NC Building Contractor License EXAM QUESTIONS WITH CORRECT ANSWERS SOLVED AND 100% VERIFIED..0149 of an inch - CORRECT ANSWERMetal veneer siding shall have a minimum thickness of______ .25 of an inch - CORRECT ANSWERThe minimum thickness for fiber cement lap siding as weather covering is _____ #12 - CORRECT ANSWERThe minimum size screws used to attach steel decking are__________. $100,000 - CORRECT ANSWERThe Miller Act requires that all federal projects exceeding ____________ must be bonded. $152,000 - CORRECT ANSWERIf a contractor made $38,000 on a project and this represented 25% profit, what was the total amount of the project?

Show more Read less











Whoops! We can’t load your doc right now. Try again or contact support.

Document information

Uploaded on
June 16, 2025
Number of pages
40
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

NC Building Contractor License EXAM
QUESTIONS WITH CORRECT ANSWERS SOLVED
AND 100% VERIFIED.


- CORRECT ANSWER✅✅✅What board is nailed to the end of a rafter tail?



.0149 of an inch - CORRECT ANSWER✅✅✅Metal veneer siding shall have a minimum thickness
of______



.25 of an inch - CORRECT ANSWER✅✅✅The minimum thickness for fiber cement lap siding as
weather covering is _____



#12 - CORRECT ANSWER✅✅✅The minimum size screws used to attach steel decking
are__________.



$100,000 - CORRECT ANSWER✅✅✅The Miller Act requires that all federal projects exceeding
____________ must be bonded.



$152,000 - CORRECT ANSWER✅✅✅If a contractor made $38,000 on a project and this represented
25% profit, what was the total amount of the project?



$50,441 - CORRECT ANSWER✅✅✅If your account balance is $47,382 on May 11th and during May
you pay $11,318 worth of involces, and you deposit $14,377, what is your balance on June 2nd?



$6,740 - CORRECT ANSWER✅✅✅The schedule of values for a project shows Task A is worth
$18,000, Task B is worth $6,500 and Task Cis worth $45,000. Task A is 16% complete. Task B is 4%
complete and Task Cis 8% complete. What is the value of the progress payment due?

,0.024 inches - CORRECT ANSWER✅✅✅What is the minimum thickness of aluminum used as valley
lining material?



0.028 - CORRECT ANSWER✅✅✅Weld washers are recommended for metal thickness less
than_______.



1 - CORRECT ANSWER✅✅✅Plain bevel siding must overlap at least ________ inches.



1 1/2 inch - CORRECT ANSWER✅✅✅Clear space between a handrail and a wall/ surface shall be not
less than _____



1 1/2 inch - CORRECT ANSWER✅✅✅What is the minimum concrete cover (in inches) for a W31
piece of rebar, when using Hign- early strength concrete on a patio slab?



1 1/2 inch. 3 inches - CORRECT ANSWER✅✅✅The ends of arch joist shall have not less than
________ inches of bearing on wood/metal or not less than ______ on masonry



1 1/2 to 1 3/4 percent - CORRECT ANSWER✅✅✅What is the allowable slope for a side-to side
sloped soccer field.



1 3/4 inches - CORRECT ANSWER✅✅✅Max 2 inches circular handrails shall have a diameter no more
than _____ and no greater than _____



1 Acre or Larger - CORRECT ANSWER✅✅✅An erosion and sedimentation control plan must be
approved before land distrubance begins on any site ______



1 inch - CORRECT ANSWER✅✅✅The edges of lugs, brackets, rivets and bolt heads attached to
structural members shall be permitted to extend to within ___ of the surface of the fire
protection/fireproofing



1 inch - CORRECT ANSWER✅✅✅The maximum distance to cut back the sheathing from a post-
tension strand for the anchor is______.

,1 inch - CORRECT ANSWER✅✅✅Ventilation requirements: an air space/gap of ___ is required
between the insulation and the roof sheathing



1 layer of felt - CORRECT ANSWER✅✅✅Underlayment application: for roof slopes 4 units in 12 units
horizontal (33% slope) ___________ is required



1 unit vertical and 12 units horizontal - CORRECT ANSWER✅✅✅Ramps used as part of a means of
egress shall have a running slop no steeper than __ vertical in ___ horizontal



1-1/2 - CORRECT ANSWER✅✅✅The sidelap or offset for wood shingles and shakes must be
_________ inches.



1-1/2 - CORRECT ANSWER✅✅✅The space between a wall and a grab bar shall be _____ inches.



1-1/2 horizontal to 1 vertical - CORRECT ANSWER✅✅✅The maximum slope allowed for excavation
less than 20 feet in total depth in a Type C soilis ___________.



1-1/2 hours, 300 revolutions - CORRECT ANSWER✅✅✅When it comes to ready mixed concrete,
what period of time do you have from batching at the plant to complete discharge on the jobsite?



1-1/2 x 3-1/2 - CORRECT ANSWER✅✅✅The actual size of a 2 x 4 is___________.



1:12 - CORRECT ANSWER✅✅✅The maximum slope of a ramp is ________?



1:12 - CORRECT ANSWER✅✅✅Which of the following is the maximum slope allowed for a ramp?



1:20(5%slope) - CORRECT ANSWER✅✅✅10 feet Site grading: the grade shall be sloped away from a
building no less than ______ for a minimum distance of ______ feet.

, 1.054 - CORRECT ANSWER✅✅✅The roof slope factor for a 4 in 12 roof slope is__________.



1.5. 4 - CORRECT ANSWER✅✅✅Normally the travel speed of a dozer is ______ to ______ mph.



1) Chain and hook through the center of the bundles

2) Forklift blades

3) Nylon straps used as a choker

4) None of the above. ******* - CORRECT ANSWER✅✅✅The best method for unloading post-
tensioning cable would be..



1/2 - CORRECT ANSWER✅✅✅A concrete wearing surface like terrazzo is typically ________ inch
thick.



1/2 inch thick - CORRECT ANSWER✅✅✅Combustible insulating boards no more than___ & covered
with finish flooring are permitted when attached directly to non combustible floor or wood subfloor
attached to sleepers



1/2 inch type X gypsum board (private garage separated from dwelling unit and its attic) - CORRECT
ANSWER✅✅✅What must be applied to structures supporting the separation from habitable rooms
above the garage?



1/2 inch. 6 feet 15 inches - CORRECT ANSWER✅✅✅Roof diaphragms shall be anchored to masonry
walls with ______. diameter bolts ________feet on center or their equivalent. Bolts shall extend and be
embedded at least _____ inches into the masonry.



1/2" - CORRECT ANSWER✅✅✅When wood beams are placed inside a masonry or concrete pocket
how much clearance is required on top, sides and end of the beam?



1/3 - CORRECT ANSWER✅✅✅The total area of mezzanines must not exceed _____ of the room in
which it is located
£6.19
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached

Get to know the seller
Seller avatar
StudyAceHub

Get to know the seller

Seller avatar
StudyAceHub Abacus College, Oxford
View profile
Follow You need to be logged in order to follow users or courses
Sold
1
Member since
11 months
Number of followers
0
Documents
731
Last sold
1 month ago
Comprehensive Study Guides materials and simplified exam prep Q and A .

0.0

0 reviews

5
0
4
0
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Frequently asked questions