100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

PMP Exam Prep Practice Test evaluate your skills on the latest project management practices

Rating
-
Sold
-
Pages
94
Grade
A+
Uploaded on
06-12-2024
Written in
2024/2025

1. Rather than using Triangular Distribution while doing Three Point Estimation, you choose to use Beta Distribution. Based on your analysis and understanding, you are confident that the project would be completed with a total cost of $108,000. You also estimate that a best case would be $90000, while a worst-case scenario would result in the costs incurred to shoot up to $138000. What would the Three Point Cost estimate be when using Beta Distribution?

Show more Read less
Institution
PMP Prep Practice
Module
PMP Prep Practice











Whoops! We can’t load your doc right now. Try again or contact support.

Connected book

Written for

Institution
PMP Prep Practice
Module
PMP Prep Practice

Document information

Uploaded on
December 6, 2024
Number of pages
94
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

Free PMP® Exam Prep Practice Test
Have you been abreast with the latest changes in the project management practices updated in the PMBOK guide - 6th
edition? If yes, here’s a chance to test your knowledge. Simplilearn’s free PMP mock exam 6th edition is a great way to
evaluate your skills on the latest project management practices. This PMP exam contains free PMP 6th edition exam
questions that are similar to the questions that you can encounter in the PMP certification exam. In an attempt to help
you clear the certification exam in the first try, the PMBOK test is a great stepping stone for the all important PMP
certification exam. So, why wait? Take the free PMP practice exam 6th edition for free!

200 Questions, 240 Minutes



Related course
PMP® Certification

The PMP certification is the global gold standard for project management professionals. Keep abreast of the changes in the
project manag ...


GET 20% DISCOUNT
GO TO COURSE
coupon will be auto applied.




Explanations

200 124 62
Questions Correct Answers %Correct Answers




1. Rather than using Triangular Distribution while doing Three Point Estimation, you
choose to use Beta Distribution. Based on your analysis and understanding, you are
confident that the project would be completed with a total cost of $108,000. You also
estimate that a best case would be $90000, while a worst-case scenario would result in
the costs incurred to shoot up to $138000. What would the Three Point Cost estimate
be when using Beta Distribution?


112000


110000


101000


None of the above

,Explanation:

The question states that you should do Three Point Estimation using Beta Distribution. The formula for this
estimation technique is 4a + b + c / 6, where a = Most Likely Estimate, b = Estimate based on Best-case scenario,
and c = Estimate
Callbased
Us on Worst-case scenario. So, the Three
Chat Point Estimate using Beta distribution is (4
Query?
*108000) + 90000 + = 660000/6 = $ 110000.




2. John is managing a project. The project is about three-fourths done when the site
engineer reports that due to inherent complexities in a certain task, the deliverables
would get delayed. This would involve additional analysis and then implementation. He
requests that this new work, which was not envisioned earlier, be added to the scope
and also the time required be added to the schedule. You and the site engineer have
analyzed the impact of this change to cost and have written up a change request and
requested approval from change control board. Just today, you have received approval
from the change control board. What should be the immediate course of action?


Start work immediately


Ascertain the impact of this change to scope, schedule, and cost before making any change


Perform Quality Assurance


Make sure that the scope baseline and schedule baseline are updated to reflect the approved change before
implementing the change




Explanation:

As the change has been approved, you should always update the baseline (in this case, the scope and schedule
baseline) before implementing the change. This will ensure that you track performance against the new scope
and schedule, and not against the old benchmarks.




3. You are in charge of managing a software development project that is related to
simulations for driving racing cars. In one of your team meetings, it is revealed that a lot
of issues have been reported in the air tunnel modelling module. On deeper analysis, it
is found that many of the issues could have been prevented had a simple code review
checklist been used. You prepare a code review checklist and ensure the code is
reviewed per the checklist. This is a good example of:


Corrective Action


Preventive Action


Defect Repair

, Quality Control




Explanation:

This question is meant
Call Us to test your understanding of the difference
Chat between corrective action andQuery?
preventive
action. Defect repair might sound tempting, but it is only applicable for the issues found in the current delivery.
This is also not about Quality Control, so that leaves you with only two options: Corrective or Preventive actions.
Corrective actions are always preceded by nonconformity, while preventive actions are never preceded by
nonconformity. In this case, nonconformity in the form of a lot of issues during Quality Assurance were reported.
The root cause was identified to be the need of a standard checklist which was later used. Preventive action is
always taken proactively. In the question stated there is no demonstration of any proactive steps taken and hence
this is not an example of Preventive action.




4. You have replaced an earlier project manager in a project .The earlier project
manager has left the organization and you are now responsible for the project. On
reviewing the project management plan you are disturbed because a number of
procurement contracts have been signed off and they all turn out to be Cost plus fixed
fee types of contracts. Why are you worried?


All the risk is now with the seller


Contracts should always be T and M


Seller has no motivation to control cost and cost could spiral


Contracts should always be Fixed Price




Explanation:

As a project manager, you indeed have a reason to be worried if your project has already been signed off on Cost
Plus Fee type of contracts. In such contracts, you, the buyer, needs to pay the seller for all the costs and also an
agreed percentage of the cost. As a result, there is no motivation on the seller to control the costs; in fact, it is in
the interest of the seller to increase the costs. It is not necessary that all projects should always be T and M or
Fixed Price. Option A is clearly wrong since all the risks are, in fact, with the buyer and not the seller.




5. Your team is in its second month of development. You are managing a software
development project for a banking product. In one of the team meetings, a debate
arises if defects found during Quality control need to undergo change control. Some
team members are convinced that all defects should undergo change control, while the
others are convinced that defects need not undergo change control. Which of the
following statements are untrue?


Defects to deliverables need to undergo change control

, Defects to deliverables need not undergo change control


Corrective actions need to undergo change control


Preventive actions need to undergo change control
Call Us Chat Query?



Explanation:

Defects to deliverables, corrective actions, and preventive actions need to undergo change control. So all the
above statements are true except option B.




6. You are responsible for managing a project that deals with laying out a freeway
connecting two major port cities. Progress on the project has been smooth, and you
and your team are very confident on completing the project well within the stipulated
timelines. On reviewing, you see that the project has also run below the budget,
resulting in savings. You decide to add an extra feature of reflector strips on the road
every mile. You do a quick calculation and are satisfied that neither budget nor
schedule will slip. You feel that by adding these extra features you could also bag some
future projects. This is an example of:


Scope Creep


Gold Plating


Integrated Change Control


Fast Tracking




Explanation:

This is an example of Gold Plating. Integrated change control deals with formally approving or rejecting changes
before they are implemented, so it is not the correct answer. Fast tracking is a schedule compression technique,
so it too is not the correct answer. While Scope Creep is related to change in scope, it is related to uncontrolled
changes in product or projects scope and is often due to client interference. Gold plating is done intentionally or
knowingly for some strategic purpose. Here, the manager believes that by adding the extra features, future
projects could be bagged.

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Exammate Indiana University Of Pennsylvania
Follow You need to be logged in order to follow users or courses
Sold
51
Member since
4 year
Number of followers
8
Documents
3202
Last sold
6 hours ago
The plug

You cannot simultaneously prevent and prepare for war. Albert Einstein We'd love to hear how satisfied you are with your order. Please take a moment to leave a review, Thank you.

2.4

5 reviews

5
1
4
0
3
1
2
1
1
2

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Frequently asked questions