Answers
____________ in a project schedule identify critical events and other
activities that must be performed by specific dates before the project
may proceed. correct answer Milestones
____________, project acceptance criteria, and technical requirements
are common components of project scope statements. correct answer
Project constraints
1. At the end of a project, the project manager documents the
____________ that provide valuable insights into what went well and
what went poorly on similar projects. correct answer 1. lessons learned
2. Examples of documenting ____________ include recording the
different points of a project where rework was required and where
additional resources were added. correct answer 2. lessons learned
A __________ budget distributes costs across the time periods of the
project. correct answer calendarized
A _________________ is characteristic of a project in need of extreme
project management methods. correct answer high level complexity
,A decrease in the ____________ can lead to a shortened project
schedule and/or lower project costs. correct answer project scope
A decrease in the original ____________ may make it possible to
increase the project scope and/or add materials or resources that make
it possible to speed up the project schedule. correct answer project
costs
A linear path and sequential steps are defining characteristics of
___________ project management methods. correct answer traditional
A timeline that specifies when the project begins and when it is
supposed to end is called a ____________. correct answer project
schedule
A typical example of ____________ in a project is the involvement of
many different people, many different materials, and many different
outcomes. correct answer complexity
According to the ____________, a project manager should avoid
controlling tasks that take less than eight hours and should not let more
than two weeks go by without checking in. correct answer 8 and 80
Rule
, Any variances from the ____________ will be compared with the
baseline requirements and approved changes once a project is
completed. correct answer initial cost, schedule, or deliverables
At which level in the OPM3 is there more refined documentation,
consistent management support, consistent execution, and efficiency
across all projects?
Level 5
Level 2
Level 3
Level 4 correct answer Level 4
Budget are created through the careful and complete documentation of
the assumptions that come from the ___________ phase. correct
answer project planning
During what kind of meeting does each leader speak to the status of
their work and project risks, and explain the status of any mitigation
activities?
Monthly customer meeting
Monthly management project review
Internal management project review
Weekly internal status meeting correct answer Weekly internal status
meeting