Owner Builder exam questions with 100% correct answers. /. At what depth of trench is shoring require / At what depth of an excavation is shoring required? - Answer-1.2 M or 4 Feet /.How can shoring be done past 4 feet? - Answer-This can be done with purpose-built shoring, or, it is acceptable to use plywood if it is properly constructed. /.Which of the following is not an acceptable method for determining the correct grading for a trench? - Answer-experienced contractor says it's ok /.Before a worker enters any excavation over 1.2 m (4 ft) in depth or, while in the excavation, approaches closer to the side or bank than a distance equal to the depth of the excavation, the employer must ensure that the sides of the excavation are - Answer-(a) sloped as specified in writing by a qualified registered professional, (b) sloped at angles, dependent on soil conditions, which will ensure stable faces, but in no case, may the slope or combination of vertical cut and slope exceed that shown in Figure 20-1, (c) benched as shown in Figure 20-2, (d) supported as specified in writing by a professional engineer, (e) supported in accordance with the minimum requirements of section 20.85, or (f) supported by manufactured or prefabricated trench boxes or shoring cages, or other effective means. /.Which best describes the design principle of rain water deflection? - Answer-Design and construction which stops water from ever entering /.What lighting certifications are required in Canada? - Answer-CSA safety certification /.What grit of sandpaper would get smoothest result? 150-180 etc. - Answer-The higher the grade, the smoother the finish. When finishing a surface, you typically start with a low grit and work up to a high grit. /.What is the maximum rise in a flight of stairs? a. The vertical height any flight stairs - Answer-The vertical height shall not exceed 3.7 M /.What is the minimum distance that a ladder must extend above a parapet wall or landing? - Answer-3 feet /.If you have a 4m ladder, how far from the wall does the base of the ladder have to be? - Answer-74 degrees or 4:1 ratio. So 4 m ladder, needs to be 1 m away. /.What heights are end dams to be on window and door flashings? - Answer-25 mm / 1 inch (from BCBC) /.When to call for inspections and how to make them efficient as possible? - Answer-Group together when possible and call when work is complete /.When is an HRV required? - Answer-Almost always: "Effective December ϭε, ϮϬϭκ residential dwelling units, such as houses, apartments and secondary suites will be required to have a principal ventilation system that exhausts air from bathrooms and kitchens and supplies fresh air to bedrooms and living areas [ε.ϯϮ.ϯ.ϯ." "Some small dwelling units in mild climates are permitted to supply fresh air through passive vents [9.32.3.4.(6)], but for most dwelling units exhaust and supply will require a mechanical fan" /.What can you build under the owner-builder HPO process? - Answer-Single detached home under a single title. One single dwelling unit in or attached to a pre-existing building older than 10 years (includes the addition of a unit to convert a detached home to a duplex, or conversion of a duplex to triplex, or conversion of non -residential space to a dwelling unit). One single dwelling unit in or attached to a new non-residential building (one only per building, such as a caretaker suite or home built above a family-run store). 12. Who issues permits for a gas fireplace? /.Which of the following is not allowed under the HPO owner-builder program? - Answer-A new dwelling unit attached to building *newer* than 10 years old /.Who issues permits for a gas fireplace? - Answer-The Safety Authority - Now called Technical Safety BC /.Can an owner builder take out his or her own electrical permit? - Answer-Yes -work up to 200A is allowed. /.What types of Buildings that Can be Wired by Homeowners? - Answer-You are entitled to do electrical work in a fully detached residential dwelling that you occupy or intend to occupy. Your dwelling may not contain a suite. Fully detached dwellings are buildings that are designed for single family use only. You are not allowed to do electrical work in or on any buildings if: ͻ you do not live in or intend to live in the dwelling, ͻ any part of the building includes a separate self-contained suite or occupancy, ͻ the building, or any part of the building is being used to provide rental income, or ͻ the building, or any part of the building is used for commercial purposes. /.What is the best practice to apply asphalt waterproofing on a foundation? - Answer-Spray-on or roll on dry foundation with 2inch (max) below grade /.What is best practice for waterproofing on foundation? - Answer-Spray or roll 12 inch above grade on dry surface /.When is the appropriate time to backfill a foundation? - Answer-After Damp-proofing /.Where does one apply Damp-proofing Material - Answer-Exterior damp-proofing shall be applied from finished ground level to the top of the exterior of the footing. /.What do you need to do when applying a peel and stick waterproof membrane foundation? - Answer-Use an approved primer before installing /.The distance from the gas vent to the roof must be... - Answer-...greater than the overhang of the roof. Nothing (no gas appliance exhaust vents) within 1m either side and 4.5 meters above. Any powered air intake must not be within 3 meters. /.When do you need to install a handrail, or have worker wear fall protection? - Answer-10 feet above grade /.If a worker has no fall protection, at what height must a handrail be provided? - Answer-4 feet /.How high does a construction fence around a site needs to be? - Answer-6 feet /.When installing the footer, it was dug down 2 inches deeper then what the elevation should be. What needs to happen? - Answer-Install the footing form at proper elevation and fill with extra concrete /.When installing flashing for a roof valley how much do the asphalt shingles need to overlap it? - Answer-6 inches /.What would cause a Blister on a flat roof? - Answer-Moisture trapped under roof

