CON 1400 Exam Study Questions and Answers
|Graded A+|Latest Update
The KO may specifically delegate ___ normal functions listed in FAR 42.302(a) & DFARS
242.302(a).
72
True or False. Authorize work outside the scope of the contract is one of the functions that
cannot be delegated by the PCO.
True
True or False. Some of the contractor's systems, business and technical, are crucial in the
overall goal for both the Seller (contractor) and buyer (Government).
False, All of the contractor's system are crucial
What are the types of Contract Deliverables?
- Supply Contract,
- Service Contract,
- Construction Contract
- Data/Report Deliverables
What are the 3 categories of acquisition in terms of impact of contract administration and
post award?
- Supplies
- Services
- Construction
What does NAICS stand for?
North American Classification System (NAICS)
, True or False. The SAM is an official website of the U.S. Government to hold information
relevant to procurement and financial transactions.
True
What is the key role of the Contracting Officer Representative?
- Observe,
- Document
- Communicate
True or False: Post-award is technically everything related to the contractual action that
occurs after the contract is awarded.
True
Is it always necessary to conduct a Post-Award Orientation?
No. It depends on the nature of the contract and intended performance.
What is the importance of a post-award orientation according to FAR 42.501?
- Aids both government and contractor achieve a clear and mutual understanding of contract
requirements.
- Identifies and resolves potential problems.
- Is not a substitute for contractors understanding work requirements during offer submission.
- Should not be used to alter the final agreement reached through negotiations
The KO may specifically delegate 72 normal functions listed in FAR 42.302(a), and may retain
any of the 72 functions except these three:
- Forward pricing rate agreements
- Final indirect rates and billing rates
- Adequacy of CAS disclosure statements
What are the functions that cannot be delegated by the PCO?
|Graded A+|Latest Update
The KO may specifically delegate ___ normal functions listed in FAR 42.302(a) & DFARS
242.302(a).
72
True or False. Authorize work outside the scope of the contract is one of the functions that
cannot be delegated by the PCO.
True
True or False. Some of the contractor's systems, business and technical, are crucial in the
overall goal for both the Seller (contractor) and buyer (Government).
False, All of the contractor's system are crucial
What are the types of Contract Deliverables?
- Supply Contract,
- Service Contract,
- Construction Contract
- Data/Report Deliverables
What are the 3 categories of acquisition in terms of impact of contract administration and
post award?
- Supplies
- Services
- Construction
What does NAICS stand for?
North American Classification System (NAICS)
, True or False. The SAM is an official website of the U.S. Government to hold information
relevant to procurement and financial transactions.
True
What is the key role of the Contracting Officer Representative?
- Observe,
- Document
- Communicate
True or False: Post-award is technically everything related to the contractual action that
occurs after the contract is awarded.
True
Is it always necessary to conduct a Post-Award Orientation?
No. It depends on the nature of the contract and intended performance.
What is the importance of a post-award orientation according to FAR 42.501?
- Aids both government and contractor achieve a clear and mutual understanding of contract
requirements.
- Identifies and resolves potential problems.
- Is not a substitute for contractors understanding work requirements during offer submission.
- Should not be used to alter the final agreement reached through negotiations
The KO may specifically delegate 72 normal functions listed in FAR 42.302(a), and may retain
any of the 72 functions except these three:
- Forward pricing rate agreements
- Final indirect rates and billing rates
- Adequacy of CAS disclosure statements
What are the functions that cannot be delegated by the PCO?