weeks.
C You have a project float of two weeks.
D You have a negative float of two weeks.
Your initial plan was to finish all configuration work before testing would start. However, due to some
delays, you have decided to start testing even though configuration is not yet complete. Which of the
following would best describe this situation?
A You have changed a finish to start to a start to start relationship.
B You have changed a mandatory dependency to a discretionary dependency.
C You have changed soft logic to hard logic.
D You have changed a start to finish relationship to a finish to start.