PRACTICE EXAM QUESTIONS
WITH CORRECT DETAILED
ANSWERS | ALREADY GRADED
A+<RECENT VERSION>
1) Project delivery system - answer how team members are organized,
establishes when parties engage, determines roles of parties, and
determines sequence of design, procurement, and construction (db, cmar,
dbb)
2) Procurement method - answer how team members are selected (qbs,
best value, low price, sole source)
3) Contracting approach - answer how team members are paid (fp, gmp,
cost reimbursement, target price, unit price)
4) Design-bid-build (dbb) - answer linear, sequential process, a/e
selected on qualifications, gc selected on low price, design is fully
completed without input from gc, a/e acting in owner's interests, with a
historically strong bond, process is well-established and understood
5) Construction manager at risk - answer similar org structure to dbb,
construction manager selected by qbs or best value, contractor provides
precon services, negotiated gmp contracting approach, open book
, estimating process, potential to fast track project, construction cost
determined before design completed, potential issues over what is
reasonably inferable from gmp design documents
6) Design-build - answer the owner contracts with one entity (a person or
firm) to provide both design and construction services, designer and
contractor have a direct contractual relationship, selected by qbs or best
value, wide spectrum of contracting approaches and organizational
structures, single point responsibility, owner does not manage designer,
owner exposure to claims is significantly reduced
7) Engineer procure construct (epc) - answer similar to design build, in
industrial and power generation sectors, systems and performance testing
are central to scope, contractor will typically perform engineering with its
in-house staff, owner has need for single point responsibility, contracts
include plant and process performance guarantees, contract items include
performance and schedule liquidated damages and limitations of liability
8) Multiple prime contracting - answer owner contracts with multiple
trade contractors, attributes are typically similar to dbb, owner's ability to
schedule and coordinate the work
9) Integrated project delivery (ipd) - answer multi-party agreement - all
parties equal, qbs procurement and target pricing contract approach,
private sector use (limited at this time), key: owner's ability to accept risk
10) Public-private partnership (p3) - answer instead of government
building and maintaining major infrastructure (such as highway, water
treatment plant), build and maintenance is outsourced to a private
company. Opposed by public sector unions. This is not considered a
delivery system but its underlying approaches are delivery systems and
typically use db. Multiple procurement and contracting approaches
, 11) Shift left - answer intense efforts to establish scope early in the
process; drives early team formation to include key trade subcontractors;
can enable big decisions to be made early, affect project outcomes at
lowest cost, establish a need for co-location and collaboration, and
compress time during concurrent design and construction
12) Traditional design build - answer typically two-phase best value
procurement with lump sum contract; owner defines project requirements
and scope of prescriptive work; use of performance-based technical
requirements with limited prescriptive specifications
13) Progressive design build - answer design and price are
progressively developed after the design-builder is under contract; final
project cost and schedule commitment is not established as part of the
selection process; two phases: preliminary services and final design and
construction services
14) Criteria documents - answer describe the end result
15) Bridging documents - answer prescribes how to achieve the end
result
16) Design bid build paradigm - answer prior to bidding, owner
undertakes a process to design the project and all of its details to 100%
complete plans and specs. The owner is therefore responsible for success
or failure of details of the design, and warrants the sufficiency of design
to the contractor. The owner is therefore liable to the contractor for any
gaps between plans and specifications and owner's requirements for
project performance
17) Design details responsibility - answer the owner should define
its performance requirements and award the contract on the basis of
preliminary design; this makes the design-builder responsible for