Project Management Professional (PMP)Certification Exam – Complete Guide to Passing the PMI PMP Test for Career Advancement Project Management Professional (PMP) Certification Exam – Complete Guide to Passing the PMI PMP Test for Career Advancement 1.While monitoring and controlling the project, the project manager and the team have consistently received broken equipment from a particular vendor. They have spoken with the vendor and implemented a new process that will ensure the equipment does not show up broken. This seems to have solved the problem. What is the next step the project manager should take? A. Investigate the problem B. Check the solution C. Analyze the problem D. Solve the problem – - correct ans- -B. Check the solution Explanation {When encountering any problem on a project, the project manager should first identify the problem, define the problem, investigate, analyze, solve, and then check the solution. In this situation, the problem has already been solved, so the next step would be to check the solution to ensure the problem has actually been solved.} 2.Senior management has requested an update to the current product upgrade project. The project manager knows she has to keep the information high level and as short as possible. Which resource would be the best to show senior management? A. Milestone chart B. Project schedule network diagram C. WBS dictionary D. WBS - correct ans- -A. Milestone chart Explanation {A milestone chart shows only the major start and end of the major deliverables. All other choices such as the WBS, WBS dictionary, and the network diagram are very detailed.} 3.John is working on a project that he knows little about. He was assigned by the project management office (PMO) and they have almost complete control over the project. What type of PMO best describes this scenario? A. Controlling B. Directive C. Guiding D. Supportive - correct ans- -B. Directive 4.Dolly's new project staff are some of the best talents in the organization. The team members will use their own methodologies and prefer to be in control of the project; they would only like to be provided templates and lessons learned from other projects.

Show more Read less
Institution
Project Management Professional Certification
Module
Project Management Professional Certification











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Project Management Professional Certification
Module
Project Management Professional Certification

Document information

Uploaded on
June 5, 2025
Number of pages
133
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

Project Management Professional
(PMP)Certification Exam – Complete Guide
to Passing the PMI PMP Test for Career
Advancement
[Document subtitle]

, Project Management Professional (PMP)
Certification Exam – Complete Guide to Passing the
PMI PMP Test for Career Advancement



1.While monitoring and controlling the project, the project manager and the team have
consistently received broken equipment from a particular vendor. They have spoken
with the vendor and implemented a new process that will ensure the equipment does
not show up broken. This seems to have solved the problem. What is the next step the
project manager should take?

A. Investigate the problem

B. Check the solution

C. Analyze the problem

D. Solve the problem –
- correct ans- -B. Check the solution



Explanation

{When encountering any problem on a project, the project manager should first identify
the problem, define the problem, investigate, analyze, solve, and then check the
solution. In this situation, the problem has already been solved, so the next step would
be to check the solution to ensure the problem has actually been solved.}



2.Senior management has requested an update to the current product upgrade project.
The project manager knows she has to keep the information high level and as short as
possible. Which resource would be the best to show senior management?



A. Milestone chart

B. Project schedule network diagram

C. WBS dictionary

D. WBS

- correct ans- -A. Milestone chart
[1]

,Explanation

{A milestone chart shows only the major start and end of the major deliverables. All
other choices such as the WBS, WBS dictionary, and the network diagram are very
detailed.}



3.John is working on a project that he knows little about. He was assigned by the project
management office (PMO) and they have almost complete control over the project.
What type of PMO best describes this scenario?



A. Controlling



B. Directive



C. Guiding



D. Supportive
- correct ans- -B. Directive



4.Dolly's new project staff are some of the best talents in the organization. The team
members will use their own methodologies and prefer to be in control of the project;
they would only like to be provided templates and lessons learned from other projects.
What type of PMO would be best for this project?



A. Controlling



B. Directive



C. Supportive



D. Managing
- - correct ans- -C. Supportive


[2]

, 5.Denny is working in an organization where she does project management full time.
However, she still needs to consults with functional managers in order to acquire her
project team. What organizational structure type best describes this situation?



A. Functional



B. Strong Matrix



C. Project Oriented



D. Weak Matrix
- correct ans- -D. Weak Matrix



6.Chris has just gotten a new job at an organization where everyone works from home.
His job is to manage a team of software developers around the world to create a new
billing
system. Everyone on the project will be working from home, and Chris will be managing
the project full time. What type of organizational structure is this?



A. Virtual



B. Online



C. Virtual Strong Matrix



D. Online Strong Matrix
- correct ans- -A. Virtual



7.ABX Shipping is a large global organization with many departments, some of which
are have part-time project management and others, such as research and development,
where it is full time. Where the project managers work determines their control over
resources. What organizational structure best describes this organization?

[3]

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
NjoguAmos Exam
Follow You need to be logged in order to follow users or courses
Sold
18
Member since
3 year
Number of followers
18
Documents
614
Last sold
2 months ago

2.0

1 reviews

5
0
4
0
3
0
2
1
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Frequently asked questions