Answers 100% pass
USACE Response Options - ✔✔Forward Engineer Support Team-Advance (FEST-A) or
Reconnaissance Team (RT)
Advanced Echelon (ADVON) team
Contingency Engineer District (CED)
Reconnaissance Tasks - ✔✔Technical Reconnaissance (**General Engineers)
Infrastructure Survey
Environment Assessment
Airfield Assessment
Route Classification
Tactical Reconnaissance (**Combat Engineers)
Bridge Reconnaissance
Route Reconnaissance
Obstacle Reconnaissance
Reconnaissance vs. Classification - ✔✔Classification is done by General Engineers
COPYRIGHT © 2025 BY GRACE AMELIA, ALL RIGHTS RESERVED 1
, Reconnaissance is done by Combat Engineers
SWEAT-MSO - ✔✔Sewage
Water
Electricity
Academics
Trash
Medical
Safety
Other Considerations
MDMP and Construction Planning - ✔✔MDMP nests within construction planning and
EN requirements for sustainment
Project Origin/Routing - ✔✔Unit requests on a DA4283
Go to DPW for approval
Create list for troop construction requests
S3 syncs with DPW for project
Projects are picked and project packet are given; scope of work, site plan, and drawings
S3C produces construction directive, BOM, and Construct Activities
Project assigned to executing company
Definable Features of Work - ✔✔project supervisor identifies features of work during
estimating and scheduling process. "Task which is sperate and distinct from other tasks,
has separate control requirements, and may be identified by different trades or
disciplines, or it may be work by the same trade in a different environment"