Show more Read less
Institution
Owner Builder
Module
Owner Builder

Content preview

Owner Builder exam questions with 100% correct
answers.



/. At what depth of trench is shoring require / At what depth of an excavation is shoring
required? - Answer-1.2 M or 4 Feet

/.How can shoring be done past 4 feet? - Answer-This can be done with purpose-built
shoring, or, it is acceptable to
use plywood if it is properly constructed.

/.Which of the following is not an acceptable method for determining the correct grading
for a trench? - Answer-experienced contractor says it's ok

/.Before a worker enters any excavation over 1.2 m (4 ft) in depth or, while in the
excavation,
approaches closer to the side or bank than a distance equal to the depth of the
excavation, the employer must ensure that the
sides of the excavation are - Answer-(a) sloped as specified in writing by a qualified
registered professional,
(b) sloped at angles, dependent on soil conditions, which will ensure stable faces, but in
no case, may the slope or combination
of vertical cut and slope exceed that shown in Figure 20-1,
(c) benched as shown in Figure 20-2,
(d) supported as specified in writing by a professional engineer,
(e) supported in accordance with the minimum requirements of section 20.85, or
(f) supported by manufactured or prefabricated trench boxes or shoring cages, or other
effective means.

/.Which best describes the design principle of rain water deflection? - Answer-Design
and construction which stops water from ever entering

/.What lighting certifications are required in Canada? - Answer-CSA safety certification

/.What grit of sandpaper would get smoothest result? 150-180 etc. - Answer-The higher
the grade, the smoother the finish. When finishing a surface, you typically start with a
low grit and
work up to a high grit.

/.What is the maximum rise in a flight of stairs?

,a. The vertical height any flight stairs - Answer-The vertical height shall not exceed 3.7
M

/.What is the minimum distance that a ladder must extend above a parapet wall or
landing? - Answer-3 feet

/.If you have a 4m ladder, how far from the wall does the base of the ladder have to be?
- Answer-74 degrees or 4:1 ratio. So 4 m ladder, needs to be 1 m away.

/.What heights are end dams to be on window and door flashings? - Answer-25 mm / 1
inch (from BCBC)

/.When to call for inspections and how to make them efficient as possible? - Answer-
Group together when possible and call when work is complete

/.When is an HRV required? - Answer-Almost always:
"Effective December ϭε, ϮϬϭκ residential dwelling units, such as houses, apartments
and secondary suites will be required to have
a principal ventilation system that exhausts air from bathrooms and kitchens and
supplies fresh air to bedrooms and living areas
[ε.ϯϮ.ϯ.ϯ."
"Some small dwelling units in mild climates are permitted to supply fresh air through
passive vents [9.32.3.4.(6)], but for most
dwelling units exhaust and supply will require a mechanical fan"

/.What can you build under the owner-builder HPO process? - Answer-Single detached
home under a single title. One single dwelling unit in or attached to a pre-existing
building older than 10 years (includes
the addition of a unit to convert a detached home to a duplex, or conversion of a duplex
to triplex, or conversion of non -residential space
to a dwelling unit). One single dwelling unit in or attached to a new non-residential
building (one only per building, such as a caretaker suite
or home built above a family-run store).
12. Who issues permits for a gas fireplace?

