GE101: Introduction to General Engineering - ✔✔· Purpose of GE Module: Develop
officers with ability to plan and generate General Engineering effects in support of the
maneuver commander during ULO
· Definition of GE: Those engineering capabilities and activities other than combat
engineering that modify, maintain, or protect the physical environment.
· GE is utilized in support of: - ✔✔o Defense- Continuously conducted to harden and
prepare positions, facilities, installations
o Offense- Providing assured mobility of forces from ports of debarkation to forward
AOs
o Stability- Focus is likely GE capabilities applied to restore essential services and
support infrastructure development
Geospatial - ✔✔supports vertical and horizontal construction
GE104: Engineer Reconnaissance - ✔✔· Engineer Reconnaissance Is NOT a FORM of
reconnaissance. The forms are route, zone, area, reconnaissance in force, and special.
· USACE Contingency Elements (UCE): Forward Support Team Advance (FEST-A),
Reconnaissance Team (RT), Advanced Echelon (ADVON) Team, Contingency Engineer
District (CED).
COPYRIGHT © 2025 BY GRACE AMELIA, ALL RIGHTS RESERVED 1
,· Technical Reconnaissance vs. Tactical Reconnaissance
GE105: Planning Construction Operations - ✔✔Projects come from requestor (unit or
installation entity) identifies a need which can be met by engineer support
MDMP in Construction Planning 1 of 2 - ✔✔o MDMP Step 1: Receive Mission->
Understand what you actually need to do. Gather tools, time analysis, higher intent,
shortfalls, Excess. Do not overlook geospatial.
o MDMP Step 2: Mission Analysis-> Compile analysis into one effort. Involve BDE S2
Geospatial cell
MDMP in Construction Planning 2 of 2 - ✔✔o MDMP Step 3-6: COA development,
COA analysis, COA comparison, COA approval
o MDMP Step 7: Rehearsals
Real Estate - ✔✔The overall collection of property
When planning construction operations also account for...? - ✔✔· Protection
Considerations, Sustainment Considerations...
MDMP COA development produces what? - ✔✔· different designs to meet the
commander's intent.
GE107: Project Management - ✔✔Is application of knowledge, skills, and resources to
accomplish activities that are intended to achieve a specific goal.
· A project will: - ✔✔o Not be part of ongoing day to day business.
o Involve notable risk.
o Be significantly impacted upon failure of activities.
Have at least 2 people or elements working together
COPYRIGHT © 2025 BY GRACE AMELIA, ALL RIGHTS RESERVED 2
, Project Components - ✔✔o Time- Time to complete the project as reflected in your
project schedule.
o Money- Project budget based on cost of the resources.
Scope- Goals and tasks of project and work required to complete them
Project Steps - ✔✔Defining/Initiating, Planning, Doing/Executing, Reviewing,
Monitoring and Controlling
Resource Estimation - ✔✔Reference: · Work rates from Page 174 in Battle Book, Activity
Estimation Steps (6 steps).
Standard Effort Equation - ✔✔(Quantity) X (Work Rate)
Troop Effort Equation - ✔✔(Standard Effort) / (Efficiency)
Duration Equation - ✔✔(Troop Effort) / (Crew Size)
Project Equation Table - ✔✔Quantity Work Rate Standard Effort Efficiency Troop Effort
Crew Size Duration Remarks
· Node Time Estimate: - ✔✔o Forward Pass: (Early Start) + (Duration) = (Early Finish)
o Backward Pass: (Late Finish) - (Duration) = (Late Start)
Critical Path Characteristics - ✔✔o Longest time path through the network
o Has no float
o (Early Start) = (Late Start), (Early Finish) = (Late Finish)
Total Float - ✔✔o Total Float (TF): Amount of time an activity can be delayed without
delaying project
TF=LS-ES or TF=LF-EF