ARE 5.0 - PJM - Project Execution UPDATED ACTUAL Exam Questions and CORRECT Answers Best approach to meeting client expectations for construction budgets - CORRECT ANSWER - carefully monitor the relationship between scope, quality, and cost as a design is being developed When a conflict, sit with the client and review and adjust one or more of the project parameters of quality, time, and cost before proceeding to the next step in the design process To stay on top of issue, budget compliance & adjustment problems added to mtg agendas and discussed regularly w client and proj team

Show more Read less
Institution
ARE 5.0
Module
ARE 5.0










Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
ARE 5.0
Module
ARE 5.0

Document information

Uploaded on
January 30, 2025
Number of pages
25
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

ARE 5.0 - PJM - Project Execution
UPDATED ACTUAL Exam Questions and
CORRECT Answers
Best approach to meeting client expectations for construction budgets - CORRECT
ANSWER - carefully monitor the relationship between scope, quality, and cost as a design is
being developed
When a conflict, sit with the client and review and adjust one or more of the project parameters
of quality, time, and cost before proceeding to the next step in the design process
To stay on top of issue, budget compliance & adjustment problems added to mtg agendas and
discussed regularly w client and proj team


Challenges of managing consultants that PM must allot time and resources for - CORRECT
ANSWER - Consultant coordination
1. Reaching finish line at the same time and avoiding disruption when docs are issued
2. Making sure all parties using same versions of plan backgrounds
3. Uncovering and coordinating conflicts bet work of diff disciplines


Quality management responsibilities of PM - CORRECT ANSWER - PM to manage and
control project's quality level
Must be a daily concern
Redlines
Helping w specs and dwgs
Most of all, know the status of work at all times
Oversee and direct quality management controls as they are performed


PM responsibilities for Document Reviews - CORRECT ANSWER - Doc reviews as
opportunity to find uncover mistakes before they create problems during construction
Schedule time/resources for internal reviews of CDs before bidding
Reviewer could be PM, leader from another proj, or spec writer

,External reviews also helpful and should be welcomed (engineers, consultants, owners,
constractors, agencies that give permits.)


Managing expectations of client tips - CORRECT ANSWER - Help client set expectations
Have frank discussion of potentially tough issues
Use technique of creative conflict (process of engaging in debate to be able to recall issues later
on to gain concensus. Do this when change is requested, not after. Even is architect overruled,
owner will remember concerns were expressed)
Dont use jargon that is "undefined" or absolute by client or might be setting unreslistic
expectations ("our docs are %100 complete)


Suitable alternative for
"We look forward to designing a first-class new school for you."


"100% Complete Construction Documents"


"50% Schematic Design Set"


The masonry walls have been completed." - CORRECT ANSWER - We look forward to
designing your new school project.


Issued for Construction"


"Interim Schematic Review Set"


"The masonry walls appear complete."


Explaining consequences as a responsibility of PM - CORRECT ANSWER - For example, if
a client decides to eliminate waterproofing on the basement walls, it is not enough for the
architect to simply disagree with the decision. The project manager should go a step further and
explain that the decision could result in water leaking into the basement, causing damaged

, finishes and expensive repair costs. While such consequences may seem obvious to the
experienced project manager, they might not be so obvious to the owner.


Client wanting to save money on building system. Architect to explain increase of cost of
building maintenance


Monitoring tips for PM - CORRECT ANSWER - Most projects require a montly evaluation



Monitoring terms - CORRECT ANSWER - Net service revenue
Planned cost
Job-to-date
Estimate-to-complete
Estimate-at-completion
Planned estimate at completion
Percent complete
Multipliers (break even, overhead, effective multiplier, target, planned multiplier, estimate at
completion multiplier)
Billed/invoiced amounts
Earned revenue amounts
Billed-not-earned
Earned-not-billed


Net service revenue - CORRECT ANSWER - Net fee determined by subtracting consultant
fees from the gross fee for the project


Planned cost: - CORRECT ANSWER - Labor hours and dollar amounts planned at project
initiation


Job-to-date (JTD): - CORRECT ANSWER - Labor hours and dollar amounts spent as of
current date
£8.88
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached


Also available in package deal

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
MGRADES Stanford University
Follow You need to be logged in order to follow users or courses
Sold
1053
Member since
1 year
Number of followers
100
Documents
68976
Last sold
2 hours ago
MGRADES (Stanford Top Brains)

Welcome to MGRADES Exams, practices and Study materials Just think of me as the plug you will refer to your friends Me and my team will always make sure you get the best value from the exams markets. I offer the best study and exam materials for a wide range of courses and units. Make your study sessions more efficient and effective. Dive in and discover all you need to excel in your academic journey!

3.8

166 reviews

5
72
4
30
3
42
2
8
1
14

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Frequently asked questions