/.Which of the following is not allowed under the HPO owner-builder program? -
Answer-A new dwelling unit attached to building *newer*
than 10 years old

/.Who issues permits for a gas fireplace? - Answer-The Safety Authority - Now called
Technical Safety BC

/.Can an owner builder take out his or her own electrical permit? - Answer-Yes -work up
to 200A is allowed.

, /.What types of Buildings that Can be Wired by Homeowners? - Answer-You are entitled
to do electrical work in a fully detached residential dwelling that you occupy or intend to
occupy. Your
dwelling may not contain a suite. Fully detached dwellings are buildings that are
designed for single family use only.
You are not allowed to do electrical work in or on any buildings if:
ͻ you do not live in or intend to live in the dwelling,
ͻ any part of the building includes a separate self-contained suite or occupancy,
ͻ the building, or any part of the building is being used to provide rental income, or
ͻ the building, or any part of the building is used for commercial purposes.

/.What is the best practice to apply asphalt waterproofing on a foundation? - Answer-
Spray-on or roll on dry foundation with 2inch (max) below grade

/.What is best practice for waterproofing on foundation? - Answer-Spray or roll 12 inch
above grade on dry surface

/.When is the appropriate time to backfill a foundation? - Answer-After Damp-proofing

/.Where does one apply Damp-proofing Material - Answer-Exterior damp-proofing shall
be applied from finished ground level to the top of the exterior of the footing.

/.What do you need to do when applying a peel and stick waterproof membrane
foundation? - Answer-Use an approved primer before installing

/.The distance from the gas vent to the roof must be... - Answer-...greater than the
overhang of the roof. Nothing (no gas appliance exhaust vents) within
1m either side and 4.5 meters above. Any powered air intake must not be within 3
meters.

/.When do you need to install a handrail, or have worker wear fall protection? - Answer-
10 feet above grade

/.If a worker has no fall protection, at what height must a handrail be provided? -
Answer-4 feet

/.How high does a construction fence around a site needs to be? - Answer-6 feet

/.When installing the footer, it was dug down 2 inches deeper then what the elevation
should be. What needs to happen? - Answer-Install the footing form at proper elevation
and fill with extra concrete

/.When installing flashing for a roof valley how much do the asphalt shingles need to
overlap it? - Answer-6 inches

/.What would cause a Blister on a flat roof? - Answer-Moisture trapped under roof

Written for

Institution
Owner Builder
Module
Owner Builder

Document information

Uploaded on
July 13, 2025
Number of pages
22
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

£11.95
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Brainariam Harvard University
Follow You need to be logged in order to follow users or courses
Sold
149
Member since
1 year
Number of followers
7
Documents
8376
Last sold
2 days ago

Our store offers a wide selection of materials on various subjects and difficulty levels, created by experienced teachers. We specialize on NURSING,WGU,ACLS USMLE,TNCC,PMHNP,ATI and other major courses, Updated Exam, Study Guides and Test banks. If you don't find any document you are looking for in this store contact us and we will fetch it for you in minutes, we love impressing our clients with our quality work and we are very punctual on deadlines. Please go through the sets description appropriately before any purchase and leave a review after purchasing so as to make sure our customers are 100% satisfied. I WISH YOU SUCCESS IN YOUR EDUCATION JOURNEY

Read more Read less
3.3

26 reviews

5
8
4
2
3
9
2
3
1
4

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions